ICC F1 · Give each week a clear focus.
8 weeks · About 7 hours per week
Building Construction, Fire Resistance, and Means of Egress
Diagram the five construction types (I–V) and label the fire-resistance requirements that apply to each major structural element.
Calculate occupant load for at least eight spaces using occupancy-specific area factors and net vs. gross distinctions.
Trace egress paths on three sample floor layouts and measure exit access travel distance, common path, dead-end travel, and required egress width.
Compare required versus provided number of exits, exit width, and exit arrangement for the same three layouts and note every deficiency.
Your checkpoint
A self-built 10-question worksheet with fully worked occupant-load and egress-width calculations, scored at 90% or better against the code tables.
Building Construction, Fire Resistance, and Means of Egress & Fire Protection Systems and Equipment
Explain how fire-resistance-rated assemblies, opening protectives, and penetration protection work together to hold a compartment boundary, and identify where each is verified in the field.
Sketch a sprinkler riser showing main drain, control valve, check valve, FDC, alarm valve, branch lines, and heads, and state the inspector's field check for each.
Differentiate wet-pipe, dry-pipe, pre-action, and deluge systems by activation logic and typical application.
Separate the items an inspector verifies during a periodic inspection from those the owner's testing and maintenance program covers.
Your checkpoint
A labeled riser diagram with at least 15 annotated components plus a two-column table dividing inspector verification duties from owner maintenance duties.
Fire Protection Systems and Equipment
Describe the sequence of operation of a fire alarm system from initiation through notification, and contrast conventional with addressable architecture.
Match smoke, heat, flame, and gas detection technologies to the fire stages and occupancies where each is appropriate.
List the acceptance test steps for a new fire alarm system and for a new sprinkler system in the order an inspector witnesses them.
Select portable extinguishers by hazard class and interpret the rating markings and travel-distance placement rules.
Your checkpoint
A detection-technology comparison matrix (technology × fire stage × suitable occupancy × limitation) plus 20 flashcards on system components and inspection points.
Occupancy Classification and Fire Safety Requirements
Classify 25 described buildings and tenant spaces into occupancy groups and justify each with the defining use characteristic.
Distinguish accessory uses, incidental uses, mixed uses, and a true change of occupancy in borderline scenarios.
Determine when a change of use or occupancy triggers a new certificate of occupancy and what documentation it requires.
Map the occupant-load factors, egress rules, and fire protection features that follow from each occupancy group assigned.
Your checkpoint
A classification log of 25 buildings listing the assigned group, the rationale, and one egress or protection implication each, scored at 90% against an answer key.
Occupancy Classification and Fire Safety Requirements & Administration and Enforcement of Fire and Life Safety Codes
Relate each occupancy group to its required fire protection features, including sprinkler thresholds, separation requirements, and allowable height and area limits.
Outline the permit and plan review workflow from application through final certificate of occupancy, naming the inspector's decision at each step.
Identify the inspector's legal authority and limits: right of entry, notices of violation, stop-work orders, citations, and the appeal route.
Summarize how adopted code editions, local amendments, and referenced standards interact when requirements appear to conflict.
Your checkpoint
A one-page flowchart of the permit → plan review → inspection → certificate of occupancy process, annotated with the inspector's decision point at every stage.
Administration and Enforcement of Fire and Life Safety Codes
Distinguish a code violation from a non-code maintenance or housekeeping issue and select the correct corrective remedy for each.
Draft a notice of violation containing every required element, including the code section cited, the corrective action, and the compliance deadline.
Explain the boundary between a fire code inspection and a fire investigation and state when to escalate to an investigator.
Describe the records an inspection file must contain and how long each record type is retained.
Your checkpoint
Three complete written notices of violation for escalating scenarios, each self-scored against a 10-point completeness checklist.
Inspection Procedures, Hazard Identification, and Reporting
Build inspection checklists for a mercantile occupancy and for an assembly occupancy, sequencing items in a walk-through order.
Identify and rank at least 10 common field hazards by risk, including storage clearance, electrical misuse, blocked egress, and hot work.
Document findings in a field report with measurements, photographs described in text, and the governing code reference for each item.
Describe the procedure for handling an imminent hazard and the follow-up re-inspection process.
Your checkpoint
Two occupancy-specific inspection checklists plus one full mock field report containing at least eight findings, each with a measurement and a code reference.
Administration and Enforcement of Fire and Life Safety Codes & Occupancy Classification and Fire Safety Requirements & Building Construction, Fire Resistance, and Means of Egress & Fire Protection Systems and Equipment & Inspection Procedures, Hazard Identification, and Reporting
Complete two full-length timed practice exams and tabulate every missed item by domain.
Re-drill the two weakest domains until practice accuracy reaches 85% or better.
Recite from memory the key tables and definitions - construction types, occupancy groups, occupant-load factors, and system components - without notes.
Simulate exam-day conditions and confirm scheduling, identification, and allowed-reference logistics.
Your checkpoint
A timed full-length practice exam score of 80% or better accompanied by a written error log categorizing every missed question by domain and cause.
Milestones
Week 2: Completed riser diagram and duty-split table; explain the sprinkler riser components from memory without notes.
Week 4: Closed-book 40-question set covering Domains 3 and 4 scored at 75% or better, plus the 25-building classification log at 90%.
Week 6: Closed-book 30-question set covering Domains 1 and 2 scored at 80% or better, plus three complete notices of violation passing the 10-point checklist.
Week 8: Full-length timed practice exam at 80% or better with an error log showing no single domain below 70%.