Buildings Ordinance (BO)

The primary Hong Kong statute controlling the design, construction, alteration and demolition of buildings. It sets out duties of owners and contractors, approval procedures, and enforcement powers exercised by the Building Authority.

Related: Building Authority, Approved Plans and Consent to Commence Work
Building Authority (BA)

The statutory officer, currently the Director of Buildings, responsible for administering the Buildings Ordinance. The BA approves plans, issues permits and consents, inspects works, and may order rectification or demolition.

Related: Buildings Ordinance (BO), Occupation Permit
Approved Plans and Consent to Commence Work

Construction may only start after the Building Authority has approved the submitted plans and granted consent to commence building works. Working without either is an offence under the Ordinance.

Related: Buildings Ordinance (BO), Occupation Permit
Occupation Permit (OP)

A permit issued by the Building Authority allowing a newly completed building to be occupied. It confirms structural stability, fire safety, drainage and other prescribed requirements have been satisfactorily met.

Related: Temporary Occupation Permit, Certificate of Completion
Temporary Occupation Permit (TOP)

A time-limited permit allowing partial occupation before full completion, granted when the Building Authority is satisfied that the portion concerned is safe and essential works are finished.

Related: Occupation Permit (OP)
Authorized Person (AP)

A registered professional under the Buildings Ordinance who prepares and submits building plans and supervises building works on behalf of the owner. Registration requires prescribed qualifications and experience.

Related: Registered Structural Engineer (RSE), Registered Specialist Contractor (RSC)
Registered Structural Engineer (RSE)

A registered professional responsible for the structural design, calculations and supervision of building works requiring structural submission, and for certifying structural adequacy to the Building Authority.

Related: Authorized Person (AP), Structural Submission
Registered Specialist Contractor (RSC)

A contractor registered for a specific category of specialized works, such as foundation, demolition, site formation or ground investigation, and permitted to carry out only that category.

Related: Registered General Building Contractor (RGBC), Site Formation Works
Registered General Building Contractor (RGBC)

A contractor registered to carry out general building works and, where applicable, specialist works for which it holds registration. Registration depends on management, financial and technical competence.

Related: Registered Specialist Contractor (RSC)
Site Formation Works

Works that prepare land for construction, including excavation, filling, slope treatment and retaining structures. They are controlled as a specialist category under the Buildings Ordinance.

Related: Registered Specialist Contractor (RSC), Retaining Wall
Plot Ratio

The ratio of total gross floor area of a building to the area of the site on which it stands. It is a principal planning and lease control limiting development bulk.

Related: Site Coverage, Gross Floor Area
Site Coverage

The proportion of a site covered by the building footprint at ground level, expressed as a percentage. It controls open space and spacing between buildings and is often capped by lease or plan.

Related: Plot Ratio, Setback
Gross Floor Area (GFA)

The total floor area of all floors of a building measured to defined rules, including certain covered areas and excluding specified plant or open areas. It is the basis for plot ratio calculations.

Related: Plot Ratio, Site Coverage
Setback

The required horizontal distance between a building or its projections and a site boundary, street or adjoining building, imposed to provide light, ventilation, fire separation and street widening space.

Related: Site Coverage, Fire Compartment
Means of Escape (MOE)

The continuous route from any point in a building to a place of safety, comprising exit routes, protected corridors, staircases and discharge points sized to handle the occupant load.

Related: Means of Access, Fire Compartment, Occupant Capacity
Means of Access

The routes provided for firefighters and rescue personnel to reach a building and its firefighting facilities, including access roads, hardstanding and firefighting shafts or lobbies.

Related: Means of Escape (MOE), Fire Compartment
Fire Compartment

A space enclosed by fire-resisting construction that limits the spread of fire and smoke to a defined area for a specified period, allowing occupants to escape and firefighters to operate.

Related: Fire Resistance Rating (FRR), Means of Escape (MOE)
Fire Resistance Rating (FRR)

The period, in minutes, for which a building element resists fire in a standard test, expressed for stability, integrity and insulation. Required ratings depend on element type and building use.

