FOA CFOS/DAS study materials
FOA CFOS/DAS study resources

FOA CFOS/DAS study plan

FOA CFOS/DAS · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Fiber Optic Network Design

  • Map the FOA CFOS/DAS domain-1 outline into a personal checklist of subtopics, marking each item as known, shaky, or unknown

  • Define optical power budget terms in your own words: launch power, connector loss, splice loss, fiber attenuation, margin, and receiver sensitivity

  • Compute three sample link power budgets by hand at 850 nm, 1310 nm, and 1550 nm using published attenuation values

  • Set up a formula sheet and unit-conversion reference (dB vs dBm, mW to dBm) that you will reuse all eight weeks

Your checkpoint

A dated one-page power-budget worksheet with three worked links and a subtopic checklist scored known/shaky/unknown

Week 2

Fiber Optic Network Design

  • Compare multimode and single-mode fiber types by core size, bandwidth, and typical reach, and justify a choice for three described campus scenarios

  • Calculate bandwidth-distance limits and modal dispersion effects for a given multimode link length

  • Select connector and splice types for indoor, outdoor, and high-density environments, stating one tradeoff for each choice

  • Sketch two physical topologies (star and ring) and annotate where redundancy and failure points sit

Your checkpoint

A two-page design memo recommending fiber type, connectors, and topology for three distinct scenarios with numeric justification

Week 3

Fiber Optic Network Design

  • Explain how link-loss budgets feed into standards-based reach limits and where margin is deliberately reserved

  • Size a cable plant for a described building, estimating sheath counts, spare fibers, and pathway capacity

  • Identify documentation a designer must produce: loss budget, route map, fiber assignment chart, and as-built records

  • Distinguish design constraints that come from codes, environment, and customer requirements, and note how each changes the budget

Your checkpoint

A complete design package for one fictional building: loss budget, fiber assignment chart, and route sketch with spare-fiber rationale

Week 4

Fiber Optic Network Design & Project Planning and Management

  • Review your week 1-3 deliverables and close every subtopic still marked shaky or unknown

  • Draft a work breakdown structure for a fiber installation project, decomposing to tasks of one day or less

  • Sequence WBS tasks into a dependency network and identify the critical path

  • Estimate labor hours per task using a stated productivity assumption and flag the riskiest estimate

Your checkpoint

A WBS with dependency network and critical path for a 40-fiber campus link, plus a one-paragraph risk note

Week 5

Project Planning and Management

  • Build a project schedule with durations, milestones, and float, then identify which delays consume float versus move the end date

  • Define acceptance-testing criteria (insertion loss, ORL, length) and write them as pass/fail clauses

  • Plan a testing and commissioning sequence that respects when splicing, termination, and certification can occur

  • List safety and permit requirements that gate the schedule and state the lead time for each

Your checkpoint

A one-page schedule with milestones, float values, and a pass/fail acceptance-test clause set

Week 6

Project Planning and Management

  • Write a communication plan naming stakeholders, reporting cadence, and escalation triggers

  • Describe how to handle a change order: who approves, what gets re-baselined, and how cost and schedule impact is documented

  • Identify the records a project manager must collect for handover and explain why each matters to the owner

  • Practice a short verbal status update covering scope, schedule, cost, and risk in under two minutes

Your checkpoint

A stakeholder communication plan plus a change-order template with fields for cost, schedule, and approval

Week 7

Fiber Optic Network Design & Project Planning and Management

  • Re-derive two power budgets from memory and check them against your week 1 worksheet

  • Walk through a full project scenario end to end, from requirements to design to schedule to handover, noting where the two domains interact

  • Build a 30-question self-test mixing design calculations and project-management judgment calls, then score it

  • Revisit every item you missed and write the corrected reasoning in one sentence each

Your checkpoint

A scored 30-question self-test with one-sentence corrections for every miss

Week 8

Fiber Optic Network Design & Project Planning and Management

  • Condense both domains into a single review sheet of formulas, standards references, and decision rules

  • Complete two timed practice sets under exam conditions and record your pacing

  • Target your two weakest subtopics with focused re-study and re-test them

  • Restate the ten concepts you are least confident about and confirm each against a reliable source

Your checkpoint

A final one-page review sheet plus timed practice scores showing improvement over the week

Milestones

Week 2: You can compute a link power budget unaided and defend a fiber-type choice with numbers

Week 4: Domain 1 design package is complete and every checklist item is marked known or resolved

Week 6: You can produce a schedule with critical path and a pass/fail acceptance clause without notes

Week 8: Timed practice scores are stable and rising, and no subtopic remains marked unknown