FOA CFOS/DAS flashcards
FOA CFOS/DAS · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Link loss budget
- The maximum allowable optical loss between transmitter and receiver, equal to transmitter output power minus receiver sensitivity. Design losses plus margin must stay below this figure.
- Receiver sensitivity
- The minimum optical power at which a receiver achieves its specified bit error rate, usually expressed in dBm. It sets the lower limit of the link loss budget.
- Design margin
- Extra loss allowance, typically at least 3 dB, added to calculated link loss to cover aging, repairs, temperature effects, and future splices.
- Modal dispersion
- Pulse spreading in multimode fiber caused by different modes traveling different path lengths. It limits bandwidth and distance, especially at 850 nm with older fiber grades.
- OM4 fiber
- Laser-optimized 50/125 µm multimode fiber with high bandwidth. It supports 10GBASE-SR to roughly 400 m and is common in data-center and building backbones.
- OS2 fiber
- Single-mode 9/125 µm fiber with low attenuation at 1310 and 1550 nm. It is used for campus, metro, and long-reach links beyond multimode distance limits.
- Connector loss allowance
- The dB budgeted per mated connector pair in a loss calculation. Common design values are 0.5 dB for field-terminated and 0.3 dB for factory connectors.
- Splice loss allowance
- The dB budgeted per fusion splice in a loss calculation, typically 0.1 to 0.3 dB. Actual measured splice loss should be verified with OTDR testing.
- Bend radius rule
- Minimum cable bend is about 10× outside diameter under load and 20× when pulling. Tighter bends cause loss and long-term fiber damage.
- Polarity method A
- A duplex patch cord wiring scheme where the transmit position at one end maps to the receive position at the other, using straight-wired cords and keyed adapters.
- Polarity method B
- A duplex wiring scheme using a crossover patch cord at one end so transmit pairs align with receive pairs across the link. Method must stay consistent end to end.
- 10GBASE-LR reach
- A single-mode 1310 nm Ethernet standard with roughly 10 km reach. Actual distance depends on the transceiver link budget, splice count, and connector losses.
- Attenuation coefficient
- Fiber loss per unit length in dB/km at a given wavelength. It drives total span loss and is multiplied by route length in the loss budget.
- Optical return loss
- The ratio of reflected to incident power at an interface, in dB. Poor return loss from bad connectors or tight bends degrades transmitter performance and link stability.
- Route diversity
- Design practice of providing physically separate cable paths so a single cut or disaster cannot disable both links. It is a reliability requirement in critical networks.
- Work breakdown structure
- A hierarchical decomposition of project scope into manageable deliverables. Each task in the schedule should map to exactly one WBS element.
- Critical path
- The longest chain of dependent tasks through the schedule network. It has zero float, so any delay on it delays project completion.
- Float (slack)
- The amount of time a task can slip without delaying the project finish. It equals late start minus early start, or late finish minus early finish.
- Cost variance (CV)
- Earned value minus actual cost. A negative CV means the project has spent more than the value earned to date.
- Schedule variance (SV)
- Earned value minus planned value. A negative SV means work is behind the planned schedule baseline.
- Cost performance index
- Earned value divided by actual cost. A CPI below 1.0 indicates cost overrun; above 1.0 indicates better-than-planned cost efficiency.
- Schedule performance index
- Earned value divided by planned value. An SPI below 1.0 indicates the project is behind schedule relative to the baseline.
- Estimate at completion
- Projected total cost, often calculated as actual cost plus estimate to complete. A common formula is EAC = BAC divided by CPI.
- Budget at completion
- The total approved budget for the project baseline. It is compared with earned value and actual cost to compute variance and performance indices.
- Risk register
- A log of identified risks with probability, impact, owner, and response strategy. Responses include avoid, mitigate, transfer, and accept.
- Change control board
- The group that reviews and approves or rejects scope, schedule, and cost changes. Approval updates the baseline before work proceeds.
- Cost of quality
- Total cost of prevention, appraisal, and failure. Prevention and appraisal spending usually reduces expensive rework and warranty failure costs.
- Punch list
- A documented list of incomplete or defective work items found at inspection. Closeout requires resolving each item before final acceptance.
- As-built drawings
- Final drawings reflecting actual installed routes, splice locations, and fiber assignments. They are a required closeout deliverable for acceptance and future maintenance.
- Acceptance testing
- Formal verification that installed links meet specified loss and OTDR criteria. Passing results trigger milestone payment and start of the warranty period.
- Procurement lead time
- The interval between ordering and receiving materials such as cable or transceivers. Long lead times are scheduled early and tracked as schedule risk.
- Milestone
- A zero-duration schedule marker representing a significant event, such as test completion or owner acceptance. Milestones carry no work but anchor reporting.