HKIE Professional Assessment - Gas Discipline study materials
HKIE Professional Assessment - Gas Discipline study resources

HKIE Professional Assessment - Gas Discipline study plan

HKIE Professional Assessment - Gas Discipline · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Gas supply systems and network design

  • Map the anatomy of a Hong Kong town gas transmission and distribution network from town gas plant through governor stations to district medium-pressure mains and service laterals, and label each tier on a one-page system sketch

  • Distinguish medium-density polyethylene (MDPE) and steel mains by operating pressure tier and justify material selection for each tier using pressure, corrosion and jointing arguments

  • Compute the pressure drop across a simple series main section using a standard flow-pressure relationship and state the assumed friction factor and roughness you used

  • Explain the role of district governors, district valve arrangements and network segmentation in maintaining supply continuity

  • Identify the design inputs you would request before sizing a new estate distribution main: peak demand, diversity, allowable pressure drop and future load

Your checkpoint

A one-page annotated network schematic plus a worked pressure-drop calculation for one synthetic main section, with stated assumptions.

Week 2

Gas supply systems and network design & Gas installation design and pipework sizing

  • Size a low-pressure service pipe and internal riser run for a multi-storey residential building using an equivalent-length method and tabulated sizing data, documenting every assumption

  • Apply diversity and simultaneous-demand factors to a domestic and a commercial load profile and show how the chosen factor changes the pipe size

  • Compare allowable pressure loss criteria for upstream of the meter and downstream of the meter and explain why the downstream allowance is tighter

  • Select and justify meter type, meter position and isolation arrangement for a residential and a commercial case

  • Critique a given (synthetic) riser layout for accessibility, compartmentation and future maintenance access

Your checkpoint

A pipe-sizing calculation sheet for one synthetic 12-storey residential riser, showing loads, diversity factors, equivalent lengths, selected diameters and pressure check.

Week 3

Gas properties, combustion and utilisation & Ventilation, flueing and indoor air quality

  • State the composition ranges and key properties of town gas, natural gas, LPG vapour and LNG-derived gas, and explain how Wobbe number governs interchangeability

  • Calculate stoichiometric air requirement and theoretical CO2 and water vapour yield for methane and for a representative LPG mixture, showing each step

  • Explain flame stability, lift-off, light-back and incomplete combustion in terms of aeration, port loading and burner design

  • Diagnose three combustion-fault scenarios from flue gas readings (CO, CO2, excess air, flue temperature) and state the corrective action for each

  • Relate combustion air requirement, dilution and flue dilution to ventilation rate and room air-change criteria for an appliance in an internal space

Your checkpoint

A combustion calculation and fault-diagnosis table covering three appliance scenarios with readings, diagnosis and corrective action.

Week 4

Ventilation, flueing and indoor air quality & Gas safety, hazard and risk management

  • Design a ventilation strategy for an internal commercial kitchen and for a residential open-flue appliance, sizing openings against appliance rating and dilution needs

  • Trace a flue route through a building and identify every point where flue terminal position, recirculation, building overhang or adjacent opening creates a hazard

  • Build a hazard register for a gas installation using a recognised risk-scoring approach, scoring likelihood and consequence explicitly

  • Apply the hierarchy of control to gas leak, fire, explosion and carbon monoxide exposure scenarios and justify the chosen controls

  • Explain how gas detection, emergency isolation and interlock systems reduce risk, and state their failure modes

Your checkpoint

A risk register with at least eight identified hazards, scored likelihood and consequence, controls mapped to the hierarchy of control, and residual risk stated.

Week 5

Gas safety, hazard and risk management & Codes, standards and regulatory framework (Hong Kong)

  • Assemble a personal index of the Hong Kong statutory and code framework relevant to gas installations, noting for each instrument the scope, the duty holder and the type of obligation it imposes

  • Distinguish the roles of the gas supplier, the registered gas installer, the registered contractor and the authority in approval, commissioning and ongoing inspection

  • Map notification, approval and inspection stages for a new installation and for an alteration to an existing installation onto a single process timeline

  • Explain the legal and professional consequences of working outside registration or competence, and the reporting duty when an unsafe installation is found

  • Identify which code clauses you would cite to justify a refusal to commission an installation, and record the citation format you would use

Your checkpoint

A two-page regulatory map: instrument, scope, duty holder, obligation type, plus a process timeline from design approval to periodic inspection.

Week 6

LPG and LNG installations and bulk storage & Commissioning, testing, inspection and maintenance

  • Compare bulk LPG storage options (underground, above-ground, mounded) on separation distance, bunding, fire protection and access, and select one for a constrained urban site with justification

  • Describe the LNG receiving, storage, vaporisation and send-out chain and identify the safety systems that protect each stage

  • Write a commissioning sequence for a new installation from purging and pressure testing through strength test, tightness test, appliance commissioning and handover

  • Specify the test medium, test pressure, hold duration and acceptance criterion for a strength test and a tightness test, and explain why the two differ

  • Build a preventive maintenance schedule for a commercial installation covering appliance, flue, controls, emergency devices and documentation

Your checkpoint

A commissioning and handover checklist plus a 12-month preventive maintenance schedule for one synthetic commercial installation.

Week 7

Professional practice, ethics and project management & Energy efficiency, environment and emerging low-carbon gases

  • Prepare a written response to a client who insists on a cheaper, non-compliant pipe route, stating the technical basis, the risk and the professional position without personalising the conflict

  • Identify the ethical duties triggered when you discover another party's non-compliant work during commissioning, and set out the escalation sequence

  • Structure a project programme for a gas installation using defined work packages, dependencies, hold points and inspection sign-offs

  • Evaluate hydrogen blending, biomethane injection and electrified heating against gas network decarbonisation goals, stating one technical constraint and one infrastructure implication for each

  • Quantify the energy and emissions benefit of a condensing appliance or a heat-recovery measure using a simple before-and-after calculation

Your checkpoint

A one-page professional-practice case note (ethical dilemma, position, escalation) plus a short low-carbon options comparison table with one quantified efficiency or emissions estimate.

Week 8

Gas supply systems and network design & Gas installation design and pipework sizing & Gas safety, hazard and risk management & Codes, standards and regulatory framework (Hong Kong)

  • Re-derive the network pressure-drop and pipe-sizing calculations from memory under time pressure and check the answers against your week 1 and week 2 sheets

  • Re-score the week 4 risk register with fresh eyes and justify any changed scores

  • Answer timed mixed-domain questions spanning network design, sizing, safety and regulation, then classify every error as knowledge gap, misreading or calculation slip

  • Recite the regulatory map from week 5 without notes and correct any drift in duty holder or obligation

  • Write a 10-point pre-exam checklist covering assumptions to state, units to confirm and common traps to avoid

Your checkpoint

A timed mock paper score sheet with error classification and a personal 10-point pre-exam checklist.

Milestones

Week 2: You can size a service and riser run unaided, state every assumption, and defend the diversity factor you chose.

Week 4: You can diagnose a combustion fault from flue gas readings and link it to a ventilation or flueing defect, and your risk register scores are defensible to a reviewer.

Week 6: You can write a full commissioning sequence and state the strength-test and tightness-test criteria without reference material.

Week 8: Timed mock score is stable across two attempts, every error is classified, and no error recurs from an earlier week.