CSCS Mobile Crane study materials
CSCS Mobile Crane study resources

CSCS Mobile Crane cheat sheet

CSCS Mobile Crane · Keep the key ideas within reach.

Quick reference

Site and Lift Planning

  • Ground bearing pressure = total load (crane weight + counterweight + load + rigging) divided by the bearing area under each outrigger or track.

  • Percent of capacity = (lift load including rigging and deductions) ÷ (rated capacity for the actual radius and configuration) × 100.

  • Load radius is measured horizontally from the crane's rotation axis to the center of gravity of the load, not to the hook or the edge of the load.

  • Plan the lift so the crane's rotation axis stays a fixed distance from any obstruction; swinging a load changes radius only if the boom angle or boom length changes.

  • Deductions from gross capacity include jib, auxiliary head, hook block, and any stowed attachments; net capacity = gross capacity minus these deductions.

  • A lift plan must identify power line clearances, underground utilities, soil type, slope, and the crane's access and egress route.

  • Critical lift criteria commonly include exceeding 75% of rated capacity, lifting over occupied areas, or using more than one crane.

  • Wind area of the load increases with the square of load dimensions; a load's sail area matters more than its weight for wind effects.

Quick reference

Crane Setup, Assembly, and Disassembly

  • Outrigger floats increase bearing area; pressure on soil = load per outrigger ÷ float area, so doubling float dimensions quarters the pressure.

  • Crane must be level within the manufacturer's tolerance (commonly 1% or as specified) before lifting; use a bubble level or inclinometer on the carrier.

  • Outriggers must be fully extended and set on firm, drained, compacted ground; cribbing must be sized to spread load, not just to level.

  • Boom assembly pins and pendants must be fully engaged and retaining pins installed before the boom is raised.

  • Counterweight must match the load chart configuration selected; removing or adding counterweight changes the rated capacity.

  • Assembly/disassembly area must be barricaded and controlled; only the assembly director and crew enter the boom and counterweight zone.

  • Boom length, jib length, and boom angle must be recorded and matched to the specific load chart before the first lift.

  • Electrical grounding, anemometer installation, and anti-two-block function checks are completed during setup verification.

Quick reference

Load Charts, Capacity, and Configuration

  • Rated capacity is read at the intersection of load radius and boom length for the specific boom, jib, counterweight, and outrigger configuration.

  • Interpolate between chart values only linearly and only where the manufacturer permits; never extrapolate beyond the chart.

  • Capacity decreases as radius increases and as boom length increases at a given radius; a longer boom at the same radius usually reduces capacity.

  • On-rubber capacities are typically much lower than on-outrigger capacities and often require the boom centered over the front or rear.

  • Deductions: hook block, headache ball, slings, spreader bars, and jib must be subtracted from gross capacity to get allowable load.

  • Load chart notes govern special conditions: travel with load, pick-and-carry, personnel platforms, and multiple-part line requirements.

  • The number of parts of line affects capacity only through the chart's stated reeving limits; the chart already accounts for the standard reeving.

  • When two cranes lift a load, each crane's share depends on load geometry; common practice limits each to 75% of its rated capacity unless a qualified engineer specifies otherwise.

Quick reference

Rigging and Load Handling

  • Sling tension in a two-leg bridle = (load ÷ 2) ÷ cos(angle from vertical); as the angle from vertical increases, tension increases.

  • Sling angle is measured from horizontal; a 30° horizontal angle doubles the tension compared with a vertical lift.

  • Working load limit (WLL) of a sling must be at least the load divided by the number of legs, adjusted for angle and any unequal loading.

  • Center of gravity must be under the hook; an off-center pick causes load tilt and unequal leg loading.

  • Shackles, hooks, and rigging hardware must be rated and match the sling capacity; hooks need a functioning latch.

  • Tag lines control rotation and swing but must never be used to pull a load beyond the crane's rated radius.

  • Softeners or edge protection are required where slings contact sharp edges; wire rope slings must not be kinked or birdcaged.

  • Shock loading multiplies dynamic forces; lift smoothly and avoid sudden stops that add to static sling tension.

Quick reference

Signalperson Duties and Hand Signals

  • The signalperson must be qualified and must use standard signals; any signal may be given by anyone to stop the load in an emergency.

  • Only one designated signalperson directs the operator at a time; a change of signalperson must be communicated to the operator.

  • Hand signals must be clear, distinct, and given from a position in full view of the operator; radio communication is an alternative when specified.

  • Standard signals: raise boom (arm extended, fingers closed, thumb up); lower boom (arm extended, thumb down); stop (arm extended, palm down, hold).

  • Standard signals: hoist (forearm up, index finger up, circular motion); lower (arm down, index finger down, circular motion); dog everything (clasp hands at waist).

  • Standard signals: swing (arm extended, point in direction of swing); travel (fists in front, circular motion in travel direction).

  • Emergency stop is given by anyone and requires the operator to stop immediately and hold.

  • Signalperson must maintain line of sight or radio contact; if contact is lost, the operator stops until communication is restored.

Quick reference

Operating Practices and Load Control

  • Smooth acceleration and deceleration limit pendulum swing; swing the boom, not the load, to control position.

  • Avoid side loading the boom; booms are designed for vertical loads within the chart's rated capacity.

  • Keep the load as low as practical and control swing with tag lines; centrifugal force increases radius during rapid swings.

  • Anti-two-block device prevents the hook block from contacting the boom tip; never bypass or disable it.

  • Load moment indicator (LMI) or rated capacity limiter warns and stops operations approaching rated capacity; operators must not override except per manufacturer procedure.

  • Travel with a load only per the manufacturer's travel chart, with the boom in the specified position and the load as low as possible.

  • Wind speed limits and load sail area govern when a lift must stop; use the anemometer reading at boom tip height.

  • Park the crane with the boom lowered, hook secured, and controls in neutral; set brakes and remove the key.

Quick reference

Inspection and Maintenance

  • Pre-shift inspection covers wire rope, hook, rigging, outriggers, levels, LMI, anti-two-block, brakes, and fluid levels.

  • Wire rope removal criteria include broken wires per lay, diameter reduction, corrosion, kinking, and birdcaging per the manufacturer or standard.

  • Hook inspection: check for cracks, throat opening increase (commonly 15%), wear, and latch function.

  • Periodic inspections are required at intervals (commonly monthly to annually) and after any incident, shock load, or modification.

  • Documented inspections must be retained; records include date, inspector, findings, and corrective action.

  • Hydraulic systems must be checked for leaks and cylinder condition; leaking cylinders can cause uncontrolled boom lowering.

  • Load moment indicator and anti-two-block must be function-tested before each shift, not just inspected visually.

  • Any safety device found defective removes the crane from service until repaired and re-tested.

Quick reference

Safety, Hazards, and Emergency Procedures

  • Maintain the required minimum clearance from power lines per the applicable standard; if clearance cannot be maintained, de-energize and ground the lines.

  • If contact with a power line occurs, the operator should stay in the cab and warn others away; if evacuation is necessary, jump clear and shuffle away.

  • Barricade the swing radius and the area under the load; no personnel under a suspended load.

  • Emergency lowering procedures must be known: use the manufacturer's emergency pump or lowering valve per the manual.

  • Fire extinguisher must be on the crane and inspected; know the fuel shutoff and battery disconnect locations.

  • Load drop or tip-over response: stop operations, secure the area, notify supervision, and do not re-enter until assessed.

  • Personnel platforms require the manufacturer's approval, a fall protection system, and reduced capacity per the platform chart.

  • Wind, lightning, and severe weather require stopping the lift and lowering the boom per the manufacturer's storm procedures.