Israel Electrician Licensing Exam study materials
Israel Electrician Licensing Exam study resources

Israel Electrician Licensing Exam cheat sheet

Israel Electrician Licensing Exam · Keep the key ideas within reach.

Quick reference

Electrical Theory and Fundamentals

  • Ohm's law: U = I × R; power P = U × I = I²R = U²/R. In AC, use rms values unless stated otherwise.

  • Three-phase power: P = √3 × U_L × I_L × cosφ for balanced loads; reactive power Q = √3 × U_L × I_L × sinφ.

  • Series circuit: same current everywhere, resistances add, voltages divide in proportion to resistance.

  • Parallel circuit: same voltage across branches, conductances add (1/R_total = Σ1/R_i), currents divide inversely with resistance.

  • Impedance: Z = √(R² + X²); inductive reactance X_L = 2πfL, capacitive reactance X_C = 1/(2πfC).

  • Power factor cosφ = P/S; correction capacitors reduce reactive current without changing active power.

  • Kirchhoff's laws: sum of currents at a node is zero; sum of voltages around a closed loop is zero.

  • RMS and peak: for a sine wave U_rms = U_peak/√2 ≈ 0.707 × U_peak; Israeli low-voltage supply is 230 V phase-to-neutral, 400 V phase-to-phase, 50 Hz.

Quick reference

Electrical Installation Design and Calculations

  • Design current I_b must satisfy I_b ≤ I_n ≤ I_z, where I_n is the protective device rating and I_z the cable current-carrying capacity.

  • Voltage drop limit for final circuits in consumer installations is commonly 3% and for the whole installation from origin 5%; verify against SI 100 requirements.

  • Cable sizing: apply correction factors for ambient temperature, grouping, thermal insulation and installation method to the tabulated capacity.

  • Diversity/demand factors allow summing expected simultaneous load rather than connected load; document assumptions in the design.

  • Motor circuits: size for starting current; use I_b based on rated current plus appropriate starting allowance, and coordinate protection with the motor's starting characteristic.

  • Short-circuit withstand: k²S² ≥ I²t, where k depends on conductor material and insulation, S is conductor cross-section, I and t are fault current and clearing time.

  • Protective conductor sizing: typically equal to phase conductor up to 16 mm², 16 mm² for 16-35 mm², and half the phase conductor above 35 mm² (subject to adiabatic check).

  • Neutral conductor may be reduced only where harmonics are low and the load is balanced; for significant triplen harmonics keep full neutral or oversize.

Quick reference

Wiring Systems, Cables, and Protection Devices

  • Cable designation encodes conductor material, insulation, sheath and features (e.g., copper XLPE-insulated, PVC-sheathed); read the code before selecting for a location.

  • MCB types: B trips at 3-5×I_n, C at 5-10×I_n, D at 10-20×I_n; choose type to ride through inrush while clearing faults.

  • RCD sensitivity: 30 mA for socket circuits and additional protection; 300 mA or selective types for fire protection and upstream selectivity.

  • RCBO combines overcurrent and residual-current protection in one device; RCCB provides residual current protection only and needs separate overcurrent protection.

  • Cable installation methods (in conduit in wall, clipped direct, in thermal insulation, buried) each have a distinct current-carrying capacity reference column.

  • Minimum cross-sections: lighting circuits commonly 1.5 mm², socket circuits 2.5 mm², with larger sizes per load; always confirm against SI 100 tables.

  • Fuses and MCBs protect against overload and short circuit; they do not replace RCD protection against electric shock.

  • Cable derating for grouping: multiple circuits in one conduit or trunking require a grouping factor below 1.0 applied to tabulated capacity.

Quick reference

Earthing, Bonding, and Protection Against Electric Shock

  • TN-S: separate neutral and protective conductors from the source; TN-C-S: combined PEN split into PE and N at the origin; TT: installation earth electrode independent of the supply neutral.

  • In TT systems, disconnection relies on RCDs; the earth electrode resistance R_A must satisfy R_A ≤ 50 V / I_Δn.

  • In TN systems, disconnection time depends on the earth-fault loop impedance Z_s: Z_s ≤ U_0 / I_a, where I_a is the current that trips the device within the required time.

  • Maximum disconnection times for 230/400 V final circuits are typically 0.4 s (TN) and 0.2 s (TT) for socket circuits up to 32 A; 5 s permitted for distribution circuits per SI 100.

  • Main equipotential bonding connects metallic water, gas and structural services at the origin with a conductor sized per the incoming supply neutral/phase.

  • Supplementary bonding ties together exposed and extraneous conductive parts in a location to reduce touch voltage, independent of the main earthing terminal.

