SOLAS Bricklaying study materials
SOLAS Bricklaying study resources

SOLAS Bricklaying flashcards

SOLAS Bricklaying · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Coordinating size of a brick
The nominal size of a brick plus its joint: 225 mm x 112.5 mm x 75 mm for a standard UK brick, used for setting out and calculating brick quantities.
Bricks per square metre
A half-brick wall in standard bricks requires 60 bricks per square metre; a one-brick wall requires 120 bricks per square metre, allowing for 10 mm joints.
English bond
A bond with alternating courses of all stretchers and all headers, giving strong walls with no continuous vertical joints; the strongest traditional bond for one-brick walls.
Flemish bond
A bond in which each course alternates a stretcher and a header, producing a decorative face pattern; weaker than English bond but more attractive.
Stretcher bond
A bond where all bricks are laid lengthwise with joints offset by half a brick; used mainly for half-brick walls and cavity leaves, not for one-brick walls.
3-4-5 method
A setting-out technique using a triangle with sides in the ratio 3:4:5 to establish a right angle at a corner before building begins.
Gauge rod
A marked staff with course heights at 75 mm intervals (65 mm brick plus 10 mm joint) used to keep courses level and bed joints consistent.
Mortar mix 1:1:6
One part cement, one part lime and six parts sand by volume; a general-purpose mortar suitable for normal exposure and most brickwork above DPC.
Mortar mix 1:1/4:3
One part cement, a quarter part lime and three parts sand; a strong mortar used below DPC, in exposed positions and for engineering bricks.
Damp-proof course height
The DPC must be at least 150 mm above finished external ground level to prevent rising damp entering the building fabric.
Wall tie spacing
Cavity wall ties are fixed at maximum 900 mm horizontal and 450 mm vertical centres, with extra ties at openings and edges.
Wall tie slope
Ties should slope slightly downwards towards the outer leaf so any water reaching them drains outwards rather than into the inner leaf.
Movement joint spacing
Clay brickwork typically needs movement joints at 10-12 m centres; concrete brickwork at about 6 m, and always at changes of height or material.
Frost resistance classes
Bricks are classed F0, F1 or F2 for frost resistance; F2 is required for severe exposure and for brickwork below DPC.
Brick compressive strength class
Bricks are designated by strength in N/mm2 (e.g. 10, 20, 30); the class must suit the structural and exposure requirements of the wall.
Cavity width
The clear cavity between leaves is commonly 50-100 mm; it must be kept clear of mortar droppings to preserve thermal and weather performance.
Cavity board
A board or batten pulled up the cavity as work proceeds to catch mortar droppings and stop them bridging the cavity and blocking weep holes.
Weep holes
Open vertical joints left in the outer leaf above flashings and DPCs, typically at 900 mm centres, to allow water to drain from the cavity.
Half-brick lap
The minimum overlap between bricks in a half-brick wall is a quarter brick; in a one-brick wall a quarter brick lap is also required for bonding.
Quoin
The corner brickwork of a wall, built with alternating headers and stretchers to tie the two faces and provide a true, plumb corner.
Range work
Brickwork built between two profiles or corner quoins, with a line strained between them to keep courses straight and level.
Profiles
Timber or metal frames set at corners showing the line and level of each course, used to stretch the building line for accurate range work.
Bed joint thickness
Standard bed and perp joints are 10 mm; consistent joints control course height and the 75 mm coordinating gauge.
Perp joint
The vertical joint between the ends of bricks in a course; it must be fully filled with mortar for strength and weather resistance.
Tooting
Filling the vertical perp joint after laying the brick by pressing mortar into the joint from the face, used where full jointing is difficult.
Sulphate-resisting cement
A cement used in mortar below DPC or in sulphate-bearing ground to prevent expansion and deterioration of the brickwork.
Engineering bricks
Dense, strong, low-absorption bricks (classes A and B) used below DPC, in retaining walls and in severe exposure situations.
Frog
The indentation in one bed face of a brick; the frog is laid upwards and filled with mortar to improve the bond and strength of the wall.
Plumb rule
A straightedge with a spirit level or plumb line used to check that corners and faces of brickwork are truly vertical.
Soldier course
A course of bricks laid on end with the stretcher face showing, commonly used as a decorative course or above openings.
Lintel bearing
A lintel should have a minimum bearing of 150 mm on each side of an opening unless designed otherwise, to transfer loads safely.
Brick bonding at openings
Bricks around openings must be bonded into the wall, and wall ties or reinforcement provided to control cracking at the corners of the opening.