Mistake 1

Citing a statutory requirement by regulation number or section without stating the governing ordinance and its current amendment status, so the cited provision is either superseded or misapplied to the wrong building type.

Candidates memorise regulation numbers in isolation during revision and never practise tracing a requirement back to its parent ordinance, its scope of application, and any subsidiary legislation or code of practice that modifies it. Under exam pressure the number surfaces without its context.

What to do instead

Build a one-page map per ordinance (for example Buildings Ordinance and its subsidiary regulations, Fire Safety (Buildings) Ordinance, and the relevant design codes) showing what each instrument governs and which building classes it covers. In every practice answer, write the instrument name, the scope sentence, and the code of practice reference before the specific clause. Mark any clause you cannot verify from a current source as uncertain rather than asserting it.

Mistake 2

Answering a plan-submission or approval-process question with a single sequential list, omitting the parallel tracks, the statutory deemed-approval or deemed-refusal timeframes, and the point at which works may lawfully commence.

Candidates learn the submission stages as a narrative (submit, wait, approve, build) and never test it against scenarios where approval is deemed to have been given, where amendments are resubmitted mid-stream, or where separate consents are needed for different parts of the works.

What to do instead

Redraw the process as a flow with time bars written on each arrow and a separate lane for each consent type. For each stage, note what triggers the clock, what stops it, and what the applicant may do if no response arrives. Practise with three scenarios: a straightforward new building, a major amendment after approval, and a submission that is rejected on a technical ground.

Mistake 3

Treating means of escape as a single calculation of travel distance and exit width, ignoring the interaction with fire compartmentation, protected routes, and the assumption that lifts are unavailable during evacuation.

Revision notes present escape and compartmentation as separate chapters, so candidates answer each in isolation and never reconcile the trade-offs (for example, increased travel distance permitted where a protected route or sprinkler system is provided).

What to do instead

For each occupancy type, produce a table linking permitted travel distance, dead-end limit, exit capacity, and the compensatory features that relax them. Then answer past-style questions by explicitly stating the assumption set (occupant load, sprinkler provision, lift isolation) before the numbers, so the examiner sees the reasoning chain rather than an isolated figure.

Mistake 4

Describing fire resistance periods and compartment sizes by memory of a single table, without stating the building's purpose group, height, and whether a sprinkler or other active system is installed, which are the variables that set the requirement.

Candidates anchor on one familiar figure (for example a one-hour rating) and apply it universally, because revision summaries strip away the classification step that precedes the table lookup.

What to do instead

Practise classification first: given a building description, assign the purpose group and height class, then derive the fire resistance period and compartment limits from those inputs. Write the classification step explicitly in every answer. Where you are unsure of a numeric limit, state the method and the governing code, and flag the figure as needing verification rather than inventing it.

Mistake 5

Answering structural or geotechnical questions with qualitative reassurance ('adequate foundation', 'suitable support') instead of naming the design action, the limit state checked, and the acceptance criterion.

Candidates from a building-surveying or architectural background are less fluent in structural verification language and default to descriptive prose, which scores poorly against questions seeking a demonstrable check.

What to do instead

Adopt a fixed answer skeleton: load path, design action and combination, limit state (ultimate or serviceability), governing criterion (for example allowable settlement, crack width, factor of safety against sliding or overturning), and the consequence if exceeded. Rehearse this skeleton on foundation, retaining, and temporary works scenarios until it is automatic.

Mistake 6

Discussing site safety and construction methodology without identifying the specific statutory duty holder and the approval or notification step that precedes the activity (for example temporary works, excavation support, or works near a party boundary).

Candidates describe good practice generically because they have not linked construction activities to the permit, notification, or supervision requirements that attach to them, and they conflate the designer's and contractor's obligations.

What to do instead

For each high-risk activity, write a short card: who must approve or be notified, what evidence must exist before work starts, who supervises, and what triggers a stop. Include the temporary works coordinator concept and the distinction between the authorised person and the competent supervisor. Use these cards to structure answers so responsibilities are attributed, not merged.

Mistake 7

Handling an existing-building or alteration question as if it were new construction, ignoring the applicable regime for existing buildings, the concept of building safety measures, and the distinction between prescribed repair or improvement notices and voluntary works.

Most revision material centres on new development, so candidates transplant new-build standards onto existing structures and miss the enforcement pathway, the role of the authority's notice, and the appeal route.

What to do instead

Study the existing-buildings regime as a separate topic: what triggers a notice, what the owner must do and by when, how non-compliance is enforced, and where appeal lies. In answers, state the building's status first (new, existing, altered, change of use) and select the regime before applying technical standards.

Mistake 8

Writing answers that list correct facts but never state a conclusion or recommendation, leaving the examiner to infer whether the candidate would approve, reject, or require further information.

Candidates treat professional assessment as a knowledge recall test and do not realise that scenario questions are marked on professional judgement expressed as a defensible decision with reasons.

What to do instead

End every scenario answer with an explicit position: approve, approve subject to stated conditions, reject, or request specified further information. Give the reason by reference to the governing requirement, and state what evidence would change the decision. Practise writing the conclusion first, then building the justification to support it.

Mistake 9

Misallocating time: writing a long essay on the first question, then producing bullet fragments for later questions that carry equal or greater marks, and omitting the compulsory section entirely.

Candidates rehearse content but never rehearse the paper's structure and mark distribution, so they discover the compulsory or high-weight sections too late.

What to do instead

Before the exam, write down the section structure, mark allocation, and a minute budget per section, reserving time for the compulsory part and a review pass. In mocks, use a timer and stop writing when the budget expires, even mid-sentence, to build the discipline of moving on. Practise producing a complete short answer in the budgeted time rather than a perfect long one.

Mistake 10

Using vague professional vocabulary ('adequate', 'suitable', 'in accordance with the code') as the substance of an answer, without quantifying, citing the clause, or showing the check performed.

Candidates imitate the register of codes of practice, which use such words as outcomes of a defined process, without reproducing the process that gives them meaning.

What to do instead

Apply a substitution test to every draft answer: wherever 'adequate' or 'suitable' appears, replace it with the quantity, the criterion, and the source. If you cannot supply them, rewrite the sentence as an explicit assumption with the reason it is reasonable. Review past answers specifically hunting for these words and count how many survive.