Aerial ADSS Span Clearance and Hardware Selection

FOA CFOS/O · Put your knowledge to work in context.

All case studies

Aerial ADSS Span Clearance and Hardware Selection

A utility plans a 300 m aerial span of 48-fiber ADSS cable across a two-lane road. The existing pole is 11 m tall; the proposed attachment is at 9.0 m. Calculated sag at maximum ice (12 mm) and wind (80 km/h) is 5.8 m. The road surface at midspan is 0.2 m below the pole base. NESC requires 5.5 m clearance over the road. The area has a 25 kV distribution line on the same pole line, and the utility wants to use standard suspension clamps with armor rods at both ends. Cable OD is 14 mm, weight 0.22 kg/m, rated tension 12 kN, and the hardware has a 10 kN ultimate strength. The route has one 25° line angle at the crossing pole.

1. Calculate the midspan clearance and determine whether the design meets the 5.5 m requirement.

Read the worked answer

Midspan height above pole base = attachment height − sag = 9.0 − 5.8 = 3.2 m. The road is 0.2 m below the pole base, so clearance above the road = 3.2 + 0.2 = 3.4 m. The requirement is 5.5 m, so the design fails by 2.1 m. The calculation must use maximum ice and wind sag, not initial stringing sag. A design that looks adequate at installation can fail under the required load case.

2. What cable and hardware issues matter for ADSS near a 25 kV line and at a 25° line angle?

Read the worked answer

Near a 25 kV line, use ADSS with a track-resistant sheath and verify the electric-field condition at the attachment; hardware should be dielectric or properly bonded per the utility's practice. At a 25° line angle, a single suspension clamp imposes side load and bending; use double suspension or a dead-end/guy arrangement. Armor rods protect the cable but do not increase the cable's tensile rating. The hardware ultimate strength of 10 kN is below the cable rating of 12 kN, so the hardware is the weak link; check NESC safety factors and use hardware rated above the maximum tension. Confirm daily and short-term tension limits.

3. Propose two viable design changes and state a trade-off for each.

Read the worked answer

Change 1: raise the attachment or use a taller pole to gain at least 2.1 m clearance. Trade-off: higher cost, possible permits, and more wind load on the pole. Change 2: shorten the span with an intermediate pole to reduce sag. Trade-off: additional pole and hardware, another line angle, and more construction time. A third option is to increase tension within cable and hardware limits with a guyed dead-end, but that raises ice and wind loads. The clearance calculation must be redone for the chosen design at maximum ice and wind.