Related: Fire Compartment, Fire Stop
Occupant Capacity

The maximum number of persons a space or building is designed to hold, derived from floor area and use factors. It determines egress widths, staircase numbers and exit capacity.

Related: Means of Escape (MOE)
Fire Stop

A seal or barrier installed to close openings and gaps in fire-resisting construction, such as where services penetrate walls or floors, to maintain the required fire resistance.

Related: Fire Resistance Rating (FRR), Fire Compartment
Structural Submission

The set of structural plans, calculations and supporting documents prepared by a Registered Structural Engineer and submitted to the Building Authority for approval before structural works proceed.

Related: Registered Structural Engineer (RSE), Approved Plans and Consent to Commence Work
Foundation Works

Substructure works transferring building loads to the ground, including piles, caissons and footings. They are a specialist category requiring qualified supervision and, often, staged approval.

Related: Pile Driving, Site Formation Works
Pile Driving

Installation of piles by driving, boring or other methods to support structures. It is controlled for structural adequacy, noise and vibration, and requires method statements and supervision.

Related: Foundation Works, Ground Investigation
Ground Investigation

Field and laboratory work to determine soil and rock conditions, groundwater levels and engineering properties at a site, providing the basis for foundation and excavation design.

Related: Foundation Works, Retaining Wall
Retaining Wall

A structure that resists lateral earth pressure to hold back soil at a change of level. Its design, construction and maintenance are controlled because failure can endanger adjacent land and buildings.

Related: Site Formation Works, Ground Investigation
Drainage Works

Construction of drains, sewers and associated facilities for foul sewage, surface water and groundwater. Approval and connection requirements protect public health and the drainage system.

Related: Approved Plans and Consent to Commence Work
Certificate of Completion

A certificate submitted by the Authorized Person and Registered Structural Engineer confirming that building works have been completed in accordance with approved plans, supporting the occupation permit application.

Related: Occupation Permit (OP), Authorized Person (AP)
Unauthorized Building Works (UBW)

Building works carried out without the required approval or consent, or contrary to approved plans. The Building Authority may issue removal or rectification orders and register them against the property.

Related: Building Order, Approved Plans and Consent to Commence Work
Building Order

A statutory notice issued by the Building Authority requiring an owner to rectify, remove or investigate defective or unauthorized works within a stated period, with rights of appeal.

Related: Unauthorized Building Works (UBW), Dangerous Building
Dangerous Building

A building or part that is structurally unsafe or otherwise hazardous, allowing the Building Authority to require remedial works, closure or demolition to protect occupants and the public.

Related: Building Order
Minor Works Control System

A simplified regime allowing specified small-scale building works to proceed under prescribed procedures with qualified personnel, instead of full plan approval, while retaining safety control.

Related: Unauthorized Building Works (UBW), Approved Plans and Consent to Commence Work
Barrier-Free Access

Design provisions enabling persons with disabilities to reach and use buildings independently, covering ramps, lifts, widths, gradients and signage under the relevant design requirements.

Related: Means of Escape (MOE)
Sustainable Building Design

Design approaches reducing energy use, waste and environmental impact, including building separation, setback, greenery and permeable surfaces, encouraged through the Buildings Ordinance framework.

Related: Setback, Site Coverage
Temporary Works

Structures or installations needed to construct permanent works, such as falsework, scaffolding and excavation support. They must be designed, erected and maintained to ensure safety.

Related: Falsework, Site Formation Works
Falsework

Temporary support structure carrying formwork and fresh concrete until it can support itself. It requires design, inspection and supervision because collapse can cause serious injury.

Related: Temporary Works
Code of Practice

Technical guidance issued under the Buildings Ordinance that sets out accepted standards and methods for complying with statutory requirements. Compliance is commonly treated as evidence of adequacy.

Related: Buildings Ordinance (BO), Fire Resistance Rating (FRR)
Site Supervision Plan

A document setting out supervision levels, personnel, frequencies and records for building works, required to demonstrate adequate control of quality and safety on site.

Related: Authorized Person (AP), Registered Structural Engineer (RSE)