ICC 86 SFRM Inspector · Keep the key ideas within reach.

Quick reference

Codes, Standards, and Referenced Documents

  • ICC 86 SFRM inspection references IBC Chapter 7 (fire-resistance-rated construction) and the approved fire-resistance directory listings for the specific SFRM product.

  • ASTM E119 is the fire-test-response standard for building construction and materials; SFRM fire-resistance ratings are established by E119 testing of the specific assembly.

  • ASTM E736 covers cohesion/adhesion of sprayed fire-resistive materials; ASTM E605 covers thickness and density; ASTM E759 covers deflection under load.

  • UL 263 is the fire test standard equivalent to ASTM E119; listings in the UL Fire Resistance Directory specify required SFRM thickness and density for each assembly.

  • The SFRM manufacturer's published application instructions (ICBO/ICC-ES evaluation report or UL listing) are the governing document for mixing, thickness, and curing.

  • IBC Section 704.13 and 1705 require special inspection of SFRM where the fire-resistance rating is required; the statement of special inspection defines scope.

  • ASTM C635 covers manufacture, performance, and testing of metal suspension systems for acoustical tile; not directly SFRM but referenced in ceiling assemblies.

  • NFPA 70 (NEC) and NFPA 72 may be referenced for penetration protection and firestopping coordination with SFRM.

  • Project specifications (Division 07 81 00) often invoke ASTM E736, E605, and manufacturer requirements in addition to code.

Quick reference

SFRM Materials, Types, and Fire-Resistance Principles

  • SFRM types include cementitious (gypsum/portland cement based), fibrous (mineral wool or slag wool with binder), and intumescent coatings; each has distinct density and application requirements.

  • Fire-resistance principle: SFRM insulates steel by endothermic reaction and low thermal conductivity, slowing the temperature rise of the steel to maintain structural capacity.

  • Steel temperature limit for structural capacity is typically 1000°F to 1300°F depending on the member and code; SFRM must keep steel below this for the required rating time.

  • Density ranges: cementitious SFRM often 15–25 pcf; fibrous SFRM often 10–20 pcf; low-density fibrous may be 8–12 pcf. Verify with manufacturer data.

  • SFRM must be compatible with primers and shop coatings; incompatible coatings can cause adhesion failure.

  • Asbestos-containing SFRM is prohibited in new construction; existing SFRM must be tested before disturbance.

  • Intumescent coatings are thin-film and rely on swelling when heated; they are not SFRM in the traditional sense but may be inspected under similar protocols.

  • SFRM must be applied to clean, primed steel; galvanized surfaces may require a compatible primer or surface preparation per manufacturer.

Quick reference

Substrate Preparation, Surface Conditions, and Environmental Requirements

  • Steel substrate must be free of oil, grease, dirt, loose rust, and mill scale; SSPC-SP 2 (hand tool) or SP 3 (power tool) cleaning may be specified.

  • Primers must be compatible with SFRM; shop primers are often required to be tested for adhesion per ASTM E736.

  • Ambient temperature during application typically must be at least 40°F (4°C) and rising; substrate temperature must be above 40°F unless manufacturer allows otherwise.

  • Ventilation must be adequate to remove moisture and dust; humidity limits per manufacturer (often <80% RH).

  • Surfaces must be dry; moisture can cause blistering or delamination of SFRM.

  • Masking and protection of adjacent surfaces, penetrations, and equipment is required before spraying.

  • Welded areas, bolts, and edges require SFRM coverage; sharp edges may need extra thickness or reinforcement.

  • Environmental conditions during curing must be maintained; freezing temperatures can damage uncured SFRM.

Quick reference

Application Methods, Equipment, and Installation Procedures

  • SFRM is typically applied by spraying using a mixer/pump and compressed air; dry mix and water are combined at the nozzle or in a mixing chamber.

  • Application is done in multiple passes; each pass thickness is limited by manufacturer (often 1/2 inch to 1 inch) to prevent sagging or poor adhesion.

  • Nozzle distance and angle affect density and uniformity; maintain consistent distance (typically 12–24 inches) and perpendicular to surface.

