HK Truss-out Scaffolder (CIC) flashcards
HK Truss-out Scaffolder (CIC) · Build recall with a focused review session.
31 cards. Read the term and the definition here. The deck at the top of this page is optional.
- FIUO and CSSR relationship
- The Factories and Industrial Undertakings Ordinance is the parent legislation; the Construction Sites (Safety) Regulations are subsidiary regulations made under it, so scaffold duties in the CSSR are enforced through the FIUO.
- CSSR scaffold inspection interval
- A scaffold must be inspected by a competent person before first use, after alteration or weather affecting stability, and at intervals not exceeding 14 days, with a written report kept.
- Code of Practice status
- The Code of Practice for Bamboo and Metal Scaffolding Safety gives practical guidance; breaching it is not itself an offence but is admissible as evidence of failing the FIUO or CSSR duties.
- FIUO section 6 duty
- Every employer must provide safe plant and systems of work, safe premises, and adequate information, training and supervision, so far as reasonably practicable, for all workers on the site.
- Competent person definition
- A person with the training, experience and knowledge to inspect and certify scaffolding, able to recognise deflection, corrosion, missing ties and inadequate anchorage against the relevant code.
- Scaffolder scope of work
- A scaffolder erects, alters and dismantles only to a defined design or instruction, keeps fall protection anchored, checks components and stops work to report unsafe conditions.
- Subcontractor scaffold duty
- A subcontractor must work only within its competence, must not alter another party's scaffold without authorisation, and must report defects rather than improvise repairs.
- Defect reporting chain
- Any person finding a scaffold defect reports it to the supervisor or competent person; the affected section is isolated and tagged until repaired and re-inspected.
- Truss-out scaffold principle
- A cantilevered frame projecting from a facade, relying on anchorage and triangulated raking struts for stability rather than ground bearing, so overturning and anchor pull-out govern design.
- Overturning check
- The design must resist the overturning moment of the cantilevered span about the anchorage line, with a factor of safety against overturning and against anchor pull-out.
- Acceptable anchorage substrate
- Anchors must fix into sound structural concrete or structural masonry; render, cladding, tiles and lightweight block are not acceptable unless specifically designed and tested.
- Truss-out spacing rule
- Truss-out units are spaced at centres set by the designer, commonly around 1.5 to 2.0 metres; no unit may be omitted and no span increased without re-design.
- Steel tube rejection
- Reject tube that is bent, kinked, dented, cracked, heavily corroded with section loss, or has a deformed end; check straightness by sighting and thickness where corrosion is suspected.
- Coupler rejection criteria
- Reject a coupler if its threads are damaged, the bolt is bent, the plate or wedge is deformed, or it fails to grip and tighten properly on the tube.
- Timber board rejection
- Reject boards that are split, warped, rotted, excessively knotty, or not of the specified grade and thickness; boards must not be springy underfoot at the designed support spacing.
- Protective mesh inspection
- Check mesh for tears, UV degradation, broken fixings and correct overlap; damaged mesh must be replaced before work continues because it forms part of falling-object protection.
- Erection sequence
- Survey and confirm anchor positions, install anchors and frames from a safe platform, add ties and raking struts, lay platform and edge protection, fit mesh, then inspect and tag.
- Tie removal rule
- No tie, raking strut or guardrail may be removed without authorisation; if a tie must be temporarily removed, the design must specify a temporary replacement approved by the competent person.
- Dismantling direction
- Dismantle top-down, member by member, in reverse of erection; never drop components or release anchors while a platform above is still loaded.
- Post-typhoon re-inspection
- After a typhoon, severe storm, impact or suspected overload, the scaffold must be inspected by a competent person before reuse, regardless of the normal 14-day inspection cycle.
- Independent lifeline
- A separately anchored lifeline, not the scaffold tube or truss-out frame, used where the scaffold is the work location and anchored for the fall-arrest load.
- Fall-arrest hierarchy
- Eliminate work at height first, then provide a platform with guardrails and toe boards; fall arrest by harness and lanyard is the last line of defence, not the primary control.
- Harness inspection points
- Check webbing, stitching, D-rings, buckles, lanyard and shock absorber before each use; reject items with cuts, fraying, heat damage, corrosion, or after any fall arrest.
- Suspension trauma risk
- A worker suspended in a harness can deteriorate rapidly, so a rescue plan must be briefed before work and the casualty recovered promptly and treated for suspension trauma.
- Covered walkway purpose
- A designed roof over the public footpath protects pedestrians and residents from falling tools, couplers, boards and waste during facade scaffold work, and must stay clear.
- Overhead cable control
- Identify and isolate or divert power lines before erecting near them, keep the statutory safe clearance, and treat all cables as live until the utility confirms they are dead.
- Resident interface controls
- Agree access times, protect windows and property, keep escape routes clear, and stop residents opening windows into the scaffold or using it for access.
- Facade drilling hazards
- Drilling anchors can release loose render, spalling concrete, tiles, asbestos-containing material and hidden services; survey and make safe the facade before drilling.
- Scaffold tag content
- A tag shows the scaffold ID, inspection date, pass or do-not-use result, inspector and next inspection date; a red tag or missing tag means no access.
- Pre-use user check
- Before each shift the user checks guardrails, toe boards, boards, ties, mesh, tags and access; any defect means stop work and report it to the supervisor.
- Incident reporting duty
- Fatalities, serious injuries, dangerous occurrences and specified accidents must be reported to the Labour Department and other authorities as required, with the scene and records kept.