III IC-86 study materials
III IC-86 study resources

III IC-86 cheat sheet

III IC-86 · Keep the key ideas within reach.

Quick reference

Risk Management

  • Risk = uncertainty that matters; it has two measurable components: probability (or likelihood) of occurrence and impact (severity of consequence) on objectives.

  • Risk management process order: establish context → identify risks → analyze risks → evaluate risks → treat risks → monitor and review → communicate and consult. Communication and monitoring are continuous, not single end-of-cycle steps.

  • Qualitative analysis ranks risks by likelihood × impact using scales or a matrix; quantitative analysis assigns monetary or numeric values (EMV, Monte Carlo, decision trees) to compare risks and options.

  • Expected Monetary Value (EMV) = probability × monetary impact. For a risk with 20% chance of a $50,000 loss, EMV = 0.20 × (−50,000) = −$10,000; sum EMVs of all risks in a branch to compare alternatives.

  • Risk response strategies for threats: avoid (eliminate the cause), transfer (shift financial consequence, e.g., insurance, contracts), mitigate (reduce probability or impact), accept (retain, active acceptance funds a contingency reserve).

  • Risk response strategies for opportunities: exploit, share, enhance, accept. Selecting a response is a decision rule: choose the option whose cost is less than the expected reduction in exposure.

  • Risk register records: risk ID, description, cause, potential effect, probability, impact, risk score, owner, response plan, residual risk, status, and trigger/early-warning indicator.

  • Residual risk is exposure remaining after treatment; secondary risk is a new risk created by the response itself. Both must be re-entered and monitored in the register.

  • Risk appetite is the amount of risk an organization is willing to pursue or retain; risk tolerance is the acceptable measurable variation around that appetite. Thresholds beyond tolerance trigger escalation.

Quick reference

Risk Management (continued)

  • Contingency reserve covers known-unknowns (identified risks) and sits under the owner's control; management reserve covers unknown-unknowns and requires higher-level approval to release.

  • Risk breakdown structure (RBS) organizes risk categories hierarchically (technical, external, organizational, commercial) to ensure identification covers all sources rather than only obvious ones.

  • Risk audit compares actual response effectiveness against the plan; variance and trend analysis track how risk exposure changes over time using the risk register's score history.

  • A risk trigger is a defined condition or event signaling that a risk is about to occur; its detection activates the contingency plan.

  • Probability-impact matrix zones: high-probability/high-impact risks require immediate action; low-probability/low-impact risks are typically placed on a watch list rather than actively treated.

Quick reference

Risk Management (governance and controls)

  • Risk owner is accountable for managing a specific risk and its response; risk action owner executes individual response actions. Accountability is not delegated with the action.

  • Inherent risk is exposure before controls; residual risk is exposure after controls. Control effectiveness = (inherent − residual) / inherent, expressed as a percentage of risk removed.

  • Four treatment options in a general risk framework: tolerate (accept), treat (mitigate), transfer, terminate (avoid). Selection depends on whether residual risk falls within tolerance.

  • Key risk indicators (KRIs) are leading metrics with defined thresholds; breaching a threshold escalates the risk. Key performance indicators measure outcomes, not exposure.

  • Three lines model: operational management owns risk (first line), risk/compliance functions monitor and advise (second line), internal audit provides independent assurance (third line).

  • Risk heat map plots likelihood against impact; position determines priority, and the map is refreshed after each treatment cycle to show residual exposure.

  • Risk register review cadence is set by risk velocity: fast-moving risks (regulatory, cyber) are reviewed more frequently than slow-moving strategic risks.

Quick reference

Risk Management (quantitative and reporting)

  • Monte Carlo simulation runs many iterations of input distributions to produce a probability distribution of outcomes; output supports confidence-level estimates (e.g., P80 cost).

  • Decision tree expected value = sum over branches of (branch probability × branch outcome value); choose the branch with the highest expected value, then subtract option cost.

  • Sensitivity analysis (tornado diagram) ranks which variables most affect the outcome; it identifies the drivers worth monitoring rather than predicting a single result.

  • Value at Risk (VaR) states the maximum loss at a given confidence level over a defined horizon; it does not describe the size of losses beyond that threshold (tail risk).

