HKIE Professional Assessment - Gas Discipline study plan
HKIE Professional Assessment - Gas Discipline · Give each week a clear focus.
8 weeks · About 7 hours per week
Gas supply systems and network design
Map the anatomy of a Hong Kong town gas transmission and distribution network from town gas plant through governor stations to district medium-pressure mains and service laterals, and label each tier on a one-page system sketch
Distinguish medium-density polyethylene (MDPE) and steel mains by operating pressure tier and justify material selection for each tier using pressure, corrosion and jointing arguments
Compute the pressure drop across a simple series main section using a standard flow-pressure relationship and state the assumed friction factor and roughness you used
Explain the role of district governors, district valve arrangements and network segmentation in maintaining supply continuity
Identify the design inputs you would request before sizing a new estate distribution main: peak demand, diversity, allowable pressure drop and future load
Your checkpoint
A one-page annotated network schematic plus a worked pressure-drop calculation for one synthetic main section, with stated assumptions.
Gas supply systems and network design & Gas installation design and pipework sizing
Size a low-pressure service pipe and internal riser run for a multi-storey residential building using an equivalent-length method and tabulated sizing data, documenting every assumption
Apply diversity and simultaneous-demand factors to a domestic and a commercial load profile and show how the chosen factor changes the pipe size
Compare allowable pressure loss criteria for upstream of the meter and downstream of the meter and explain why the downstream allowance is tighter
Select and justify meter type, meter position and isolation arrangement for a residential and a commercial case
Critique a given (synthetic) riser layout for accessibility, compartmentation and future maintenance access
Your checkpoint
A pipe-sizing calculation sheet for one synthetic 12-storey residential riser, showing loads, diversity factors, equivalent lengths, selected diameters and pressure check.
Gas properties, combustion and utilisation & Ventilation, flueing and indoor air quality
State the composition ranges and key properties of town gas, natural gas, LPG vapour and LNG-derived gas, and explain how Wobbe number governs interchangeability
Calculate stoichiometric air requirement and theoretical CO2 and water vapour yield for methane and for a representative LPG mixture, showing each step
Explain flame stability, lift-off, light-back and incomplete combustion in terms of aeration, port loading and burner design
Diagnose three combustion-fault scenarios from flue gas readings (CO, CO2, excess air, flue temperature) and state the corrective action for each
Relate combustion air requirement, dilution and flue dilution to ventilation rate and room air-change criteria for an appliance in an internal space
Your checkpoint
A combustion calculation and fault-diagnosis table covering three appliance scenarios with readings, diagnosis and corrective action.
Ventilation, flueing and indoor air quality & Gas safety, hazard and risk management
Design a ventilation strategy for an internal commercial kitchen and for a residential open-flue appliance, sizing openings against appliance rating and dilution needs
Trace a flue route through a building and identify every point where flue terminal position, recirculation, building overhang or adjacent opening creates a hazard
Build a hazard register for a gas installation using a recognised risk-scoring approach, scoring likelihood and consequence explicitly
Apply the hierarchy of control to gas leak, fire, explosion and carbon monoxide exposure scenarios and justify the chosen controls
Explain how gas detection, emergency isolation and interlock systems reduce risk, and state their failure modes
Your checkpoint
A risk register with at least eight identified hazards, scored likelihood and consequence, controls mapped to the hierarchy of control, and residual risk stated.
Gas safety, hazard and risk management & Codes, standards and regulatory framework (Hong Kong)
Assemble a personal index of the Hong Kong statutory and code framework relevant to gas installations, noting for each instrument the scope, the duty holder and the type of obligation it imposes
Distinguish the roles of the gas supplier, the registered gas installer, the registered contractor and the authority in approval, commissioning and ongoing inspection
Map notification, approval and inspection stages for a new installation and for an alteration to an existing installation onto a single process timeline
Explain the legal and professional consequences of working outside registration or competence, and the reporting duty when an unsafe installation is found
Identify which code clauses you would cite to justify a refusal to commission an installation, and record the citation format you would use
Your checkpoint
A two-page regulatory map: instrument, scope, duty holder, obligation type, plus a process timeline from design approval to periodic inspection.
LPG and LNG installations and bulk storage & Commissioning, testing, inspection and maintenance
Compare bulk LPG storage options (underground, above-ground, mounded) on separation distance, bunding, fire protection and access, and select one for a constrained urban site with justification
Describe the LNG receiving, storage, vaporisation and send-out chain and identify the safety systems that protect each stage
Write a commissioning sequence for a new installation from purging and pressure testing through strength test, tightness test, appliance commissioning and handover
Specify the test medium, test pressure, hold duration and acceptance criterion for a strength test and a tightness test, and explain why the two differ
Build a preventive maintenance schedule for a commercial installation covering appliance, flue, controls, emergency devices and documentation
Your checkpoint
A commissioning and handover checklist plus a 12-month preventive maintenance schedule for one synthetic commercial installation.
Professional practice, ethics and project management & Energy efficiency, environment and emerging low-carbon gases
Prepare a written response to a client who insists on a cheaper, non-compliant pipe route, stating the technical basis, the risk and the professional position without personalising the conflict
Identify the ethical duties triggered when you discover another party's non-compliant work during commissioning, and set out the escalation sequence
Structure a project programme for a gas installation using defined work packages, dependencies, hold points and inspection sign-offs
Evaluate hydrogen blending, biomethane injection and electrified heating against gas network decarbonisation goals, stating one technical constraint and one infrastructure implication for each
Quantify the energy and emissions benefit of a condensing appliance or a heat-recovery measure using a simple before-and-after calculation
Your checkpoint
A one-page professional-practice case note (ethical dilemma, position, escalation) plus a short low-carbon options comparison table with one quantified efficiency or emissions estimate.
Gas supply systems and network design & Gas installation design and pipework sizing & Gas safety, hazard and risk management & Codes, standards and regulatory framework (Hong Kong)
Re-derive the network pressure-drop and pipe-sizing calculations from memory under time pressure and check the answers against your week 1 and week 2 sheets
Re-score the week 4 risk register with fresh eyes and justify any changed scores
Answer timed mixed-domain questions spanning network design, sizing, safety and regulation, then classify every error as knowledge gap, misreading or calculation slip
Recite the regulatory map from week 5 without notes and correct any drift in duty holder or obligation
Write a 10-point pre-exam checklist covering assumptions to state, units to confirm and common traps to avoid
Your checkpoint
A timed mock paper score sheet with error classification and a personal 10-point pre-exam checklist.
Milestones
Week 2: You can size a service and riser run unaided, state every assumption, and defend the diversity factor you chose.
Week 4: You can diagnose a combustion fault from flue gas readings and link it to a ventilation or flueing defect, and your risk register scores are defensible to a reviewer.
Week 6: You can write a full commissioning sequence and state the strength-test and tightness-test criteria without reference material.
Week 8: Timed mock score is stable across two attempts, every error is classified, and no error recurs from an earlier week.