ARC PPE study materials
ARC PPE study resources

ARC PPE flashcards

ARC PPE · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Break-even rate
Annual overhead divided by annual direct labor; the billing rate at which revenue covers overhead and direct labor with zero profit.
Utilization rate
Direct billable hours divided by total paid hours; measures staff efficiency and is typically 65–75% for architectural firms.
Critical path
The longest sequence of dependent activities in a project network; it has zero float and determines the minimum project duration.
Earned value CPI
Cost Performance Index = Earned Value divided by Actual Cost; a value below 1.0 indicates the project is over budget.
Net assignable area
Usable floor area assigned to specific functions, excluding circulation, mechanical, and structural spaces; used to compute building efficiency.
Adjacency matrix
A grid that weights the required proximity between pairs of spaces; used to test bubble diagrams and optimize floor plan layout.
Floor area ratio
Gross floor area divided by lot area; a zoning metric that limits building bulk relative to the site.
Occupancy classification
Building code grouping by use-such as A assembly, B business, E educational, R residential-that determines allowable height, area, and egress requirements.
CSI MasterFormat
A 50-division specification organization system; Division 01 covers general requirements, and later divisions address specific trades and materials.
Substantial completion
The stage when work is sufficiently complete for the owner's intended use; it starts warranties and the punch list period.
Rational method
Stormwater runoff formula Q = CiA, where C is the runoff coefficient, i is rainfall intensity, and A is drainage area.
Contour interval
The vertical elevation difference between adjacent contour lines; closer spacing indicates steeper terrain.
Cooling ton
A unit of cooling capacity equal to 12,000 BTU per hour; office spaces typically require 400–500 square feet per ton.
Fixture unit
A plumbing load metric where 1 fixture unit equals 1 gallon per minute; a water closet is 2.5 units and a lavatory is 1 unit.
Standard of care
The legal benchmark requiring an architect to perform with the reasonable skill and care of similar professionals under similar circumstances.
Mechanic's lien
A statutory claim allowing contractors or suppliers to file against a property for unpaid work or materials, potentially clouding title.
Overhead multiplier
A factor applied to direct labor to cover overhead and profit; typically ranges from 2.5 to 3.5 in architectural fee proposals.
Float
The amount of time an activity can be delayed without affecting the project completion date; calculated as late start minus early start.
Occupant load factor
The floor area per occupant used to calculate egress requirements; for example, 150 gross square feet per occupant for offices.
Egress width factor
The required exit width per occupant: 0.2 inches for stairs and 0.15 inches for other egress components such as corridors and doors.
Allowable area increase
A building code provision permitting larger floor area when the building has open frontage or is equipped with automatic sprinklers.
Accessible route width
The minimum clear width for an accessible path, typically 36 inches, with 60-inch turning spaces and a maximum slope of 1:12.
Door schedule
A construction document table listing each door's type, size, material, fire rating, and hardware group for coordination and procurement.
Stair riser and tread
Code limits for stairs: risers 4–7 inches high and treads at least 11 inches deep, with handrails 34–38 inches above the nosing.
Application for payment
A contractor's monthly request for payment based on completed work; the architect reviews and certifies the amount due.
Punch list
A documented list of incomplete or defective work items that the contractor must correct before final completion and final payment.
Cut and fill
Site grading process of removing soil from high areas and depositing it in low areas to achieve a balanced site with minimal hauling.
Setback
The required distance from a property line to a building, established by zoning to control light, air, and privacy.
Duct velocity method
HVAC duct sizing approach using target air velocities: supply trunks at 1000–1500 feet per minute and branches at 600–900 feet per minute.
Live load
The non-permanent load on a structure from occupants and movable objects; office floors typically require 50 pounds per square foot.
Architect's seal
The licensed architect's stamp on construction documents, certifying professional responsibility and compliance with state licensing laws.
Conflict of interest
A situation where an architect's financial or personal interest could compromise professional judgment; must be disclosed to the client.