Quoting ₹2.24 Lakh Against a ₹1.85 Lakh Rival, a Cash Deal and a One-Week Subsidy Promise

Punjab PSEB Sr. Sec. NSQF Electronics (Solar Panel Installation Technician) · Put your knowledge to work in context.

All case studies

Quoting ₹2.24 Lakh Against a ₹1.85 Lakh Rival, a Cash Deal and a One-Week Subsidy Promise

You run a two-person solar firm in a Punjab district town. A farmer with a 2 kW sanctioned domestic connection (four hours of grid supply a day) wants a 3 kWp hybrid system to back up six LED lights, two fans, a refrigerator and a 1 hp tubewell pump for two hours daily. Your landed material cost is ₹1,72,000 - ALMM-listed mono PERC modules, a hybrid inverter, a 5 kWh LFP battery, galvanised structure, DC/AC cabling, ACDB/DCDB, earthing and a lightning arrester. Labour and transport is ₹28,000, and you need a 12% margin plus GST at the prevailing rate. A competitor has quoted ₹1.85 lakh turnkey with non-ALMM modules, no battery, no lightning arrester, no net-metering paperwork and a one-year warranty. The farmer wants to pay ₹40,000 in cash 'without bill' to bring your price down, insists the system be tied to his existing 2 kW single-phase meter, and wants you to guarantee that the ₹78,000 rooftop subsidy will reach his account within a week.

1. Build the headline quote from the given costs and set out the line items you will and will not trim. Justify each decision technically, not emotionally.

Read the worked answer

The arithmetic

  • Cost = 1,72,000 + 28,000 = ₹2,00,000.
  • Margin at 12 % = 2,00,000 × 1.12 = ₹2,24,000, plus GST at the prevailing rate shown as a separate line. Never bury GST inside the lump sum; the customer will compare your gross figure with a rival's net one and you will lose an argument you should win.

Non-negotiable items

  • ALMM-listed modules - required for the subsidy and for net metering; non-ALMM modules make the file ineligible and the customer finds out months later, at your door.
  • Battery and hybrid inverter - he asked for backup; the competitor's ₹1.85 lakh has no battery, so the two quotes are not the same product. Say this on one page of paper.
  • Earthing and lightning arrester - Punjab has violent pre-monsoon storms; without an LA and a good earth pit the inverter and the subsidy both disappear in one strike.
  • Net-metering and subsidy paperwork - this is skilled labour, not paperwork; it takes visits to the DISCOM office.

Can be trimmed with the customer's informed consent

  • Module make within the ALMM list, cable brand, structure galvanising thickness above the minimum, monitoring dongle, and the length of the free O&M period.

Value argument: 3 kWp × ~4.5 kWh/kWp/day × 365 ≈ 4,900 kWh/year; over 25 years with 0.8 average derate that is roughly 98,000 kWh for ₹2.24 lakh - about ₹2.3 per unit against a grid tariff of ₹6–7. Put that on the quotation.

2. The farmer wants to pay ₹40,000 cash without a bill, connect 3 kW to his existing 2 kW single-phase meter, and have the subsidy in a week. Address all three.

Read the worked answer

Cash without a bill - refuse, and explain why in his terms

  • An unaccounted ₹40,000 means the invoice does not match the installed capacity; the subsidy claim and the net-metering application both require a GST invoice and serial-numbered material that match the site.
  • Module warranty is not transferable without proof of purchase; a burnt inverter in month 14 becomes his loss.
  • It is also a tax offence that can cost you your registration, which means you cannot serve him in year 5 when the system needs service. Offer instead: staged payment (advance, post-structure, post-commissioning), or a smaller scope he can upgrade later.

3 kW on a 2 kW sanctioned load

  • Net metering is granted against the sanctioned load, and the inverter AC capacity must not exceed it. Either he applies for load enhancement to at least 3 kW first, or you install a smaller system - there is no third route.
  • A 1 hp pump plus a fridge on a 2 kW single-phase connection also needs a load check for simultaneous running; the hybrid inverter's pass-through limit will trip the house if the pump starts while the fridge compressor is on.
  • Confirm with the DISCOM whether they permit 3 kW export on single phase at this feeder, and get it in writing before you order material.

Subsidy in a week - no

  • Under the national rooftop scheme the residential subsidy is currently ₹30,000/kW for the first 2 kW, ₹18,000/kW for the third, capped at ₹78,000 - so his 3 kW figure is plausible, but the money is credited to his bank account directly after commissioning, inspection and net-meter installation, and the timeline is set by the DISCOM and the portal, not by you.
  • Also confirm whether the battery portion is covered - generally the subsidy is for the grid-connected rooftop component.
  • Promise only this: 'I will file correctly and follow up; the sanction is the DISCOM's, the credit is the government's, and I will show you the portal status at every stage.' Put that in writing on the quotation so it cannot be misremembered.

3. How do you handle the 'your competitor is ₹39,000 cheaper' objection, and what documentation do you hand over at completion?

Read the worked answer

Handling the objection

  1. Do not match the price. Sit down with both quotes and build a like-for-like table: battery yes/no, module certification, lightning arrester, earthing, net-metering filing, warranty years, local service response. The gap usually shrinks to a few thousand rupees once the battery is priced in.
  2. Quantify the risk: an unbranded inverter with a one-year warranty means a ₹20,000–₹30,000 replacement in year 2 - more than the difference being argued about.
  3. Offer choices, not discounts: same price with a smaller battery, or a 3 kW grid-tied stage now and battery later. Give him control of the trade-off.
  4. Offer proof: two nearby installations he can visit, with the owners' phone numbers.
  5. Walk away politely if he still insists on a price that only an unsafe installation can meet. A loss-making job becomes a warranty liability you fund for five years.

Handover file

  • GST invoice itemising make, model and serial numbers of modules, inverter and battery; warranty cards in the customer's name.
  • Single-line diagram, array layout drawing, earthing and LA details.
  • Commissioning test sheet (string Voc/Isc, insulation resistance, earth resistance, thermal images), net-meter sealing certificate and portal application number.
  • O&M schedule with cleaning frequency, battery watering/checking interval, and your emergency contact; a signed handover checklist and a feedback request after the first bill cycle.