General Requirements and Administration

  • Permits are required for new installation, alteration, replacement, and relocation of mechanical systems; ordinary repairs not involving fuel or electrical connections are exempt.

  • A permit application must include construction documents showing the scope, equipment location, and clearances; work may not begin until the permit is issued.

  • Inspection stages typically include rough-in (before concealment) and final; concealed work must be inspected before covering.

  • Approved materials and appliances must be listed and labeled by a recognized agency; field modification of listed equipment voids the listing.

  • Materials must be installed per their listing and the manufacturer's installation instructions; instructions govern where the code is silent.

  • Defects found on inspection must be corrected and re-inspected; the authority may order the work stopped for noncompliance.

  • Existing installations that are unsafe or unsanitary may be ordered repaired, altered, or removed regardless of when installed.

  • Equipment must be accessible for inspection, service, repair, and replacement without removing permanent construction.

Quick reference

Heating and Cooling Equipment and Appliances

  • Appliances installed in garages must have ignition sources elevated so burners and ignition are at least 18 in. above the floor unless the appliance is listed for lower installation.

  • Attic and under-floor furnaces need a level service platform, a passageway, and clearance to allow burner, control, and heat-exchanger service.

  • Clearances to combustible construction follow the listing label; reduced clearances require an approved method such as a listed clearance-reduction shield.

  • A furnace must not be installed in a closet unless the closet is dedicated and clearances and combustion/dilution air are provided.

  • Return-air openings must not draw from a bathroom, toilet room, kitchen, garage, or unconditioned attic unless specific code conditions are met.

  • Air-conditioning condensate drains require a trap, slope, and a secondary or auxiliary drain or pan with a drain for units in concealed spaces.

  • Appliances must be installed on a firm, level base; floor-mounted units need access for filter and blower service.

Quick reference

Duct Systems and Ventilation

  • Duct systems must be substantially airtight; joints, seams, and connections are sealed per the duct-sealing class required by the code.

  • Ducts in unconditioned space require insulation with a vapor retarder on the warm side to limit condensation.

  • Return ducts in garages or unconditioned spaces must be sealed and separated to prevent drawing contaminants into the occupied space.

  • Minimum outdoor air ventilation rates for occupancies are set by the mechanical ventilation provisions based on occupancy and floor area.

  • Exhaust systems for bathrooms and kitchens must discharge outdoors and terminate with an approved hood or backdraft damper.

  • Duct penetrations of fire-rated assemblies require approved fire dampers installed per their listing.

  • Flexible duct length, sag, and support spacing are limited by the listing; supports are required at intervals and at bends.

Quick reference

Combustion Air, Venting, and Chimneys

  • The standard method for indoor combustion air uses two permanent openings: one within 12 in. of the top and one within 12 in. of the bottom of the enclosure.

  • For the two-opening method, each opening must have a free area of at least 1 sq in. per 1,000 Btu/h of total input, with a minimum of 100 sq in. per opening.

  • If openings connect to outdoor air through vertical ducts, each opening is 1 sq in. per 4,000 Btu/h; through horizontal ducts, 1 sq in. per 2,000 Btu/h.

  • A single permanent opening near the top may be used when it has free area of at least 1 sq in. per 3,000 Btu/h of total input.

  • A Category I appliance vents with a listed vent connector; vent connector slope is at least 1/4 in. per ft upward toward the chimney or vent.

  • Vent termination must be above the roof line per the vent listing and must be clear of windows, doors, and air intakes.

  • A chimney must be lined and of the correct size; an oversized flue can cause condensation and poor draft.

  • Type B vent requires listed clearances to combustibles; single-wall connectors require greater clearance unless shielded.

Quick reference

Refrigeration, Hydronics, and Fuel Piping

  • Refrigerant piping must be supported, protected from physical damage, and installed with approved fittings; brazing requires purging and proper procedures.

  • Refrigerant quantity limits for a space are based on the refrigerant's safety classification and the volume of the occupied space.

  • Hydronic systems require expansion control, air elimination, and pressure-relief protection; relief valves discharge to a safe location.

  • Boiler relief valves must not be plugged or reduced and must discharge by gravity to a safe place of disposal.

  • Fuel gas piping must be sized for the total connected load and tested for leaks before being placed in service.

  • Gas piping test pressure and duration depend on the system; the test medium is typically air or inert gas, not fuel gas.

  • Gas piping must be supported at intervals and protected where passing through walls, and sediment traps are required at appliance connections.

  • Oil piping and tanks require approved materials, protection from damage, and venting per the code.