- Design heat loss
- The calculated whole-dwelling heat requirement at design external temperature, summing fabric and ventilation losses room by room. It determines heat pump capacity and must be used instead of boiler output.
- Output at design ambient
- Air-source heat pump capacity falls as outdoor temperature drops. Sizing must use the manufacturer's output at the design ambient (e.g. -3 °C), not the nominal A7/W35 rating.
- Delta-T emitter rating
- Radiator output depends on mean water temperature minus room temperature. A radiator rated at ΔT50 delivers roughly half its rated output at ΔT30, so emitters are usually oversized in retrofit.
- Flow temperature and COP
- Lower flow temperatures improve efficiency: each 1 °C reduction typically improves COP by about 2-3 %. Design to the lowest flow temperature the emitters can support.
- SCOP versus COP
- COP is an instantaneous ratio at one operating point; SCOP is the seasonal average including defrost, cycling and standby. SCOP is the realistic figure for design and comparison.
- DHW cylinder sizing
- Allow roughly 40-50 litres per occupant, stored at 48-55 °C with a legionella cycle to 60 °C. The coil must be sized for the heat pump's lower flow temperature.
- Buffer vessel rule
- Provide about 10-20 litres of buffer per kW of heat pump output where system water volume is low, to prevent short cycling and supply defrost energy.
- Heat pump flow rate
- Heat pumps use a smaller temperature difference (typically 5-7 K) than boilers, so design flow rates are higher. Keep primary velocities below about 1.0-1.5 m/s.
- Outdoor unit clearances
- Maintain manufacturer-specified clearances (commonly 300-1000 mm) for airflow and service access, avoid discharge air recirculation, and mount on vibration-isolating brackets.
- Pressure test and evacuation
- Pressure-test refrigerant pipework with dry nitrogen, then evacuate to below about 500 microns (66 Pa) and confirm a vacuum decay test before releasing refrigerant charge.
- System flushing and dosing
- Flush the water circuit to remove debris, fit a magnetic filter, and dose with corrosion inhibitor and biocide. Add glycol where pipework or the outdoor unit can freeze.
- Commissioning record contents
- Record design and actual flow rate, flow and return temperatures, ambient and compressor readings, electrical input, calculated COP, refrigerant charge and the completed commissioning checklist.
- Weather compensation set-up
- Configure the heating curve so flow temperature falls as outdoor temperature rises. Confirm DHW schedule, legionella cycle and correct staging or lockout of the back-up heater.
- No diversity on heat pumps
- Heat pump circuits are continuous loads. Size the protective device and cable to the full rated input, including back-up heater and crankcase heater, without applying diversity.
- Handover documentation
- Provide installation certificate, warranty registration, user manual, maintenance schedule and a demonstration of operation, plus metered performance records where monitoring is fitted.
- Ib ≤ In ≤ Iz
- Design current must not exceed the protective device rating, which must not exceed the corrected current-carrying capacity of the cable. Correction factors apply to Iz.
- Voltage drop limits
- BS 7671 guidance limits voltage drop to 3 % for lighting and 5 % for other circuits. Long runs to outdoor units often require a larger conductor.
- RCD type selection
- Inverter-driven heat pumps may produce DC residual current. Manufacturers commonly specify Type A or Type B RCDs; always follow the manufacturer's instructions and check DC leakage guidance.
- Outdoor unit isolator
- Fit a lockable, weatherproof local isolator within sight of the outdoor unit, plus isolation at the consumer unit, and label the circuit clearly.
- Sensor cable separation
- Use manufacturer-specified screened cable for sensors and communication buses, keep sensor leads away from power cables, and observe polarity on bus or 0-10 V connections.
- Part P notification
- Electrical work for heat pumps is notifiable in England and Wales. Issue an Electrical Installation Certificate or Minor Works Certificate and a Building Regulations compliance certificate.
- Earthing and bonding checks
- Confirm the means of earthing and main protective bonding of incoming metallic services. Bond extraneous conductive parts at the outdoor unit where present.
- Continuous load sizing
- Because heat pumps run for long periods at full input, protective devices and cables must be rated for continuous duty, not intermittent boiler-style loads.
- Annual service scope
- Check refrigerant charge and leaks, clean coils, inspect fan and electrical connections, test safety devices, and record flow temperatures, electrical input and calculated COP.
- F-gas leak check intervals
- F-gas rules require certificated engineers and periodic leak checks based on CO2-equivalent charge, with records of charge added or recovered kept available for inspection.
- Legionella control cycle
- Raise stored hot water to at least 60 °C periodically, typically weekly, with distribution reaching 55 °C. Record the cycle and temperatures as part of the risk assessment.
- Water quality checks
- At service, check inhibitor concentration, pH (typically 6.5-8.5) and glycol strength, top up as needed, replace filter elements and clean strainers.
- MCS and Building Regulations
- MCS certification supports grant eligibility and sign-off. Installations must comply with Part L for energy efficiency and Part P for electrical work.
- High-pressure trip causes
- High-pressure faults usually indicate restricted airflow, fouled coil, overcharge or low water flow. Check fans, coils and flow rate before adjusting charge.
- Low-pressure trip causes
- Low-pressure faults typically indicate refrigerant leak, restriction in the pipework or a faulty sensor. Leak-test and verify charge before resetting.
- Frequent defrost diagnosis
- Repeated defrost cycles point to iced coils, faulty defrost sensors, blocked drainage or low refrigerant charge. Check sensors and drain paths before parts replacement.
- Performance trend review
- Compare measured SPF and electricity use with design. Falling COP with rising flow temperature suggests fouling, low charge, air in the system or undersized emitters.