GAQM APM flashcards
GAQM APM · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Project definition
- A temporary endeavor undertaken to create a unique product, service, or result. Temporary means it has a defined beginning and end, not that the duration is short.
- Program vs portfolio
- A program is a group of related projects managed together for synergistic benefit. A portfolio is the collection of programs, projects, and operations selected to meet strategic objectives.
- Triple constraint
- The interdependent constraints of scope, time, and cost, with quality and risk as balancing factors. Changing one constraint typically forces a compensating change in another.
- Phase gate
- A decision point at the end of a project phase where the sponsor or governance body decides to continue, revise, or terminate the project before the next phase begins.
- Projectized organization
- An organizational structure in which the project manager has high authority and near-total control of project resources; team members report to the project manager rather than a functional manager.
- Project management office
- An organizational unit that standardizes project governance. It may be supportive (templates, training), controlling (methodology compliance), or directive (project managers report to it directly).
- Project charter
- A document issued by the sponsor that formally authorizes the project and names the project manager. It contains high-level scope, objectives, success criteria, milestones, and budget summary.
- Business case
- A document justifying the project through cost-benefit analysis, strategic alignment, and expected outcomes. It supports the decision to invest and precedes or accompanies the charter.
- Stakeholder register
- A living document recording each stakeholder's identification, role, interest, influence, expectations, and classification, used to plan engagement and communication throughout the project.
- Requirements traceability matrix
- A table linking each requirement to its source and to the corresponding WBS element, deliverable, and test, confirming that all requirements are covered and nothing extra is added.
- Project scope statement
- A document describing product scope, deliverables, acceptance criteria, exclusions, constraints, and assumptions. Explicit exclusions help prevent uncontrolled scope expansion during execution.
- Work breakdown structure
- A hierarchical decomposition of total project scope into work packages. The 100% rule requires the WBS to include all required work and only that work.
- Scope baseline
- The approved project scope statement plus the WBS and WBS dictionary. It is the reference used to measure and control scope changes and performance.
- Critical path
- The longest path through the schedule network. It determines the shortest possible project duration, and activities on it have zero or minimum total float.
- Total float formula
- Total float equals late start minus early start, or late finish minus early finish. Free float equals the successor's early start minus the activity's early finish.
- Forward and backward pass
- The forward pass computes early start and early finish dates; the backward pass computes late start and late finish. Their difference defines float and identifies the critical path.
- PERT expected duration
- A weighted three-point estimate: expected duration equals (optimistic + 4 times most likely + pessimistic) divided by 6. Standard deviation equals (pessimistic minus optimistic) divided by 6.
- Crashing
- Schedule compression by adding resources or cost to shorten duration. It is effective only on critical path activities and usually increases cost and risk.
- Fast tracking
- Schedule compression by overlapping activities that were planned sequentially. It shortens duration but increases the risk of rework and coordination problems.
- Resource leveling
- Adjusting activity start and finish dates to resolve resource over-allocation. It may extend the project duration and can change the critical path.
- Cost baseline
- The approved, time-phased project budget excluding management reserve. Contingency reserve for identified risks is included; management reserve for unidentified risks is not.
- Earned value formulas
- Cost variance equals EV minus AC; schedule variance equals EV minus PV; cost performance index equals EV divided by AC; schedule performance index equals EV divided by PV.
- Estimate at completion
- Forecast total cost. With atypical variance, EAC equals AC plus BAC minus EV. With typical variance continuing, EAC equals BAC divided by CPI.
- To-complete performance index
- TCPI equals (BAC minus EV) divided by (BAC minus AC) to meet the original budget, or divided by (EAC minus AC) when the forecast EAC replaces BAC.
- Integrated change control
- A process that documents each change request, assesses its impact on scope, schedule, cost, quality, and risk, obtains approval or rejection, then implements and verifies the change.
- Scope creep
- Uncontrolled expansion of project scope through unapproved additions. It differs from gold plating, which is adding unrequested features that also erode the scope baseline.
- Issue log vs risk register
- The issue log tracks current problems and their owners; the risk register tracks uncertain future events, their probability, impact, and planned responses. Both are updated during execution.
- Control quality
- The process of inspecting deliverables and recording results as verified deliverables. It focuses on detecting defects in outputs, unlike manage quality, which audits processes.
- Project closure activities
- Confirm deliverable acceptance and formal sign-off, release team resources, settle contracts, archive project documents, and update organizational process assets with final records.
- Lessons learned register
- A record of knowledge gained during the project, updated throughout execution and finalized at closure, then shared to improve future projects in the organization.
- Cost of quality
- The sum of conformance costs (prevention and appraisal) and nonconformance costs (internal and external failure). External failure is typically the most expensive category.
- Quality versus grade
- Grade is a category of technical characteristics; low grade may be acceptable if requirements are met. Low quality is never acceptable because requirements are not met.
- Pareto and fishbone
- A Pareto chart ranks causes by frequency to apply the 80/20 rule and prioritize the vital few. A fishbone (Ishikawa) diagram organizes possible causes by category for root-cause analysis.