HKIA/ARB PA Paper 3 · Keep the key ideas within reach.

Quick reference

Case Study

  • Case study answers are marked on structured analysis: identify the client's brief, statutory constraints, site conditions, and stakeholder interests before proposing options.

  • Hong Kong building plan approval sequence: AP/RSE submission to BA, BA response within 60 days (Buildings Ordinance s.16), then commencement after consent; any material amendment restarts the process.

  • For a case-study question on adaptive reuse, first establish the existing building's lease conditions, approved use, and structural capacity, because change of use may trigger a new plan submission under s.14 BO.

  • Occupant capacity for means of escape in a case study is derived from the MOE Code: calculate population from floor area divided by occupancy factor, then verify exit width at 5 mm per person and travel distance limits.

  • When a case study involves a slope or retaining structure, the Geotechnical Engineering Office's guidance and the Building (Construction) Regulations require a geotechnical assessment by a registered geotechnical engineer.

  • Heritage case studies: Grade 1/2/3 buildings are not statutorily protected until declared monuments under the Antiquities and Monuments Ordinance; adaptive reuse must respect the Antiquities Advisory Board's conservation principles.

  • A common case-study trap is ignoring the lease: even if planning permission is granted, a change of use may breach the Government lease and require a waiver or modification.

  • In a case study, distinguish 'permitted development' from 'planning permission': in Hong Kong, most building works still need BA approval even when planning permission is not required.

Quick reference

Professional Practice and Regulations

  • Buildings Ordinance (Cap. 123) s.4: building plans must be prepared by an Authorized Person (AP) and, for structural elements, a Registered Structural Engineer (RSE); supervision of works is by a Registered Contractor (RC).

  • AP/RSE/RC registration is administered by the Buildings Department under the Architects Registration Ordinance and Engineers Registration Ordinance; practising certificates are renewed annually.

  • Under the Architects Registration Ordinance (Cap. 408), the Architects Registration Board handles registration and discipline; 'architect' is a protected title.

  • Professional indemnity insurance is not mandatory for all APs but is commonly required by clients; the HKIA recommends adequate cover, and claims are typically time-barred after 6 years (contract) or 15 years (deed) in Hong Kong.

  • The Buildings Ordinance s.16(1) requires the Building Authority to approve or refuse plans within 60 days; deemed approval does not apply, so silence is not consent.

  • Occupation permit (OP) application: BA must be satisfied that works comply with approved plans and that essential services (fire, drainage, structural) are complete; a temporary occupation permit (TOP) may be granted for early occupation.

  • Under the Professional Code of Practice, an architect must not accept commissions where a conflict of interest exists without full disclosure; fee-cutting that compromises safety is a disciplinary matter.

  • Site supervision: the AP must visit the site at intervals appropriate to the stage of works; under the Site Supervision Plan, supervision frequency is specified by the BA depending on the complexity of the works.

Quick reference

Contract and Project Management

  • In Hong Kong, the HKIA Standard Form of Building Contract is commonly used; it operates on a lump-sum basis with provisional sums and a nominated sub-contractor mechanism.

  • Variation valuation under the HKIA form: work is valued at BOQ rates if applicable, otherwise at fair rates; dayworks apply only where agreed in advance.

  • Liquidated damages must be a genuine pre-estimate of loss, not a penalty; Hong Kong courts apply the Cavendish/Universe Tanks test.

  • Extension of time: the contractor must give notice within a specified period (often 28 days) of the delaying event; late notice can bar the claim under the contract.

  • Interim payments: the HKIA form requires the architect to certify payment within the stated period; non-payment may trigger suspension or termination rights.

  • Under the Construction Industry Council's guidelines, project management should include a risk register reviewed at design and construction stages; safety planning is a statutory duty under the Factories and Industrial Undertakings Ordinance.

  • The 'Security of Payment' provisions are not yet fully enacted in Hong Kong; parties rely on contractual adjudication or litigation, so contract drafting of payment terms is critical.

  • Programme analysis: use the critical path method; float ownership is typically assigned to the employer unless the contract states otherwise, affecting EOT entitlement.

Quick reference

Building Design and Technology

  • Means of escape: the MOE Code requires travel distance from any point to a protected exit not exceeding 30 m in sprinklered buildings (varies by occupancy); exit width is 5 mm per person.

  • Fire resistance period (FRP) for elements of construction is determined by building height and occupancy; typical requirements range from 60 to 240 minutes under the Code of Practice for Fire Safety in Buildings.

  • Barrier-free access: the Design Manual: Barrier Free Access 2008 requires accessible routes, ramps with a gradient not steeper than 1:12, and accessible toilets at specified intervals.

  • Structural design in Hong Kong follows the Code of Practice for the Structural Use of Concrete (and steel); wind loading is governed by the Code of Practice on Wind Effects, with a 50-year return period.

  • Energy efficiency: the Building (Energy Efficiency) Regulation and the Code of Practice for Overall Thermal Transfer Value (OTTV) set limits on OTTV for new buildings; compliance is demonstrated at plan submission.

  • Sustainable design: BEAM Plus is the voluntary green building assessment tool in Hong Kong; credits cover energy, water, materials, and indoor environmental quality.

  • Drainage: the Building (Standards of Sanitary Fitments, Plumbing, Drainage Works and Latrines) Regulations set minimum sanitary fitment numbers based on occupancy and use.

  • Natural lighting and ventilation: the Building (Planning) Regulations require prescribed window areas and open space; the Sustainable Building Design Guidelines further address building separation and permeability.