GAQM APM study plan
GAQM APM · Give each week a clear focus.
8 weeks · About 6 hours per week
Project Management Fundamentals & Project Initiation and Scope Definition
Define project, program, and portfolio and state the distinguishing criterion for each in writing
Map the five process groups against the ten knowledge areas into a single grid you can reproduce from memory
Distinguish project life cycle from product life cycle using two worked examples of your own
Write a one-paragraph charter for a project you know, naming sponsor, purpose, and high-level constraints
Your checkpoint
A one-page process-group/knowledge-area grid plus a draft project charter paragraph, self-graded against a written checklist
Project Initiation and Scope Definition
Draft a stakeholder register with power/interest classification for at least eight stakeholders
Convert vague sponsor requests into three testable scope statements with explicit exclusions
Build a requirements traceability table linking five requirements to scope items and acceptance criteria
Explain in writing how scope creep differs from approved change control, with one example of each
Your checkpoint
A scope package: stakeholder register, scope statement with out-of-scope list, and a five-row requirements traceability table
Project Planning and Scheduling
Decompose a sample deliverable into a three-level work breakdown structure with a rule for the work-package level
Sequence at least twelve activities and identify the critical path by forward and backward pass
Calculate float for every non-critical activity and explain what negative float signals
Estimate duration and cost for five work packages using three-point estimating and note the assumptions
Your checkpoint
A network diagram with computed early/late dates, total float per activity, and an identified critical path
Project Planning and Scheduling & Project Execution and Control
Build a cost baseline by distributing the budget across the schedule and plot the resulting S-curve
Compute planned value, earned value, and actual cost at a chosen status date and derive CV, SV, CPI, and SPI
Interpret each index in plain language for a non-financial sponsor
List the control inputs and outputs that connect schedule and cost control to integrated change control
Your checkpoint
A one-page earned value status report with baseline, status date, four indices, and a plain-language interpretation
Project Execution and Control
Identify five risks for a sample project, score them on probability and impact, and assign a response strategy to each
Distinguish risk response strategies for threats from those for opportunities with one example each
Describe how issue logs, risk registers, and change requests differ in purpose and routing
Draft a change request form and the criteria a change control board would apply to approve or reject it
Your checkpoint
A risk register with five scored risks, chosen response strategies, owners, and a completed change request form
Project Execution and Control & Project Closure and Quality Management
Evaluate quality using cost of quality categories and classify four sample activities correctly
Distinguish quality assurance from quality control by naming the process group and primary output of each
Select appropriate quality tools for three scenarios and justify each choice
Write three acceptance criteria that are objective and testable rather than subjective
Your checkpoint
A quality plan excerpt containing cost-of-quality classification, chosen tools with justification, and three testable acceptance criteria
Project Closure and Quality Management
Sequence the closure activities for a project and state the purpose of each
Prepare a lessons-learned agenda that produces reusable organizational process assets
Explain the difference between administrative closure and contract closure with one scenario each
List the artifacts that must be archived and who receives final acceptance
Your checkpoint
A closure checklist covering acceptance, transition, contract closeout, archive, and lessons-learned capture
Project Management Fundamentals & Project Initiation and Scope Definition & Project Planning and Scheduling & Project Execution and Control & Project Closure and Quality Management
Answer 120 mixed practice questions under timed conditions and log every miss by domain
Re-study only the two weakest domains and rewrite the missed concepts in your own words
Recite the process-group grid, EVM formulas, and risk response strategies from memory without notes
Simulate a full-length timed set and review every error for root cause, not just the correct answer
Your checkpoint
A scored practice log showing per-domain accuracy before and after targeted review, with a written list of residual weak areas
Milestones
Week 2: Can write a scope statement with explicit exclusions and explain scope creep versus change control without notes
Week 4: Can compute CV, SV, CPI, and SPI from raw numbers and interpret each in one sentence
Week 6: Can distinguish quality assurance from quality control and classify cost-of-quality items correctly
Week 8: Scores at least 80 percent on a timed mixed set and can state the two remaining weak areas with a fix plan