IPMA Level D case studies
IPMA Level D · Put your knowledge to work in context.
IPMA Level D® (Certified Project Management Associate) is the entry point of IPMA's four-level certification scheme, 4-L-C. IPMA describes it as "IPMA's starting level, aimed at starting professionals" - the tier below Level C®, which IPMA positions for people with three to five years of working experience, and below the senior Levels B® and A® for very experienced, all-round professionals. IPMA certification is competence-based rather than methodology-based: candidates are assessed against the Individual Competence Baseline (ICB), the global standard that "describes the competences that project, programme and portfolio managers should possess". Assessment happens locally - IPMA promises certification "in your own country, in your own language, at your own competence level" - delivered by national Member Associations and their Certifying Bodies, which means the practical exam format, scheduling, language and pricing are set nationally rather than published globally. The IPMA Level D case studies are 5 cases and about 3,367 words.
1The Frozen Tranche
You are project manager for a 14-month, EUR 1.2m replacement of a regional water utility's billing system. The CFO who signed the business case has left after a merger announcement; the incoming CFO told a town hall she "hasn't seen a compelling case" and has frozen the next EUR 300k tranche pending her review.
667 words, about 3 min2Two Seniors, One Architecture
You manage a nine-month integration project with a fixed deadline. Your senior solution architect has 14 years in the organisation and designed the current platform; your lead developer joined six weeks ago from a consultancy with a strong microservices record.
683 words, about 3 min3The Change Requests Nobody Counted
You are delivering a fixed-price website rebuild: six months, EUR 480k, 12 monthly deliverables. The client's marketing director has bypassed your change board twice this month by emailing developers directly with 'small' additions; her team has raised 43 change requests so far, of which 12 went through the process.
671 words, about 3 min4The Cheapest Bid
You are running a EUR 1.1m tender to replace 1,200 laptops and docks across three sites. Three bids are compliant with the specification.
657 words, about 3 min5Green by Re-Baseline
You take over a ten-month project in month 7. Of twelve deliverables, six are complete.
689 words, about 3 min