Pricing and Varying a Four-Way Motor Control Panel

Odisha CHSE +2 VOC-ITV Wireman Control Panel · Put your knowledge to work in context.

All case studies

Pricing and Varying a Four-Way Motor Control Panel

A small panel-building firm quotes for a 4-way motor control panel for a rice mill: one 63 A 4-pole MCCB incomer, three DOL feeders for 2.2 kW motors (9 A contactors, 4–6 A thermal relays, start/stop push buttons, run lamps), and one blank spare bay. The quoted rates are: CRCA sheet 2 mm, 3.0 m² at ₹700/m²; powder coating 3.0 m² at ₹250/m²; MCCB ₹2,400; contactors ₹850 each; relays ₹700 each; push-button sets ₹180 each; lamps ₹120 each; wire, lugs, busbar and terminals ₹1,800; glands and miscellaneous ₹450. Wastage is allowed at 5 % on sheet and wire only. Fabrication takes 8 h at ₹180/h, wiring 10 h at ₹150/h and testing 2 h at ₹150/h. Overhead is 8 % of direct cost and profit 12 % on the overhead-inclusive cost; GST is 18 %. The customer's budget is ₹25,000 including GST.

1. Build the price and decide whether the order can be accepted within the customer's budget.

Read the worked answer
Item Calculation ₹
Sheet 2 mm 3.0 × 700 2,100
Powder coating 3.0 × 250 750
MCCB 63 A 4P 1 × 2,400 2,400
Contactors 3 × 850 2,550
Thermal relays 3 × 700 2,100
Push-button sets 3 × 180 540
Lamps 3 × 120 360
Wire, lugs, busbar, terminals - 1,800
Glands, misc. - 450
Material subtotal 13,050
Wastage 5 % of 2,100 + 5 % of 1,800 195
Material incl. wastage 13,245
Labour 8×180 + 10×150 + 2×150 3,240
Direct cost 16,485
Overhead 8 % 0.08 × 16,485 1,318.80
Cost before profit 17,803.80
Profit 12 % 0.12 × 17,803.80 2,136.46
Price before GST 19,940.26
GST 18 % 0.18 × 19,940.26 3,589.25
Quoted price 23,529.51 ≈ 23,530

Against a ₹25,000 budget the quote leaves ₹1,470 (5.9 % of the budget) as headroom. Accept the order, but state a quotation validity of about 15 days because copper and sheet prices move, and specify the make and rating of the MCCB and contactors so a cheaper substitute is not assumed later.

2. The customer now wants the spare bay fitted as a fourth DOL feeder but will not pay more than ₹25,000. What do you do?

Read the worked answer

Cost the addition honestly:

  • Extra material: contactor 850 + relay 700 + push-button set 180 + lamp 120 + wire/lugs 150 = ₹2,000; wastage 5 % on wire = ₹7.50 → ₹2,007.50.
  • Extra labour: 2 h wiring/commissioning × ₹150 = ₹300.
  • Extra direct cost = ₹2,307.50.
  • With 8 % overhead (₹184.60) and 12 % profit (₹299.05): ₹2,791.15 before GST; with 18 % GST: ₹3,293.56.
  • New price = 23,529.51 + 3,293.56 ≈ ₹26,823.

To hold ₹25,000 including GST, the pre-GST price can only be ₹25,000/1.18 = ₹21,186. Against an overhead-inclusive cost of 18,792.50 × 1.08 = ₹20,295.90, that leaves about ₹890 profit - roughly 4.4 % on cost instead of 12 %. That removes the buffer for wastage and rework and is not a decision to make informally.

Recommended action: issue a written variation at about ₹26,800 for the fourth feeder, or hold ₹25,000 only by deleting a defined scope item with the customer's signature. Never absorb the extra silently; it teaches the customer that quoted prices are negotiable after the order.

3. What maintenance schedule and spares would you hand over with this panel?

Read the worked answer

Handover pack:

  • Drawings: single-line diagram, terminal numbering, relay settings, cable schedule.
  • Test sheets: insulation resistance at 500 V (record actual value), earth continuity, phase sequence, contactor pick-up/drop-out, relay trip test.

Maintenance schedule:

  • Monthly: visual check for dust, smell and discoloured terminals; check door gasket and fan filter; confirm lamps and push buttons.
  • Every 6 months: torque all power terminals to the manufacturer's value; inspect contactor tips and arc chutes; clean; confirm the relay dial is still at the set value and has not drifted.
  • Annually: insulation resistance test, thermographic scan under load, relay injection test, earth resistance test.
  • Every 2,000 operations or on pitting: replace contactor tips or the contactor.

Spares to stock: one contactor, one thermal relay, one push-button set, one lamp, fuses and terminal blocks.

A log card should record every trip with its current and cause. A repeated trip is data, not a nuisance.