CSCS 360° Excavator study materials
CSCS 360° Excavator study resources

CSCS 360° Excavator flashcards

CSCS 360° Excavator · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Reasonably practicable
A legal test balancing the risk against the cost, time and difficulty of controlling it; used in the Health and Safety at Work etc. Act 1974 for employer duties.
PUWER 1998
Regulations requiring work equipment such as excavators to be suitable, maintained, inspected and used only by competent persons, with adequate information and training provided.
LOLER examination interval
Lifting equipment and accessories require thorough examination at intervals not exceeding six months, or twelve months for equipment not used for lifting people.
COSHH assessment
A recorded assessment of hazardous substances such as diesel, hydraulic oil and silica dust, identifying exposure routes and the controls needed before work begins.
Waste duty of care
The legal duty to store, transfer and dispose of controlled waste such as used oil and filters only through authorised carriers with correct documentation.
Risk assessment five steps
Identify hazards, decide who may be harmed and how, evaluate risks and controls, record findings, and review and update the assessment as work changes.
Hierarchy of control
The order of risk control: eliminate, substitute, engineering controls, administrative controls, and personal protective equipment as the last resort.
Slew zone crush hazard
The area swept by the rotating upper structure and counterweight; pedestrians must be excluded because the operator cannot see the whole area from the cab.
Near-miss reporting
Recording events that could have caused harm but did not; these are leading indicators used to correct hazards before an injury occurs.
Prohibition sign
A red circle with a diagonal bar indicating an action that must not be taken, such as no unauthorised entry to a plant operating area.
Mandatory sign
A blue circular sign indicating an action that must be taken, such as wearing hearing protection or a safety helmet in a designated area.
Signaller duties
A competent person who directs machine movement using agreed hand signals or radio when the operator's view is obstructed, and who stays in a safe position.
Upper action value noise
The daily noise exposure level of 85 dB(A) at which hearing protection must be provided and used, and hearing protection zones marked.
ROPS and FOPS
Roll-over and falling-object protective structures fitted to the cab; they protect the operator only if the seat belt is worn and the structure is undamaged.
ISO control pattern
The excavator joystick layout where the left lever controls slew and dipper arm and the right lever controls boom and bucket.
Hydraulic lockout lever
A lever that isolates the pilot control circuit so that joystick movement cannot operate the machine, used before leaving the cab.
Load moment indicator
An instrument that warns the operator when the machine approaches its rated capacity for the current radius, height and attachment configuration.
Quick coupler check
A visual and functional check that the locking pin is fully engaged after changing an attachment, because coupler failure can drop the bucket unexpectedly.
Pre-use walk-around
A visual inspection of the machine before starting, covering leaks, structural cracks, track condition, guards, fluid levels and safety devices.
Defect tagging
The process of taking a defective machine out of service, attaching a clear warning tag and isolating it until a competent person repairs it.
Hydraulic injection injury
A pinhole hydraulic leak can inject fluid through the skin, causing serious tissue damage; it is a medical emergency requiring immediate hospital treatment.
Track tension check
Measuring the sag on the longest run of the track against the manufacturer's specification; over-tension damages bearings and under-tension causes derailment.
Centre of gravity rule
A machine remains stable only while its combined centre of gravity stays within the support base formed by the tracks or wheels and outriggers.
Rated capacity
The maximum load stated in the load chart for a given radius and height; it decreases as radius increases and assumes level, firm ground.
Slope travel rule
Travel with the heavier end of the machine uphill, keep the bucket low, and avoid slewing or lifting while on a gradient.
Ground bearing pressure
The load per unit area imposed by the machine on the ground; it increases with weight, load and dynamic forces and must be checked on soft or backfilled ground.
Cable avoidance tool
A device used before excavation to detect buried metallic services; it must be used with service drawings and confirmed by hand-dug trial holes.
Excavation surcharge
Load added at the top of an excavation by spoil, materials or machines, which increases the risk of side collapse and must be kept back from the edge.
Overhead line clearance
The minimum safe distance from live overhead lines specified for the line voltage; barriers or goalposts mark the limit and lines are treated as live.
Lifting with an excavator
A planned lift using certified lifting points and accessories, a load chart or rated capacity indicator, and no movement of the load over people.
Machine shutdown sequence
Park on firm level ground, lower attachments, neutralise controls, engage lockout and parking brake, cool the engine, then stop and remove the key.
Refuelling precautions
Engine off, no ignition sources, bonded nozzle, drip trays in place and spill kit available; spilled fuel and absorbents are controlled waste.