Sixty Hectares, One Choe and a Textile Plant

PSEB Matric Social Science · Put your knowledge to work in context.

All case studies

Sixty Hectares, One Choe and a Textile Plant

A textile company wants 60 hectares of flat, double-cropped land on the edge of a town in Fatehgarh Sahib district, beside a seasonal choe that carries water during the monsoon. The land belongs to 34 owners, most of them small farmers with about 1.8 hectares each; the district collector has begun acquisition under the 2013 land law and the estimated award is about four times the circle rate. The company promises 250 jobs, of which it says 60 will be skilled positions filled from outside the district, and 1,200 kilolitres of water a day. Its dyeing unit will generate wastewater. The alternative is 25 hectares of degraded land in the existing industrial focal point eight kilometres away, which needs a ₹4.2 crore approach road and a dedicated power feeder; the company says it needs 60 hectares for future expansion. Some farmers want to sell, others say the choe, the village pond and the school playground will be affected.

1. Identify the main stakeholders and state, for each, the interest at stake and the risk they bear.

Read the worked answer
Stakeholder Main interest Risk they bear
The 34 landowners Best price, or retaining land they farm Those with 1.8 ha lose their livelihood, not a surplus asset; a one-time payment can be consumed within a few years
Landless labourers Construction and factory jobs Lose regular farm labour and may not have the skills for the 60 skilled posts
The company A contiguous 60 ha, water, and a lawful discharge route Delay, local resistance, effluent liability
The gram panchayat and gram sabha Being consulted; village infrastructure Traffic, dust, pressure on groundwater and drainage
School and pond users Safe playground, clean pond for cattle Effluent and dust; loss of a common resource
Farmers downstream along the choe Unpolluted seasonal flow Dyeing effluent entering the choe in the monsoon
The state government Investment and jobs Compensation and rehabilitation costs; legal challenge if procedure is skipped
Future generations Irreversible conversion of prime farmland Loss of 60 ha of double-cropped land permanently

The key insight for the answer is that the number of stakeholders is not the point: the 34 owners are not equal (some want cash, some depend on the land), and the strongest risks fall on people who are not parties to the deal at all - labourers, downstream farmers and the school.

2. What does the 2013 land acquisition law require before this land can be taken, and what conditions should the gram sabha demand if the project proceeds?

Read the worked answer

Legal requirements before acquisition:

  1. A Social Impact Assessment of the proposed acquisition, including an assessment of alternatives, published for public comment.
  2. Consent of landowners - 80% for acquisition for a private company, 70% where the project is a public-private partnership - recorded properly, not by a show of hands.
  3. Irrigated multi-cropped land is to be acquired only as a last resort and within limits, because it is the most productive land; this site is exactly such land, so the 25 ha degraded alternative must be examined on the record.
  4. Compensation of four times the market value in rural areas, plus the value of assets attached to the land, and rehabilitation and resettlement entitlements; payment before possession.
  5. A rehabilitation and resettlement award, and a provision that land unused for the stated purpose returns to the owners.

Conditions the gram sabha should demand:

  • No discharge into the choe; a functioning effluent treatment plant and zero liquid discharge, verified by an independent monitor;
  • Metered groundwater use, with no new tubewells in an already stressed block;
  • A verifiable local employment quota with named trades and training, not a vague 250;
  • A green buffer and traffic and dust management near the school;
  • Written consent from all 34 owners, and a written commitment on timelines and on returning unused land.

3. Recommend a decision, and state the strongest argument against your own recommendation and the evidence that would change your mind.

Read the worked answer

Recommendation: direct the company to the 25 ha focal-point site unless it can prove on paper that 60 ha are technically necessary.

The reasoning is comparative. Sixty hectares of double-cropped land produces roughly 5 tonnes of wheat and 6 tonnes of paddy per hectare - about 660 tonnes of grain a year, worth well over ₹1 crore, plus fodder and the pond and choe that the village uses. The alternative site needs ₹4.2 crore of public money for a road and a feeder: a one-time cost that is smaller than the annual value of the produce alone, and it places the effluent near an existing industrial area instead of beside a seasonal stream and a school. The 60 ha demand is a future expansion wish, not a current requirement, and the law asks that irrigated multi-cropped land be taken last.

Strongest argument against me: the company may simply go to another state. Then the district keeps its farmland but loses 250 jobs, the ₹4.2 crore is not spent, and the farmers who genuinely want to sell are blocked by those who do not. Landowners have a right to dispose of their property, and a refusal that overrides the willing sellers is also a coercion.

Evidence that would change my mind: a plant layout showing that 25 ha cannot accommodate the unit; an effluent and water plan that demonstrably protects the choe; a binding job commitment with local recruitment; and a majority of the 34 owners formally consenting. If those exist, the balance shifts and properly conditioned acquisition becomes defensible.