  • Touch voltage limit in normal dry conditions is generally 50 V AC; in wet or special locations lower values and additional protection apply.

  • Earth electrode resistance can be reduced by deeper rods, multiple rods spaced at least their length apart, or chemical/backfill enhancement.

Quick reference

Safety at Work, Electrical Hazards, and First Aid

  • Five safety rules before work: disconnect, secure against reconnection, verify absence of voltage, earth and short-circuit, and protect adjacent live parts.

  • Electric shock effects: ventricular fibrillation risk rises sharply above 30 mA; 30 mA RCDs are chosen for additional protection for this reason.

  • Arc flash: do not approach; de-energize upstream, wear appropriate arc-rated PPE, and treat all conductors as live until verified.

  • First aid for electric shock: isolate the supply safely, call emergency services, check breathing and pulse, begin CPR if trained, and use an AED if available.

  • Burns from electric arcs: cool with water, do not remove stuck clothing, and seek medical evaluation even for apparently minor contact.

  • Live working is permitted only with a written permit, suitable tools, PPE, and a second competent person present; otherwise work de-energized.

  • Lockout/tagout: each worker applies a personal lock and tag; only the person who applied a lock removes it, following documented procedure.

  • Step and touch voltage hazards near fallen HV conductors: keep a wide distance and shuffle or hop away rather than stride.

Quick reference

Israeli Electrical Code and Standards (SI 100, SI 900, etc.)

  • SI 100 is the Israeli National Electrical Code (חוק החשמל and its regulations); it governs installation requirements for low-voltage installations.

  • SI 900 covers electrical installations in residential buildings and sets requirements for dwelling circuits, socket outlets and protection.

  • The Electricity Law (חוק החשמל) and the Electricity Regulations (תקנות החשמל) set licensing, inspection and safety obligations for electricians and installations.

  • Israeli low-voltage supply is 230 V / 400 V, 50 Hz, with a MEN-like combined neutral-earth arrangement at the origin; installations are typically TN-C-S.

  • Work on installations requires a licensed electrician with the appropriate class (e.g., practical electrician, electrician, electrical engineer) and a Form 1/Form 2 inspection certificate as applicable.

  • SI 100 requires RCD protection for socket circuits and for circuits in wet locations; verify current amendment because requirements are updated periodically.

  • Special locations (bathrooms, swimming pools, construction sites, medical) follow dedicated SI 100 sections with stricter zoning and protection rules.

  • New or modified installations require inspection and testing by an authorized tester before energization, with results recorded on the official inspection form.

Quick reference

Inspection, Testing, and Fault Diagnosis

  • Dead tests before energization: continuity of protective conductors, continuity of ring final circuits, insulation resistance, polarity, and earth electrode resistance.

  • Insulation resistance test: apply typically 500 V DC and require at least 1 MΩ for a healthy low-voltage installation; investigate lower readings.

  • Earth-fault loop impedance test (live) confirms protective device will disconnect within the required time; compare with Z_s limits.

  • RCD test: verify trip current and trip time at I_Δn and 5×I_Δn using a calibrated tester; record both values.

  • Continuity of protective conductors uses a low-resistance ohmmeter; null the test leads before measuring to avoid lead resistance error.

  • Polarity check ensures line is switched and connected to the correct socket terminal; reversed polarity is a common and dangerous fault.

  • Fault diagnosis sequence: gather symptoms, isolate, test for voltage, check continuity and insulation, then examine terminations and devices before replacing parts.

  • Test instruments require valid calibration certificates; record instrument serial numbers and calibration dates on the inspection report.

Quick reference

Electrical Machines, Transformers, and Motors

  • Transformer EMF equation: E = 4.44 × f × N × Φ_max; turns ratio V1/V2 = N1/N2, and for an ideal transformer V1I1 = V2I2.

  • Synchronous speed n_s = 120 × f / p (rpm), where p is the number of poles; induction motors run slightly slower at slip s = (n_s − n)/n_s.

  • Motor torque is proportional to the square of the applied voltage for an induction motor; undervoltage causes overheating and starting failure.

  • Star-delta starting reduces starting current and torque to one third of direct-on-line values; use only where load torque permits.

  • Direction of rotation of a three-phase motor is reversed by swapping any two of the three supply phases.

  • Motor protection: thermal overload relay for sustained overload, short-circuit protection for faults, and phase-failure/undervoltage protection where required.

  • Transformer losses: copper losses vary with load squared (I²R), iron losses are essentially constant; maximum efficiency occurs when copper losses equal iron losses.

  • Motor nameplate data (voltage, current, power factor, duty, insulation class, IP rating) must match the supply and environment before installation.