  • For fibrous SFRM, air pressure and material feed rate must be adjusted to achieve specified density; test panels may be required.

  • Curing time between passes varies with product and environment; follow manufacturer's recoat window.

  • Equipment must be cleaned regularly to prevent hardened material from clogging lines and affecting spray pattern.

  • Installation around penetrations, hangers, and supports must maintain required thickness and continuity; blocking or reinforcement may be needed.

  • Final thickness is achieved by building up passes; over-spray on adjacent surfaces must be removed before curing.

Quick reference

Thickness and Density Measurement, Verification, and Sampling

  • Thickness is measured per ASTM E605 using a depth gauge or caliper; measurements are taken at random locations on each member.

  • Density is determined per ASTM E605 by sampling a known volume of cured SFRM, weighing it, and calculating pounds per cubic foot (pcf).

  • Sampling frequency: typically one thickness measurement per 100 square feet and one density sample per 1000 square feet or per project, per ASTM E605.

  • Thickness must meet or exceed the specified thickness from the fire-resistance directory; average thickness and minimum individual thickness are evaluated.

  • Density must be within the range specified by the manufacturer and the listing; low density can reduce fire resistance.

  • Measurements should be recorded with location, member identification, and date; photographs are recommended.

  • For fibrous SFRM, density is critical because it affects cohesion and fire performance; samples must be taken from representative areas.

  • Test methods: ASTM E605 covers thickness and density; ASTM E736 covers cohesion/adhesion; ASTM E759 covers deflection.

Quick reference

Adhesion, Cohesion, and Bond Testing

  • Adhesion testing per ASTM E736 measures the bond between SFRM and substrate; cohesion testing measures internal strength of the SFRM.

  • Test method: a core sample is cut, a loading fixture is attached, and a tensile load is applied; failure mode (adhesive vs cohesive) is recorded.

  • Minimum adhesion/cohesion values are typically specified by the manufacturer or listing; often 150–1000 psf depending on product.

  • Test frequency: typically one test per 1000 square feet or per project, and at least one per substrate type and primer.

  • Tests should be performed after SFRM has cured sufficiently; follow manufacturer's minimum cure time.

  • Failure at the substrate indicates adhesion failure; failure within the SFRM indicates cohesion failure. Both are evaluated against acceptance criteria.

  • Areas that fail must be repaired and retested; documentation of failures and repairs is required.

  • ASTM E736 also provides for bond strength testing of sprayed fire-resistive materials.

Quick reference

Inspection Documentation, Reporting, and Records

  • Daily inspection reports should include date, weather, temperature, humidity, substrate condition, product used, batch numbers, and application thickness.

  • Records must include location of measurements, test results, and any deviations from specifications.

  • Photographs of before, during, and after application are valuable evidence of compliance.

  • Test reports for thickness, density, and adhesion must be retained and submitted to the authority having jurisdiction (AHJ).

  • Non-conformance reports (NCRs) document defects, repairs, and corrective actions; they must be closed out with verification.

  • Final inspection report should summarize compliance with the approved fire-resistance design and manufacturer instructions.

  • Records should be maintained for the project duration and as required by code; typically for the life of the building.

  • Inspection reports must be signed and dated by the inspector and kept on file.

Quick reference

Defects, Repairs, and Corrective Actions

  • Common defects: insufficient thickness, low density, poor adhesion, cracks, delamination, voids, and incomplete coverage.

  • Repair procedure: remove defective material to sound SFRM or substrate, clean, apply compatible primer if required, and reapply SFRM to specified thickness.

  • Repairs must be tested and documented; retest adhesion and thickness in repaired areas.

  • Cracks wider than a hairline may indicate cohesion failure; investigate cause and repair per manufacturer.

  • Delamination is often caused by poor surface preparation, incompatible primer, or moisture; correct root cause before repair.

  • Voids around penetrations and edges must be filled to maintain fire-resistance continuity.

  • Corrective actions should include root cause analysis and preventive measures to avoid recurrence.

  • All repairs must be approved by the AHJ and documented in the inspection record.