You are the Block Development Officer of Naraini block, Banda district, Bundelkhand, in the first week of March. The block's approved labour budget for the year is ₹4.8 crore, and the notified MGNREGA unskilled wage used in every estimate is ₹220 per person-day. Karhi Gram Panchayat (640 households, 1,150 active job cards) has passed three proposals in its Gram Sabha. Proposal A is a check dam on a seasonal nala: estimated cost ₹22.00 lakh, 3,800 person-days generated, material requirement ₹13.64 lakh. Proposal B is deepening of a 0.6-hectare village pond: ₹9.50 lakh, 3,600 person-days, material ₹1.58 lakh. Proposal C is 90 days of tanker water supply at ₹6.00 lakh. The Pradhan wants A started at once because it will be visible before the monsoon, and suggests the excavator hire be 'adjusted' partly as unskilled wages on the muster roll. The tehsil has reported drinking-water stress in two hamlets from April.

1. Which of the three proposals can you sanction as a MGNREGA work this financial year, and which can you not? Show the arithmetic and name the binding rule you are applying.

Read the worked answer

Step 1 - Test each proposal against the 60:40 rule. MGNREGA requires that at least 60% of a work's cost go to unskilled wages, i.e. the material component (including skilled wages) cannot exceed 40%.

  • A (check dam): wages = 3,800 × ₹220 = ₹8,36,000, which is 38% of ₹22,00,000; material = 62%. This breaches the 40% ceiling.
  • B (pond deepening): wages = 3,600 × ₹220 = ₹7,92,000, which is 83.4% of ₹9,50,000; material = 16.6%. Compliant and labour-intensive.
  • C (tankers): procuring and supplying water by tanker is not a permissible MGNREGA work at all - it is a drinking-water contingency, not a wage-employment work.

Step 2 - Check process. B is already in the Gram Sabha resolution and must also figure in the approved shelf of works and within the GP's share of the labour budget; that condition is satisfied.

Conclusion: sanction B only now. A is not sanctionable in its present design because material alone is 62%; C must be met from the drought-relief/drinking-water head.

2. The Pradhan proposes to book the excavator hire under 'material' up to 40% and show the balance as unskilled wages on the muster roll. How do you respond, and what lawful route could still deliver the check dam?

Read the worked answer

Refuse in writing, and do not sign the muster. The 40% material limit is a ceiling, not a target to be topped up; inflating person-days to absorb machine cost creates non-existent workers, which is misappropriation of wages - actionable in the social audit and under the anti-corruption law, with personal liability for the approving officer. Record the refusal in the file so the audit trail shows who proposed it.

Lawful alternatives for the check dam:

  1. Re-scope it to raise the labour share - manual excavation of the earthen bund, stone packing by labour, with machines used only where technically unavoidable, so that material falls to 40% or below.
  2. Fund it from a scheme meant for material-heavy structures - the 15th Finance Commission tied/untied grants, PMKSY or watershed works, or the state minor-irrigation head - and use MGNREGA only for the wage component of an approved work.
  3. Phase it across two financial years so each phase clears the ratio.

Tell the Pradhan plainly: the work is desirable, the financing route is wrong, and a rejected bill is cheaper than a social-audit finding.

3. What is the defensible response to the drinking-water shortage before April, and in what order should the works be scheduled?

Read the worked answer

Immediate (March): report the two stressed hamlets to the tehsil and arrange tanker supply from the district drought-relief/drinking-water fund, not from MGNREGA. Trolley/stand-post repair and hand-pump repair can be taken up as permissible MGNREGA works if they appear in the shelf of works. Give the SC/ST hamlets first call, since they are usually at the tail of the pipeline.

Sequencing:

  1. Start pond deepening now, so excavation is finished before the peak of summer and the desilted pond holds the monsoon and recharges the wells that feed the hamlets - this links the wage work directly to the water problem.
  2. Simultaneously process the check dam for the next financial year through the watershed/minor-irrigation route, so that the Pradhan gets the structure without a rule violation.
  3. Record in the labour budget that A was deferred for the 60:40 reason, so the block is not shown as having an idle sanctioned work.

The dependency is real: the pond must be ready before the rains, and the check dam can only be built once a lawful funding line exists.