Installation, Commissioning and Testing

Before the pipe is cut

Site survey decides everything: indoor unit clearances, outdoor airflow, wall strength, drain fall and the electrical point. Follow the manual for minimum and maximum pipe length, maximum elevation and additional charge per metre; typical domestic splits allow 3–15 m of run and 5–10 m of level difference. Fit an oil trap where the outdoor unit sits above the indoor coil.

The sequence that earns marks

  1. Mount brackets and hang units level.
  2. Flare and torque connections to the specified value - do not over-torque.
  3. Braze with dry nitrogen flowing through the pipe to prevent internal oxidation.
  4. Pressure test with dry nitrogen at the specified test pressure (often 1.5× working pressure) and hold it.
  5. Evacuate to 500 microns (about 66 Pa) and hold for at least 30 minutes; a rise means moisture or a leak.
  6. Release or charge refrigerant by weight, then record it.
  7. Check drain slope, insulation, earthing and insulation resistance.

Worked example

A free pipe limit of 5 m, but the site needs 12 m, and the manual says add 20 g/m beyond 5 m. Additional charge = (12 − 5) × 20 = 140 g, added as liquid, then verified by subcooling of 5–8 K at the condenser outlet.

Traps

Brazing without nitrogen, so scale ends up in the TXV; using the compressor as a vacuum pump; skipping the standing vacuum test; and commissioning without recording ambient temperature, pressures and superheat.