The Maharashtra SSC Plumber (General) Pre-Vocational/NSQF programme is a school-level vocational subject offered under the Maharashtra State Board of Secondary and Higher Secondary Education (MSBSHSE). It introduces secondary students to plumbing as a trade: the safety habits, tool skills, materials knowledge and system understanding that a trainee plumber needs before entering an ITI, an apprenticeship or a helper role on site. The Maharashtra SSC Plumber (General) Pre-Voc/NSQF case studies are 5 cases and about 2,837 words.

1

Manhole Entry at a Housing Society Septic Sump

At a 24-flat society in Pune, the septic sump has choked two days before the monsoon. The chamber is 2.4 m deep, with a 900 mm opening and about 300 mm of sludge.

484 words, about 2 min
2

Top-Floor Pressure Complaint in a Four-Storey Walk-Up

A four-storey, 12-flat walk-up in Nashik has a 1,000 L ground-level PVC tank and a 0.5 HP pump that fills a 500 L terrace tank. The terrace tank outlet is about 1.5 m above the top-floor ceiling.

615 words, about 3 min
3

Gurgling Traps After a Five-Storey Stack Is Extended

A 20-year-old five-storey building in Thane originally had a 100 mm SWR stack serving three floors. Two upper floors were added last year, with 75 mm branches from each WC and a 50 mm trap.

600 words, about 3 min
4

Hot-Water Line Failure at a Small Clinic

A small clinic in Nagpur adds a hot-water line from a 15 L electric geyser to two wash basins. The geyser thermostat is set at 70 °C and the line is about 15 m long, mostly concealed in a wall.

532 words, about 3 min
5

Quoting a School Toilet Block Without a Rate Take-Off

A zilla parishad school in Kolhapur asks for a quotation for a new toilet block: 6 Indian WC pans, 4 urinals, 2 wash basins and a 1,000 L overhead tank. The drawing shows a 25 mm CPVC water main about 35 m long, 15 mm branches to each fixture, a 110 mm SWR soil line about 28 m long, a 75 mm waste line about 18 m long, and a vent stack.

606 words, about 3 min