JC Engineering flashcards
JC Engineering · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Hooke's law
- Within the elastic range, stress is proportional to strain: σ = Eε, where E is Young's modulus. Beyond the proportional limit the relationship becomes nonlinear and permanent deformation may occur.
- Reynolds number
- Dimensionless ratio Re = ρvD/μ describing flow regime. Values below about 2000 indicate laminar flow, above about 4000 turbulent flow, and between them a transitional regime.
- Factor of safety
- Ratio of a material's failure strength to the allowable working stress. It accounts for load uncertainty, material variability and consequences of failure; below 1 predicts failure.
- Goodman relation
- Fatigue criterion combining alternating and mean stress: σa/Se + σm/Su = 1. It gives a conservative estimate of infinite-life safety for ductile materials under combined steady and cyclic loading.
- Tolerance stack-up
- Accumulation of individual part tolerances in an assembly. Worst-case analysis sums tolerances directly; statistical root-sum-square analysis predicts the probable variation and is less conservative.
- Martensite formation
- Hard, brittle phase formed when austenite cools too fast for diffusion, as in quenching. Tempering afterwards reduces brittleness and relieves internal stress while retaining useful hardness.
- Heat-affected zone
- Region of parent metal whose microstructure and properties are altered by welding heat without melting. It can harden or embrittle and often governs joint toughness and cracking risk.
- Critical path
- Longest duration sequence of dependent activities through a project network. It has zero total float, so any delay on it directly delays project completion.
- Cost performance index
- CPI = EV/AC, the ratio of earned value to actual cost. A value below 1 means work is costing more than budgeted; EAC is often forecast as BAC/CPI.
- Schedule variance
- SV = EV − PV, the difference between earned value and planned value. A negative value indicates the project is behind the planned schedule at the reporting date.
- Process capability index
- Cpk = min[(USL − μ), (μ − LSL)]/3σ. It measures whether a centred or off-centre process fits within specification limits; values of 1.33 or more are commonly required.
- Control chart
- Plot of a process measure over time with statistical control limits. Points outside the limits or non-random patterns signal special-cause variation requiring investigation.
- Pareto analysis
- Ranking causes of a problem by frequency or impact. It applies the principle that a small number of causes, roughly 20 percent, produce most of the effect.
- Hierarchy of controls
- Ranking of risk controls by effectiveness: elimination, substitution, engineering controls, administrative controls, then personal protective equipment as the least effective last resort.
- Lockout tagout
- Formal procedure isolating all energy sources, dissipating stored energy and verifying zero energy before maintenance. Each worker applies a personal lock so equipment cannot be re-energised.
- Confined space entry
- Entry into a space with limited access and possible hazardous atmosphere. Requires atmospheric testing, a permit, an attendant outside and rescue arrangements before entry.
- Code versus standard
- A code is a legally adopted set of rules; a standard is a consensus technical document. Codes frequently reference standards, which then become enforceable through adoption.
- Order of precedence
- Contractual ranking that resolves conflicting documents. Typically the specification and contract terms outrank general drawings, so the higher-ranked document governs the requirement.
- Present worth factor
- P = F/(1 + i)^n converts a future amount to today's value at interest rate i over n periods. It is the basis for comparing alternatives by net present value.
- Internal rate of return
- Discount rate at which a project's net present value equals zero. A project is economically acceptable when its IRR exceeds the required minimum attractive rate of return.
- Capital recovery factor
- Factor converting a present amount to an equivalent uniform annual payment: i(1 + i)^n/[(1 + i)^n − 1]. It is used for annual worth comparisons and loan payments.
- Public safety paramount
- Ethical principle placing protection of public health, safety and welfare above employer or client loyalty. Engineers must escalate unresolved safety concerns rather than stay silent.
- Conflict of interest
- Situation where personal or financial interest could improperly influence professional judgement. It must be disclosed promptly and, where material, the affected decision avoided.
- Sealing documents
- Affixing a professional seal certifies personal responsibility for the work. An engineer should seal only documents they prepared or directly supervised and reviewed.
- Availability formula
- Availability = MTBF/(MTBF + MTTR). It expresses the fraction of time equipment is operable; shortening repair time raises availability as effectively as improving reliability.
- Bathtub curve
- Failure-rate pattern over asset life: decreasing infant mortality, constant useful-life failures, then increasing wear-out failures. Maintenance strategy should differ for each region.
- Overall equipment effectiveness
- OEE = availability × performance × quality. It combines downtime, speed losses and defect losses into one measure; roughly 85 percent is considered world-class.
- Series system reliability
- System reliability equals the product of component reliabilities, so it is always lower than the least reliable component. Adding parallel redundancy is the usual way to raise it.
- Earned value management
- Method integrating scope, schedule and cost by comparing earned value with planned value and actual cost, yielding schedule and cost performance indices for forecasting.
- Stress concentration factor
- Kt is the ratio of peak local stress at a geometric discontinuity to nominal stress. It amplifies the alternating stress in fatigue assessment of notches, holes and fillets.
- Corrosion allowance
- Extra material thickness added to pressure equipment so that expected in-service corrosion does not reduce the wall below the minimum required thickness during design life.
- Predictive maintenance
- Condition-based maintenance triggered by measured indicators such as vibration, temperature or oil analysis. It schedules intervention before functional failure, reducing unplanned downtime.