A Four-Worker Home Unit, a Smoke Complaint and a 400-Badge Order
A home-based embroidery unit in a 3 m × 4 m room has four workers, one single-head 15-needle machine, one steam iron and a ceiling fan. The electrical board is a daisy chain of three extension leads plugged into one 5 A socket. The unit has won an order for 400 school uniform badges in nine days. On day two, a neighbour complains of machine noise and a burning smell; the 19-year-old trainee has wrist pain and has just had a needle-prick injury cleaned with water. The owner has no Udyam registration, no written wage record, and turnover last year was ₹18 lakh. The machine supplier says the burning smell is 'normal' for a new motor. The owner wants to ignore the complaint and finish the order.
1. List the immediate safety actions you would take before the next shift, covering electrical, fire, ergonomic and biological hazards.
Read the worked answer
Electrical: unplug the daisy chain immediately. One 5 A socket is about 1,100 W; a 15-needle machine, steam iron and fan on three extension leads can exceed that and overheat. Move the machine and iron to separate circuits with proper earthing, an RCD, and no extension leads across the floor. Have a qualified electrician inspect the motor and wiring before restart.
Fire: the burning smell is not 'normal'. Stop the machine, isolate power, and check the motor belt, wiring and lint around the needle bar. Keep a dry-powder or CO2 extinguisher within reach; never use water on electrical equipment. Clear fabric and cardboard away from the iron.
Ergonomic: the trainee's wrist pain points to a fixed-height table, repetitive gripping and no breaks. Provide an adjustable chair, wrist support, anti-fatigue mat and a five-minute break every 45 minutes; rotate tasks.
Biological: wash the needle prick with soap and running water, cover it, record it in an accident register, and check tetanus status. Use a sharps container for broken needles, not the floor or bin. Train all four workers before the next shift.
2. Advise on registration and record-keeping for this unit, and explain why they matter for the school order.
Read the worked answer
The unit is small (₹18 lakh turnover) but the school order changes the risk profile. Udyam registration is free and gives formal identity; many institutional buyers ask for it. GST: the threshold for goods in Uttar Pradesh is ₹40 lakh, so registration is not mandatory at ₹18 lakh, but the school may require a GST invoice for its accounts; voluntary registration is possible, and input credit on machine and thread may help. Shop and Establishment registration may apply to the premises under state law.
Labour records: maintain a wage register, attendance, age proof and written terms for all four workers; the 19-year-old is an adolescent and must not be given hazardous work or hours beyond the law. Safety records: accident register, first-aid box and electrical inspection certificate.
These matter because a school is accountable to parents and auditors; a unit without records can lose the order or face liability if the trainee is injured. Get the requirements in writing from the school before promising a delivery date.
3. The order needs 400 badges in the remaining 7 days. Propose a production and contingency plan that does not rely on unsafe practices.
Read the worked answer
Work content: 400 badges ÷ 7 days ≈ 58 per day. A single-head 15-needle machine running an eight-hour shift can produce well over this if the design is under about 8,000 stitches; the bottleneck is usually hooping and trimming, not sewing. Run at a safe speed, not maximum, and keep one operator dedicated to hooping so the machine does not idle.
Plan: day 1, electrician sign-off and a 10-badge test; days 2–6, two shifts only if wiring and ventilation are certified, with rotation every two hours; day 7, finishing, final inspection and buffer. Pre-hoop 60 badges in advance. Keep a trained second operator for breaks.
Contingency: if the machine fails, outsource only the stitching to a registered unit with a written quality agreement, and do the finishing in-house. Do not ask the trainee to work alone at night or bypass the RCD. If the safety fixes cannot be completed, renegotiate the deadline in writing rather than run the machine on the daisy chain.