CSCS Crawler Crane study materials
CSCS Crawler Crane study resources

CSCS Crawler Crane flashcards

CSCS Crawler Crane · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Crawler crane base
A crane with a rotating upperworks mounted on two endless crawler track assemblies, providing mobility and load spreading without outriggers.
Load moment indicator
A device that senses load and radius, computes load moment, compares it to the rated chart, and warns or locks out before an overload occurs.
Boom angle effect
As boom angle decreases toward horizontal, radius increases and rated capacity decreases; lower angles also increase boom bending loads.
Pendant lines
Fixed-length wire rope or bar assemblies that support the boom from the upperworks and transfer boom loads into the crane structure.
Rated radius definition
The horizontal distance from the crane's rotation center to the vertical line through the load's center of gravity, used to read the load chart.
Ground bearing pressure
Total weight carried by a track divided by the effective track contact area, expressed in psf or kPa and compared to soil allowable capacity.
Out-of-level limit
Manufacturer's maximum allowable crane slope, commonly about 1 percent, beyond which chart capacities are invalid and stability is reduced.
Tipping axis
The line about which the crane tips, typically the track edge or outrigger line; the crane tips when load moment exceeds resisting moment.
Crane mats purpose
Timber or steel pads that spread track pressure over a larger area so the subgrade's allowable bearing capacity is not exceeded.
Pick-and-carry rating
A separate charted capacity for traveling with a load, valid only on firm level ground with the boom in the specified travel position.
Total load calculation
Load weight plus sling and rigging weight plus hook block or headache ball plus below-the-hook devices, all deducted from gross chart capacity.
Next longer radius rule
When the actual radius falls between charted values, use the next longer radius and its lower capacity; never interpolate capacity upward.
Structural versus stability
Rated capacity is the lesser of the structural limit of boom, pins, and rope and the stability limit for that radius and configuration.
Parts of line
The number of rope falls supporting the load; required line pull equals total load divided by parts of line.
Loaded radius change
Boom deflection and load swing increase the operating radius beyond the unloaded geometric radius, reducing actual capacity.
Sling leg tension
For a two-leg bridle, tension per leg equals half the load divided by the sine of the leg angle from horizontal.
Choker hitch capacity
A choker hitch is typically rated about 75 to 80 percent of the sling's vertical capacity because the choke reduces strength.
Sling angle factor
Multi-leg sling capacity is multiplied by the sine of the angle to horizontal; 60 degrees gives about 0.866, 45 degrees about 0.707.
Shackle rating basis
Shackle working load limit is based on the pin or bowl strength, and the hook must have a functioning safety latch.
Center of gravity control
The load's center of gravity should be below or at the lift point; off-center lifts require tag lines and calculated load control.
Anti-two-block test
A daily function check that confirms the device stops hoisting before the hook block contacts the boom tip.
Boom pin inspection
Verify all boom and lacing pins are fully inserted and secured and pendant lines are properly tensioned before lifting.
LMI calibration check
The load moment indicator must be calibrated and zeroed for the installed boom and counterweight configuration; a bypassed LMI removes the crane from service.
Wire rope rejection
Rope is removed from service for broken wires exceeding the specified count per lay, kinking, crushing, bird-caging, or heat and corrosion damage.
Daily pre-shift inspection
A documented check of rope, sheaves, hook and latch, boom pins, tracks, fluids, brakes, and limit switches before each work shift.
Designated signal person
One qualified person directs the operator by hand or radio; the operator obeys only that person except for stop signals from anyone.
Stop signal rule
The operator stops immediately on a stop signal from any person, then resumes only when directed by the designated signal person.
Trial lift procedure
Lift the load a few inches, verify stability, brake holding, and rigging, then proceed with the full lift.
Swing control technique
Start and stop swing smoothly and use the boom to move the load; do not drag loads or swing the load ahead of the boom.
Power line contact response
If the crane contacts energized lines, the operator stays in the cab and warns others away until the line is de-energized.
Emergency exit from crane
If fire forces exit after line contact, jump clear without touching crane and ground together, then shuffle away with feet together.
Suspended load exclusion
No person may stand or walk under a suspended load, within the swing radius, or between the load and a fixed object.