HVAC Excellence Gas Heat study materials
HVAC Excellence Gas Heat study resources

HVAC Excellence Gas Heat Certification study plan

HVAC Excellence Gas Heat · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Gas Heating Fundamentals and Combustion

  • Define complete and incomplete combustion, then write the products of reaction for methane with both sufficient and insufficient primary air.

  • Calculate the stoichiometric air requirement for natural gas at 1,000 Btu/ft³ and explain how excess air changes the flue CO₂ and O₂ readings.

  • Distinguish the three legs of the combustion triangle plus the role of ignition energy, and describe what happens to the flame when any leg is reduced.

  • Explain the difference between ignition temperature, flashback, flame lift, and flame rollout using burner-port velocity and primary aeration.

  • Identify the Btu content, specific gravity, and Wobbe index significance of natural gas versus propane and explain why orifices are not interchangeable.

Your checkpoint

A one-page combustion cheat sheet showing the reaction equation, stoichiometric air, target O₂/CO₂ ranges, and a labeled sketch of a correct versus lifting flame.

Week 2

Gas Furnace Components and Sequence of Operation

  • Sequence the complete furnace operating cycle from thermostat call to blower off-delay, naming each switch and control that acts at each step.

  • Trace the gas train from manual shutoff through the gas valve, manifold, and burner, stating the function of each component.

  • Compare hot-surface, direct-spark, and intermittent-pilot ignition systems and list what each proves before opening the gas valve.

  • Describe the role of the pressure switch, inducer, limit, and rollout switch in proving safe operation and in lockout.

  • Explain how a two-stage or modulating gas valve and variable-speed blower change the sequence and airflow profile.

Your checkpoint

A hand-drawn sequence-of-operation flowchart with 12 or more numbered steps and the safety device that permits each transition.

Week 3

Venting, Combustion Air, and Gas Piping

  • Classify Category I, II, III, and IV venting by pressure and temperature and match each to acceptable vent materials.

  • Size a natural-draft vent connector and common vent using the tables, including the effects of connector rise, lateral run, and manifold height.

  • Determine required combustion air by the indoor-air, outdoor-air, and known-infiltration methods, and calculate free area for two-permanent-opening designs.

  • Explain how a direct-vent, two-pipe system differs from a single-pipe plus indoor-air design, including termination clearances.

  • Size a gas supply line by load, length, and pressure drop, and identify where a sediment trap, union, and drip leg are required.

Your checkpoint

A worked venting and gas-piping worksheet for one sample installation: chosen category, vent size, combustion-air method, and pipe size with the table values cited.

Week 4

Electrical Controls, Ignition Systems, and Safeties

  • Read a furnace wiring diagram and trace the 24 V circuit from transformer through thermostat, pressure switch, and gas valve.

  • Test a hot-surface igniter and flame sensor with a meter and state pass/fail criteria for each.

  • Explain flame rectification, why microamps matter, and the effect of a dirty sensor, poor ground, or reversed polarity.

  • Describe the lockout and retry logic of a modern integrated control board, including blink-code interpretation.

  • List the safety devices in series in the gas valve circuit and explain what each protects against.

Your checkpoint

A completed electrical test log for one furnace with measured igniter resistance, flame-sense microamps, pressure-switch continuity, and the meaning of each reading.

Week 5

Installation, Startup, and Combustion Analysis

  • Perform a startup checklist including gas pressure, manifold pressure adjustment, temperature rise, and static pressure measurement.

  • Adjust manifold pressure for natural gas and propane and explain derating for altitude.

  • Set airflow to hit the nameplate temperature rise by measuring supply and return temperatures in the correct locations.

  • Interpret combustion analyzer results for O₂, CO, CO₂, excess air, and stack temperature, and identify acceptable versus unsafe values.

  • Explain why CO air-free readings and draft measurement must be taken together and how to correct a reading for dilution.

Your checkpoint

A full startup report for one furnace: manifold pressure, temperature rise, static pressure, and combustion analyzer readings with a pass/fail judgment against nameplate values.

Week 6

Troubleshooting, Service, and Safety & Gas Heating Fundamentals and Combustion

  • Diagnose no-heat, short-cycling, and lockout complaints by applying the sequence of operation as a decision tree.

  • Distinguish flame rollout, delayed ignition, and sooting symptoms and identify their likely causes.

  • Test for spillage and draft at the vent connector and describe the steps to take when spillage is found.

  • Explain carbon monoxide exposure limits and the procedure for red-tagging an unsafe appliance.

  • Revisit combustion fundamentals to explain how a cracked heat exchanger, overfiring, or blocked flue raises CO.

Your checkpoint

Three written troubleshooting case studies, each with symptoms, test results, diagnosis, and the safety action taken.

Week 7

Gas Furnace Components and Sequence of Operation & Venting, Combustion Air, and Gas Piping

  • Re-sequence the operating cycle from memory and identify the control or switch that fails to advance at each step.

  • Re-check venting and combustion-air calculations for a tight-construction scenario and justify the upgrade chosen.

  • Explain how negative building pressure affects draft, spillage, and combustion air in a natural-draft furnace.

  • Compare common venting, direct venting, and power venting for a replacement installation and state the code-driven constraints.

Your checkpoint

A comparison table of three venting approaches with code constraints, combustion-air requirements, and a recommendation for a sample house.

Week 8

Gas Heating Fundamentals and Combustion & Gas Furnace Components and Sequence of Operation & Venting, Combustion Air, and Gas Piping & Electrical Controls, Ignition Systems, and Safeties & Installation, Startup, and Combustion Analysis & Troubleshooting, Service, and Safety

  • Take two timed practice exams and score each domain to find weak areas.

  • Re-study the two lowest-scoring domains and rewrite the cheat sheet and flowchart from memory.

  • Recite the sequence of operation, combustion targets, and safety limits without notes.

  • Review all deliverables and fix any calculation or reading you could not justify.

Your checkpoint

A scored practice exam summary with domain percentages and a written list of the five facts to review in the final 48 hours.

Milestones

Week 2: Explain the full operating cycle and each safety interlock aloud in under five minutes with no notes.

Week 4: Trace a 24 V circuit on an unfamiliar diagram and correctly identify the fault in a simulated lockout.

Week 6: Complete a startup report and three troubleshooting cases with correct pass/fail judgments and safety actions.

Week 8: Score at least 80 percent on both timed practice exams with no domain below 70 percent.