  • Risk reporting to governance should state exposure against appetite, trend direction, top risks with owners, and the status of treatment actions - not just a list of risks.

  • Risk velocity = impact per unit time to occurrence; a high-velocity risk needs pre-approved response plans because there is no time to design a response after the trigger fires.

Quick reference

Risk Management (identification and assessment detail)

  • Identification techniques: brainstorming, Delphi (anonymous consensus rounds), interviews, checklist analysis, assumption analysis, SWOT, and root-cause analysis of prior incidents.

  • Assumption analysis surfaces risks hidden in unvalidated project or business assumptions; each invalid assumption is a potential risk with its own probability and impact.

  • Risk score = probability rating × impact rating on a defined scale (e.g., 1–5); scores are comparable only within the same scale and matrix definition.

  • Risk categorization by cause enables portfolio-level aggregation: many individually small risks in one category can combine into a material exposure.

  • Documented risk criteria (scales, thresholds, appetite) must be set before analysis; otherwise scoring is subjective and rankings are not comparable across assessments.

Quick reference

Risk Management (lifecycle and integration)

  • Risk management is iterative: new risks emerge as scope, environment, or controls change, so identification and assessment repeat at defined intervals and at stage gates.

  • Risk appetite statements should be specific and measurable (e.g., maximum acceptable loss per event) so that escalation decisions are rule-based rather than judgmental.

  • Lessons-learned from closed risks feed back into identification checklists; recurring risk causes indicate a control design failure, not bad luck.

  • Integration rule: risk treatment decisions are made against objectives, so a response that removes risk but blocks the objective is not a valid treatment.

  • Risk aggregation across units requires a common scale and taxonomy; without a shared risk breakdown structure, portfolio totals double-count or omit exposures.

Quick reference

Risk Management (controls and assurance)

  • Preventive controls reduce probability; detective controls reduce impact by finding events sooner; corrective controls restore after an event. Map each response to its control type.

  • Control testing evidence: design effectiveness (does the control address the risk?) and operating effectiveness (did it work over the period?). Both are needed to claim risk reduction.

  • Segregation of duties, approval limits, and reconciliation are classic preventive controls; monitoring alerts and audits are detective controls.

  • Risk acceptance requires documented authority at the level matching the exposure; acceptance above tolerance must be escalated to the accountable governance body.

  • Insurance and contractual indemnities transfer financial consequence but not all risk: reputational and operational disruption usually remain with the organization.

Quick reference

Risk Management (scenario and stress analysis)

  • Stress testing applies extreme but plausible scenarios to test whether exposure stays within tolerance; it complements probability-based analysis, which underweights rare events.

  • Scenario analysis defines a plausible future state, then traces its consequences through the risk register to identify correlated or cascading risks.

  • Correlation matters: risks that usually occur together (e.g., supplier failure and transport disruption) must be assessed jointly, because summing individual EMVs understates combined exposure.

  • Business impact analysis ranks processes by maximum tolerable downtime and recovery point objective; these thresholds set the required risk response for continuity risks.

  • Single points of failure are identified by mapping dependencies; a dependency with no alternate path converts a low-probability event into a high-impact one.

Quick reference

Risk Management (roles, escalation, and metrics)

  • Escalation rule: if residual risk exceeds the tolerance threshold for the owner's authority level, escalate to the next level with the assessment and proposed response.

  • Risk owner accountability includes monitoring triggers, executing the response, and reporting status changes; an unassigned risk is an unmanaged risk.

  • Risk-adjusted decision making compares options on expected value net of treatment cost, not on gross exposure alone.

  • Trend reporting compares current risk scores with prior periods; a stable score with rising KRI values signals that the current controls are losing effectiveness.

  • Near-miss and incident data are leading inputs to risk identification; capturing them converts operational experience into updated probability estimates.

Quick reference

Risk Management (frameworks and terminology)

  • Risk is often expressed as consequence × likelihood; ISO-style definitions separate risk source, event, consequence, and likelihood so each can be assessed and treated distinctly.

  • Inherent, current, and target risk are three distinct states: before controls, with controls as they operate today, and the level the treatment plan intends to reach.

