OFTEC Heat Pump study materials
OFTEC Heat Pump study resources

OFTEC Heat Pump cheat sheet

OFTEC Heat Pump · Keep the key ideas within reach.

Quick reference

Heat Pump System Design and Sizing

  • Design heat loss is calculated room by room using the fabric U-values, ventilation/infiltration allowance and the design external temperature (commonly -3 °C to -5 °C in the UK); the heat pump is sized to the whole-dwelling total, not to boiler output.

  • Heat pump output falls with source temperature: an air-source unit rated 10 kW at 7 °C ambient may deliver only 6-7 kW at -5 °C, so sizing must use the output at design ambient, not the nominal A7/W35 rating.

  • Heat emitter output is governed by the mean water temperature above room temperature; a radiator rated at ΔT50 (e.g. 75/65/20 °C) delivers roughly half its rated output at ΔT30 (55/45/20 °C), so oversizing emitters is normal in retrofit.

  • Flow temperature drives efficiency: design to the lowest achievable flow temperature (35-45 °C for underfloor, 45-55 °C for well-sized radiators); every 1 °C reduction in flow temperature improves COP by roughly 2-3 %.

  • SCOP/SPF is seasonal performance including defrost, cycling and standby; a good air-source SCOP is around 3.0-3.5 for radiators at 45-50 °C and 4.0+ for underfloor at 35 °C, while ground-source typically achieves 4.0-4.5.

  • Domestic hot water cylinder sizing: allow roughly 40-50 litres per occupant for a cylinder heated to 48-55 °C, with a coil/heat-exchanger surface sized for the heat pump's lower flow temperature and a legionella cycle to 60 °C.

  • Buffer volume rule of thumb: provide 10-20 litres of buffer per kW of heat pump output where system water volume is low, to prevent short cycling and to give defrost energy on air-source units.

  • Pipe sizing and pump head: keep design flow velocity below about 1.0-1.5 m/s in primary pipework and check available external static pressure; heat pumps need higher flow rates than boilers because of the smaller ΔT (typically 5-7 K, not 11-20 K).

Quick reference

Heat Pump Installation and Commissioning

  • Outdoor unit siting: maintain manufacturer clearances (commonly 300-1000 mm) for airflow and service access, avoid recirculation of discharge air, and mount on anti-vibration feet or brackets rated for the unit weight plus snow load.

  • Refrigerant pipework: pressure-test with dry nitrogen (typically to 1.5x design pressure or per manufacturer, e.g. 40+ bar), then evacuate to below 500 microns (about 66 Pa) and hold a vacuum decay test before releasing charge.

  • Flushing and water treatment: flush the system to remove debris, fit a magnetic filter and dose with corrosion inhibitor and biocide; glycol antifreeze is required where the outdoor unit or exposed pipework can freeze.

  • Fill and vent thoroughly: air in the system causes high flow temperatures, noise and reduced COP; commission with all vents open, then record flow rate and differential pressure across the heat exchanger.

  • Commissioning records must include: design and actual flow rate, flow and return temperatures, compressor/ambient readings, measured electrical input, calculated COP, refrigerant type and charge weight, and the completed benchmark/commissioning checklist.

  • Controls set-up: configure weather compensation curve, DHW schedule and legionella cycle, set the heat pump to the correct capacity/defrost parameters, and confirm the back-up heater is locked out or staged correctly.

  • Electrical supply: heat pumps are continuous loads; size the dedicated circuit with diversity NOT applied (no cooker/immersion diversity), check supply capacity and earthing, and install Type A or Type B RCD as required by the manufacturer.

  • Handover: demonstrate operation to the occupant, provide the MCS/installation certificate, warranty registration, user manual and a maintenance schedule; record the measured SPF or metered performance where monitoring is fitted.

Quick reference

Electrical and Controls Work for Renewable Heating

  • Heat pump circuits are treated as continuous maximum demand: protective device and cable are sized to the full rated input (including back-up heater and crankcase heater) with no diversity applied.

  • Cable sizing uses the standard formula: Ib ≤ In ≤ Iz, with correction factors for ambient temperature, grouping, thermal insulation and installation method applied to Iz.

  • Voltage drop should not exceed 3 % for lighting and 5 % for other circuits (BS 7671 guidance); long runs to outdoor units frequently fail this and require a larger conductor.

  • RCD selection: manufacturers commonly require Type A (or Type B where DC components are present) at 30 mA for socket outlets, or 300 mA for fixed equipment per manufacturer instructions; check the inverter's DC leakage guidance.

  • Earthing and bonding: confirm the means of earthing and main protective bonding of incoming metallic services; heat pump outdoor units need equipotential bonding where extraneous conductive parts are present.

  • Outdoor unit isolator: fit a lockable, weatherproof local isolator within sight of the unit, plus a means of isolation at the consumer unit, and label the circuit clearly.

  • Controls wiring: use manufacturer-specified cable for sensor and communication buses (screened where required), keep sensor leads separate from power cables, and observe polarity on modulating/0-10 V or bus connections.

  • Notification and certification: heat pump installations are notifiable in England and Wales (Part P applies to the electrical work); issue an Electrical Installation Certificate or Minor Works Certificate and a Building Regulations compliance certificate.

Quick reference

Service, Maintenance and Regulatory Compliance

  • Annual service scope: check refrigerant pressures/charge and look for leaks, clean evaporator and condenser coils, check fan blades and motor, inspect electrical connections and contactors, verify safety devices and record flow temperatures and COP.

  • Refrigerant handling: F-gas regulations require certificated personnel, leak checks at intervals based on CO2-equivalent charge (e.g. 5 t CO2e or more triggers periodic checks), and records of charge added or recovered.

  • Legionella control: stored DHW should be raised to at least 60 °C periodically (typically weekly) with distribution reaching 55 °C; record the cycle and any temperature log as part of the risk assessment.

  • Water quality: check inhibitor concentration, pH (typically 6.5-8.5), and glycol strength at service; top up and record; replace magnetic filter elements and clean strainers.

  • Compliance: MCS certification (or equivalent) is required for government grant eligibility and building control sign-off; installations must comply with Building Regulations Part L (conservation of fuel and power) and Part P for electrical work.

  • F-gas and ODS records: maintain a log of equipment, refrigerant type, charge, leak test dates and engineer certification; keep records available for inspection.

  • Performance review: compare measured SPF/COP and electricity consumption against design; falling COP with rising flow temperature indicates fouling, low charge, air or emitter problems.

  • Breakdown decision rules: high-pressure trips point to poor airflow or overcharge; low-pressure trips to leak or restriction; frequent defrost cycles to coil icing or sensor faults; check fault codes before replacing parts.