CSCS Mobile Crane · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Site and Lift Planning

  • Map every element of a lift plan (site survey, ground conditions, hazard identification, load weight, crane selection, permits) and explain why each element exists

  • Calculate ground bearing pressure for a given outrigger load and mat size, then compare it to a stated soil capacity

  • Identify overhead and subsurface hazards from a written site description and list the controls for each

  • Draft a hazard-control sequence for a lift near power lines using the minimum approach distance concept

Your checkpoint

A complete one-page lift plan for a hypothetical site, including a worked ground bearing pressure calculation and a hazard/control table with at least 8 entries

Week 2

Site and Lift Planning & Load Charts, Capacity, and Configuration

  • Convert between load weight, radius, boom length, and boom angle using basic rigging geometry (sine/cosine relationships)

  • Read a generic capacity table and locate the governing capacity for a given radius, boom length, and quadrant

  • Apply deductions for jib, stinger, and auxiliary head configurations to arrive at net capacity

  • Explain how configuration changes (counterweight, outrigger spread, track or tire condition) alter the chart

Your checkpoint

A worked problem set of 10 capacity lookups with all deductions shown and net utilization percentage calculated for each

Week 3

Load Charts, Capacity, and Configuration

  • Distinguish gross capacity, net capacity, and allowable load, and compute each from a scenario

  • Apply the utilization and safety-factor concepts to decide whether a planned lift is acceptable

  • Identify the chart notes that most often cause field errors (deductions, quadrant restrictions, travel restrictions, wind limits)

  • Solve multi-step problems that combine radius growth during a pick with deduction stacking

Your checkpoint

A timed 20-question capacity and configuration self-test, scored and reviewed, with every missed item rewritten as a corrected rule statement

Week 4

Crane Setup, Assembly, and Disassembly & Rigging and Load Handling

  • Sequence a full crane assembly and disassembly, naming the verification checkpoints before each step

  • Select sling type, capacity, and hitch for given loads, and compute sling tension at various vertical angles

  • Determine the center of gravity of an asymmetric load and predict how it shifts when rigged from alternate points

  • Identify rigging hardware inspection rejection criteria and state the removal action for each

Your checkpoint

A written rigging plan for one asymmetric load with tension calculations at 30, 45, and 60 degrees, plus a rejected-hardware photo-free description list

Week 5

Signalperson Duties and Hand Signals

  • Demonstrate every standard hand signal from memory to a partner and have them name each signal back correctly

  • Direct a simulated blind lift using only voice and hand signals, with the operator confirming each command

  • Describe the signalperson's stop authority and the conditions that require stopping the lift immediately

  • Explain communication failure protocols, including loss of radio or line of sight, and the required response

Your checkpoint

A recorded or witnessed practical demonstration of all required hand signals, scored against a checklist with zero errors

Week 6

Operating Practices and Load Control

  • Execute the standard lift sequence (pre-lift checks, trial lift, swing, placement, load securement) and narrate each control

  • Identify swing, drift, and load-sway causes and apply the correct control input for each

  • State the wind and weather limits that require stopping or reassessing a lift

  • Explain load moment and anti-two-block systems and how to respond to each alarm or limiter activation

Your checkpoint

A written step-by-step operating procedure for one lift, with an alarm-response decision table covering at least 5 conditions

Week 7

Inspection and Maintenance

  • Build a pre-shift inspection checklist covering wire rope, sheaves, hooks, hydraulics, brakes, and safety devices

  • List wire rope removal criteria and apply them to described rope conditions

  • Distinguish daily, periodic, and annual inspection responsibilities and recordkeeping requirements

  • State what to do when a defect is found mid-shift, including documentation and lockout

Your checkpoint

A completed mock daily inspection form for a described crane, with every defect flagged and a disposition stated for each

Week 8

Safety, Hazards, and Emergency Procedures & Site and Lift Planning & Load Charts, Capacity, and Configuration

  • Rank the highest-consequence hazards across all domains and state the single control that most reduces each

  • Rehearse the emergency response sequence for power line contact, tip-over, and dropped load

  • Re-solve one missed capacity problem from weeks 2-3 and one missed lift-planning item from week 1

  • Complete a full-length timed practice exam and review every error by domain

Your checkpoint

A scored full-length practice exam with a written error log grouping misses by domain and confirming all domains above 80%

Milestones

Week 2: Can compute a ground bearing pressure and locate a chart capacity with deductions, unaided, in under 10 minutes

Week 4: Can sequence assembly and disassembly and produce a rigging plan with correct sling tensions at three angles

Week 6: Performs all hand signals with zero errors and states the correct response to 5 limiter or alarm conditions

Week 8: Scores at least 80% on the full-length practice exam with no single domain below 70%