  • Risk criteria are the terms of reference for evaluating significance: they define scales, thresholds, and what counts as acceptable, and are set by governance before assessment.

  • Risk treatment plan states the action, owner, due date, cost, and expected residual risk; a response without an owner and date is only an intention.

  • Risk communication must be timely and tailored to the audience: operational detail for owners, aggregate exposure and trend for governance bodies.

Quick reference

Risk Management (review and improvement)

  • Monitoring and review checks whether controls remain effective, whether assumptions still hold, and whether new risks have emerged; outputs update the register and the treatment plan.

  • Risk review triggers include stage gates, significant change, incidents, audit findings, and scheduled intervals - whichever comes first.

  • Recording the rationale for accepted risks preserves accountability and supports later re-evaluation when conditions or appetite change.

  • Risk maturity progression: ad hoc → repeatable → defined → managed → optimized; each level adds standard criteria, aggregation, and quantitative analysis.

  • Post-event review compares actual impact with the assessed probability and impact; systematic underestimation indicates a calibration problem in the assessment scales.

Quick reference

Risk Management (treatment selection rules)

  • Avoid is preferred when the activity's risk exceeds appetite and the objective can be met another way; it is the only strategy that removes the exposure rather than shifting it.

  • Mitigation is preferred when the cost of the control is lower than the expected loss it prevents (probability reduction × impact).

  • Transfer is appropriate when another party can bear the consequence more efficiently; it usually adds a cost (premium) and may leave residual operational risk.

  • Acceptance is valid only when residual risk is within tolerance and the acceptance is documented with authority; acceptance of an unassessed risk is not a decision.

  • Opportunity responses follow the same logic in reverse: exploit when the organization can capture the benefit, share when capability is missing, enhance when probability or benefit can be increased.

Quick reference

Risk Management (data and quantification)

  • Data quality determines risk estimate reliability: historical frequency, expert judgment, and external benchmarks each carry different confidence and should be labeled as such.

  • Expected loss = frequency × average severity; for a portfolio, total expected loss is the sum across risk categories after adjusting for correlation.

  • Confidence level in a distribution (e.g., P90) means the outcome is expected to be at or below that value in 90% of simulated iterations - not a guarantee.

  • Risk limit and risk tolerance differ: a limit is a hard boundary that triggers action; tolerance is the acceptable range of variation within the appetite.

  • Quantified risk statements pair a probability estimate with a consequence estimate and a time horizon; a probability without a horizon is not actionable.

Quick reference

Risk Management (organizational context)

  • Establishing context defines external and internal parameters (objectives, stakeholders, constraints, criteria) that bound the risk assessment; changing context invalidates prior scoring.

  • Stakeholder analysis identifies whose objectives define impact; the same event can be low impact for one stakeholder and severe for another.

  • Risk culture determines whether risks are reported early; metrics such as escalation rates and near-miss reporting volume indicate reporting health.

  • Third-party risk is assessed on the same probability-impact basis as internal risk, with added concentration analysis for dependencies on a single supplier.

  • Risk appetite cascades: enterprise appetite sets thresholds for business units, which set operational limits for individual processes and owners.

Quick reference

Risk Management (control and response mechanics)

  • Contingency plan is activated by a trigger and defines the specific actions, resources, and owner; it is prepared in advance for accepted risks with material impact.

  • Fallback plan is used when the primary response fails; it is a distinct, pre-approved alternative rather than an improvised reaction.

  • Workaround is an unplanned response to an occurred risk; it should be documented and later converted into a planned response if the risk recurs.

  • Residual risk after treatment must be re-scored and re-entered into the register; the treatment plan is not complete until residual exposure is recorded.

  • Response cost-benefit test: implement the control only if expected loss reduction exceeds the control's total cost of ownership.

Quick reference

Risk Management (assurance and reporting lines)

  • Independent assurance (internal audit, external review) tests whether reported risk and control status matches reality; it does not own or manage the risk.

  • Board or equivalent body sets appetite and receives aggregate reporting; management executes within limits; the two roles must not be merged.

  • Risk committee reviews top risks, treatment progress, and breaches of limits; its decisions are recorded with owners and dates.

