UKOM Sp.JP flashcards
UKOM Sp.JP · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- RUP
- Rencana Umum Pengadaan: the published procurement plan on SIRUP/LPSE that lists packages, methods, and schedules after the budget is approved.
- HPS
- Harga Perkiraan Sendiri: the confidential owner's estimate used to assess price reasonableness; it must not be disclosed to bidders.
- Pengadaan Langsung
- A simplified method for goods/other services up to Rp50 million, using direct negotiation with a qualified provider without a full tender.
- Penunjukan Langsung
- Direct appointment of a provider permitted only in defined exceptional cases such as emergency, sole source, or repeat order, with justification.
- Aanwijzing
- The clarification meeting in a tender or selection where the Pokja explains the Dokumen Pemilihan; minutes are binding on all participants.
- Sanggahan
- A formal objection by a bidder against the selection result or process, filed within 5 working days for tender and 3 for direct procurement.
- Dokumen Pemilihan
- The tender/selection document containing instructions, evaluation criteria, KAK, draft contract, and forms; it governs the whole selection process.
- Kontrak Lump Sum
- A contract with a fixed price for a fixed scope; the provider bears quantity risk and the price does not change with actual quantities.
- Kontrak Harga Satuan
- A unit-price contract where payment is based on measured actual quantities at agreed unit rates; the owner bears quantity risk.
- Kontrak Payung
- A framework agreement used in e-purchasing through the Katalog Elektronik, allowing call-off orders against pre-agreed terms and prices.
- Addendum Kontrak
- A contract amendment permitted only for changed scope, schedule, or policy-driven price change, capped at 10% value increase and signed before expiry.
- Denda Keterlambatan
- Late-delivery penalty typically set at 1/1000 of contract value per day, capped at 5-10% depending on the contract type.
- Jaminan Pelaksanaan
- Performance bond of 5-10% of contract value submitted by the winner to guarantee completion according to the contract.
- PHO dan FHO
- Provisional Hand Over after completion and Final Hand Over after the maintenance period, typically 6-12 months for works contracts.
- Wanprestasi
- Default or breach by a party; it permits termination after a formal warning (somasi) and follows the contract's dispute clause.
- Pakta Integritas
- An integrity pact signed by officials and bidders declaring no collusion, no bribery, and no conflict of interest in the procurement.
- Daftar Hitam
- The national blacklist barring a provider from government procurement for 1-2 years after a proven violation.
- Gratifikasi
- A gift or benefit related to official duties; accepting it in procurement is a corruption offense under UU 20/2001.
- SPSE
- Sistem Pengadaan Secara Elektronik: the national e-procurement platform operated by LKPP and hosted by LPSE at each institution.
- Katalog Elektronik
- The online catalog of approved goods/services used for e-purchasing, allowing direct orders without a full tender.
- Tanda Tangan Elektronik
- A certified digital signature under UU 11/2008 (ITE) that is legally binding and used to sign bids and contracts electronically.
- E-purchasing
- Purchasing goods/services directly from the Katalog Elektronik, generating a purchase order and contract through the system.
- Seleksi Umum
- The open method for jasa konsultansi that invites any qualified consultant and evaluates technical and price proposals.
- Two-Envelope System
- A bidding method where technical and price proposals are submitted separately; price is opened only after technical qualification.
- SBU Konstruksi
- Sertifikat Badan Usaha: the business license classifying a construction firm's permitted fields and qualifications for bidding.
- AHSP
- Analisa Harga Satuan Pekerjaan: the standard method for building unit prices used to prepare the HPS for works contracts.
- Swakelola
- Self-managed procurement where the institution executes the work itself rather than through a provider, planned in the RUP.
- POKJA PEMILIHAN
- The selection committee formed by the UKPBJ or Pejabat Pengadaan to run tender/selection, evaluate bids, and set the winner.
- PPK
- Pejabat Pembuat Komitmen: the official who manages the budget, prepares the HPS and contract, and signs on behalf of the institution.
- Banding
- An appeal to the KPA after a sanggahan is rejected, decided within 5 working days; the outcome is final within the institution.
- BPK dan BPKP
- BPK is the external constitutional auditor; BPKP is the internal government auditor; both review procurement compliance and value for money.
- Risiko Pengadaan
- A procurement risk such as budget, specification, bidder, contract, or integrity risk, recorded in a register and mitigated at each stage.