Quoting a School Toilet Block Without a Rate Take-Off

Maharashtra SSC Plumber (General) Pre-Voc/NSQF · Put your knowledge to work in context.

All case studies

Quoting a School Toilet Block Without a Rate Take-Off

A zilla parishad school in Kolhapur asks for a quotation for a new toilet block: 6 Indian WC pans, 4 urinals, 2 wash basins and a 1,000 L overhead tank. The drawing shows a 25 mm CPVC water main about 35 m long, 15 mm branches to each fixture, a 110 mm SWR soil line about 28 m long, a 75 mm waste line about 18 m long, and a vent stack. The plumber submits a lump sum of ₹1.85 lakh based on a similar job last year, saying all fittings and labour are included. His one-page quote excludes excavation, the septic tank, the manhole, the water tank, testing, painting and GST. The school's engineer asks for a measured estimate with a 5% contingency and current rates. Local rates are: CPVC 25 mm ₹180/m, 15 mm ₹95/m, SWR 110 mm ₹210/m, SWR 75 mm ₹140/m, WC pan ₹3,500 each, urinal ₹1,200 each, wash basin ₹2,000 each. Labour is about 20% of material, fittings about 15% of pipe material, and GST is 18%.

1. Prepare a structured take-off and identify at least five missing cost items that make the lump sum unreliable.

Read the worked answer

A measured take-off should list pipe lengths by diameter, fittings by type and size, fixtures, valves, tank, supports, excavation, manholes, septic tank, testing and painting. From the given drawing, the main measured items are 35 m of 25 mm CPVC, 28 m of 110 mm SWR, 18 m of 75 mm SWR, 15 mm branches, 6 WC pans, 4 urinals and 2 wash basins.

Missing items include: excavation and backfill for the soil line; septic tank and manhole construction; the 1,000 L tank and its stand; valves, bib cocks and connectors; pipe supports and clamps; testing and commissioning; painting or labelling; GST; and a contingency for site changes. A lump sum that excludes these cannot be compared fairly with a complete estimate.

2. Estimate the material cost of the listed pipes and fixtures, then explain how you would add labour, fittings, contingency and GST without double counting.

Read the worked answer

Using the given rates, the pipe material is: 35 × ₹180 = ₹6,300 for 25 mm CPVC; 28 × ₹210 = ₹5,880 for 110 mm SWR; 18 × ₹140 = ₹2,520 for 75 mm SWR. The 15 mm branches are not measured in the drawing, so take a measured length, for example 30 m at ₹95 = ₹2,850. Pipe subtotal = ₹17,550. Fixtures: 6 × ₹3,500 = ₹21,000; 4 × ₹1,200 = ₹4,800; 2 × ₹2,000 = ₹4,000; fixture subtotal = ₹29,800.

Add fittings at 15% of pipe material ≈ ₹2,633. Material before labour ≈ ₹49,983. Add labour at 20% of material ≈ ₹9,997, giving ≈ ₹59,980. Add 5% contingency ≈ ₹2,999, then 18% GST on the subtotal plus contingency ≈ ₹11,336. The illustrative total is about ₹74,300, but it still excludes the tank, excavation, manholes, septic tank and testing, so it is not a complete tender price.

3. How would you advise the school to compare the lump sum with your estimate, and what green options could reduce life-cycle cost?

Read the worked answer

Compare scope, not just the bottom line. Ask each bidder to price the same item list and to state exclusions, warranty, testing and defect-liability period. A low lump sum that omits the septic tank or testing is not cheaper; it transfers risk to the school.

Recommend water-saving fittings such as dual-flush WC pans, aerated taps, and urinals with sensors or a controlled flush. Consider a rainwater harvesting connection for toilet flushing and a leak test before handover. These may add capital cost but reduce water bills and repair costs. Keep a 5% contingency and require as-built drawings and operating instructions.