  • Escalation should include the assessment, the options considered, the recommended response, and the residual exposure if no action is taken.

  • Reporting integrity rule: aggregate risk figures must use a consistent taxonomy and scale, or the total will misstate exposure.

Quick reference

Risk Management (identification depth)

  • Root-cause analysis (e.g., 5 Whys, fishbone) identifies the underlying source of a risk; treating the symptom leaves the probability unchanged.

  • Checklist and prompt-list identification reduces omission but does not surface novel risks; combine with brainstorming and scenario analysis.

  • Delphi technique converges expert estimates anonymously over rounds, reducing dominance by senior voices; output is a probability and impact estimate.

  • Assumption-based identification: list every assumption the plan depends on and rate the consequence if it proves false.

  • Historical incident and near-miss logs are the most reliable source of frequency data for recurring operational risks.

Quick reference

Risk Management (evaluation and prioritization)

  • Risk evaluation compares analyzed risk against criteria to decide whether treatment is required; analysis describes, evaluation decides.

  • Prioritization combines score with velocity and detectability: a moderate-score risk that is fast and hard to detect can outrank a higher-scoring slow risk.

  • Risk proximity is the time until a risk could occur; near-term risks take precedence over equal-score risks further out.

  • Risk clusters and correlated risks are prioritized as a group; treating them individually can leave aggregate exposure above tolerance.

  • Watch-list rule: risks below the treatment threshold are monitored with defined triggers rather than actively treated.

Quick reference

Risk Management (treatment implementation)

  • Each treatment action is tracked like any deliverable: owner, due date, cost, dependency, and completion evidence.

  • Treatment effectiveness is verified after implementation by re-measuring the probability or impact; an unimplemented or untested control provides no risk reduction.

  • Secondary risks created by a response are identified and assessed before the response is approved.

  • Residual risk acceptance is recorded at the appropriate authority level with the rationale and review date.

  • If treatment fails to bring residual risk within tolerance, the remaining options are further treatment, transfer, avoidance, or formal escalation.

Quick reference

Risk Management (metrics and monitoring)

  • KRI thresholds have three states: green (normal), amber (warning, investigate), red (breach, escalate and act).

  • Leading indicators predict future exposure (e.g., control test failures); lagging indicators record past events (e.g., losses incurred).

  • Loss-event data feeds frequency and severity estimates; the absence of recorded events is not evidence of low risk if reporting is weak.

  • Control self-assessment lets process owners rate control effectiveness; results are validated by independent testing.

  • Monitoring output must close the loop: every breach produces an action, an owner, and a date, recorded in the register.

Quick reference

Risk Management (decision rules)

  • If probability cannot be reduced economically, reduce impact (detection, contingency, transfer); if neither can be reduced, avoid the activity or escalate acceptance.

  • Choose the response with the lowest total cost of risk: expected residual loss plus cost of control plus cost of any transfer premium.

  • Do not treat a risk whose expected loss is below the cost of the cheapest effective control; monitor it instead.

  • When two risks are correlated, evaluate the combined exposure; treating one may not reduce the aggregate below tolerance.

  • Document the decision and its rationale whenever risk is accepted above the owner's authority, or when a recommended treatment is rejected.

Quick reference

Risk Management (definitions and distinctions)

  • Hazard is a source of potential harm; risk is the combination of the likelihood of harm and its consequence. A hazard exists even when risk is low.

  • Issue is a risk that has already occurred and is now managed as a problem; it moves from the risk register to the issue log.

  • Risk vs uncertainty: risk has assessable probability and impact; uncertainty is unquantified and is managed through reserves and flexibility.

  • Control is any measure that modifies risk; a control that is not documented, owned, and tested cannot be relied on in residual risk estimates.

  • Assurance is independent verification of control effectiveness; it supports but does not replace management's own monitoring.

Quick reference

Risk Management (portfolio and aggregation)

  • Portfolio risk aggregates risks across units using a common taxonomy and scale; correlation adjustments prevent over- or under-statement of total exposure.

  • Concentration risk arises when many exposures share one driver (single supplier, single platform, single regulator); it is assessed at the driver level.

