Hydraulic system pressure is set by the relief valve, not the pump: pump displacement sets flow, relief valve setting caps pressure, so a slow-but-strong machine points to flow loss (worn pump, clogged suction strainer, aerated oil) while a weak-but-fast machine points to relief or cylinder seal leakage.
Hydraulic hose selection rule: working pressure rating must be at least 4x the system's maximum continuous pressure for pulsating plant circuits; burst rating is typically 4x working pressure, so never size hose from burst figures.
Cylinder force = pressure x piston area (bore area minus rod area on the retract side); a 100 mm bore at 200 bar gives about 157 kN extend, but the retract force is lower because rod area is subtracted.
Contamination target for plant hydraulics is ISO 4406 cleanliness around 18/16/13 for general circuits and 16/14/11 for servo or proportional controls; water ingress above 0.05% by volume accelerates corrosion and oil breakdown.
Torque rule for structural and running gear bolts: use the manufacturer's torque table plus thread lubricant condition; a torque wrench only measures applied torque, so bolt preload varies with friction and torque-to-yield bolts must be replaced, not reused.
Diesel engine no-start diagnosis order: confirm cranking speed and battery voltage (above 9.6 V during crank on 12 V systems), then fuel supply and air in lines, then compression and timing; do not chase electrical faults before confirming fuel delivery at the injectors.
Cooling system: a 50/50 glycol mix raises boiling point and lowers freeze point; pressure caps raise boiling point about 3 degrees C per 0.1 bar, so a failed cap causes overheating under load while the gauge reads normal at idle.
Outrigger and stability rule: rated capacity charts assume firm level ground and full outrigger extension; capacity falls sharply with radius, so never interpolate beyond the chart or rely on tilt/load moment indicators as a substitute for the chart.
Lockout/tagout before any maintenance on plant: isolate all energy sources including hydraulic accumulators (bleed to zero), gravity-loaded implements (block or lower), and stored spring energy; verify zero energy at the point of work before disassembly.