  • Diversification reduces aggregate risk only when exposures are not perfectly correlated; it does not reduce risk within a single correlated cluster.

  • Portfolio limits cap aggregate exposure by category and are monitored against the same thresholds used for individual risks.

  • Top-risk reporting selects by score, velocity, and proximity, not by score alone, so fast-moving exposures are not hidden.

Quick reference

Risk Management (governance cadence)

  • Risk register review frequency is set by risk velocity and volatility of the environment, not by a fixed annual cycle.

  • Stage gates and major change events trigger a full re-identification and re-evaluation of risks.

  • Incident and near-miss reviews produce updated probability estimates and, where causes recur, a control redesign.

  • Appetite and criteria are reviewed periodically; if they change, all prior evaluations must be re-tested against the new criteria.

  • Assurance findings are tracked to closure with owners and dates; open findings above tolerance are escalated.

Quick reference

Risk Management (quantitative methods)

  • Expected Monetary Value decision rule: choose the alternative with the highest expected value after including the cost of each option.

  • Decision trees handle sequential decisions: compute expected values from the terminal branches backward to each decision node.

  • Monte Carlo outputs a distribution; report the confidence level alongside the value (e.g., P80 = 80% chance of not exceeding the figure).

  • Sensitivity analysis isolates the variables with the largest effect on the outcome; those variables become monitoring priorities.

  • VaR is horizon- and confidence-specific; comparing VaR figures computed with different horizons or confidence levels is invalid.

Quick reference

Risk Management (response planning)

  • A complete response plan states the action, the owner, the trigger, the resources required, the expected residual risk, and the review date.

  • Contingency reserve is sized from the expected value or a confidence level of identified risks, and is released only by the risk owner.

  • Management reserve is held outside the risk register for unidentified risks and released by senior authority.

  • Fallback plans are prepared for responses that may fail; they are pre-approved so action is not delayed.

  • Workarounds for occurred risks are logged and reviewed so recurring causes become planned responses.

Quick reference

Risk Management (culture and behavior)

  • Early reporting is encouraged when escalation carries no blame; suppressed reporting raises undetected exposure.

  • Risk ownership is assigned to the person who controls the activity that creates the risk, not to the risk function.

  • Incentives that reward only outcomes without risk adjustment encourage excessive risk-taking; risk-adjusted measures correct this.

  • Near-miss reporting volume is a health indicator: rising reports with stable incidents suggest improving detection.

  • Governance effectiveness depends on decision rights: who may accept which level of risk must be defined in advance.

Quick reference

Risk Management (summary rules)

  • Risk management sequence: context, identification, analysis, evaluation, treatment, monitoring and review, communication and consultation throughout.

  • Qualitative analysis ranks; quantitative analysis prices. Use quantitative methods when the decision involves material cost or comparison of options.

  • Residual risk within tolerance → accept and monitor; above tolerance → treat, transfer, avoid, or escalate.

  • Every risk needs an owner, a score, a response, a trigger, and a review date; missing any one leaves the risk unmanaged.

  • Correlated risks are assessed jointly; independent summing understates aggregate exposure.

Quick reference

Risk Management (assurance and audit interface)

  • Audit findings are risks in their own right until remediated; they are entered into the register with an owner and date.

  • Design effectiveness asks whether the control, as designed, addresses the risk; operating effectiveness asks whether it worked over the period tested.

  • Sampling and testing evidence supports the residual risk estimate; unsupported estimates are assumptions, not measurements.

  • Repeat findings indicate a control environment weakness rather than an isolated failure, and require escalation.

  • Assurance coverage should target high-score, high-velocity risks first; low-risk areas need less frequent independent testing.

Quick reference

Risk Management (final reference)

  • Risk statement format: cause → event → consequence, with probability and impact attached; this structure makes the risk testable and assignable.

  • Risk appetite (willingness to pursue) and risk tolerance (acceptable variation) together define the thresholds used in evaluation.

  • Treatment cost-benefit rule: act when expected loss reduction exceeds the total cost of the control.

  • Monitoring closes the loop: re-score residual risk, verify control effectiveness, and update the register after every treatment.

  • Escalation is rule-based: residual risk above the owner's authority is escalated with the assessment, options, and recommendation.