IPMA Level D study materials
IPMA Level D study resources

IPMA Level D cheat sheet

IPMA Level D · Keep the key ideas within reach.

Quick reference

Perspective

  • IPMA ICB4 Perspective competences link projects to strategy, governance, structures and processes, compliance and standards, culture and values, and change.

  • PESTLE scans Political, Economic, Social, Technological, Legal and Environmental external factors; it is used to assess the macro-environment.

  • SWOT pairs internal Strengths and Weaknesses with external Opportunities and Threats; TOWS converts these pairs into strategy options.

  • Governance decision rule: the sponsor or steering group approves baselines, stage gates and tolerance breaches; the project manager delivers within agreed tolerances.

  • Stakeholder power-interest grid: high power/high interest = manage closely; high power/low interest = keep satisfied; low power/high interest = keep informed; low/low = monitor.

  • Compliance hierarchy: law and regulation outrank contract, contract outranks organizational policy, and policy outranks the project plan.

  • Benefits realization distinguishes outputs from outcomes: benefits are measured after deliverables are used, not when deliverables are completed.

  • Change curve stages are commonly denial, resistance, exploration and commitment; communication and participation reduce resistance.

  • Triple bottom line assesses economic, social and environmental performance, often summarized as profit, people and planet.

Quick reference

People

  • Tuckman team stages are forming, storming, norming, performing and adjourning; conflict is typically resolved during storming before stable performance.

  • Situational leadership styles are directing, coaching, supporting and delegating; the choice depends on follower competence and commitment for the specific task.

  • Thomas-Kilmann conflict modes are competing, collaborating, compromising, avoiding and accommodating; collaborating suits win-win issues with time and trust.

  • SMART goals are Specific, Measurable, Achievable, Relevant and Time-bound.

  • Communication channel count for n people is n(n - 1) / 2; channels grow quadratically as the number of participants increases.

  • SBI feedback describes the Situation, the observed Behavior and its Impact; it focuses on evidence rather than personality.

  • Herzberg separates hygiene factors such as pay and conditions, which prevent dissatisfaction, from motivators such as achievement and recognition, which create satisfaction.

  • BATNA is the best alternative to a negotiated agreement; a stronger BATNA increases a negotiator's leverage.

  • Delegation rule: authority and tasks may be delegated, but accountability for the outcome remains with the delegating manager.

Quick reference

Practice

  • Earned value formulas: CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV. CPI below 1 means cost overrun; SPI below 1 means schedule delay.

  • EAC = BAC / CPI when current cost performance continues; ETC = EAC - AC.

  • PERT expected duration = (O + 4M + P) / 6; activity standard deviation = (P - O) / 6.

  • Critical path is the longest dependent path through the schedule; it has zero total float, and delay on it delays project completion.

  • Total float = LS - ES = LF - EF; it is the time an activity can slip without delaying the project finish.

  • Risk score = probability x impact; threat responses are avoid, mitigate, transfer and accept; opportunity responses are exploit, enhance, share and accept.

  • Change control requires a request, impact assessment across scope, time, cost, risk and quality, approval decision, then baseline and log updates.

  • Cost of quality includes conformance costs (prevention and appraisal) and nonconformance costs (internal and external failure); prevention is generally cheaper than failure.

  • WBS 100% rule: the sum of child elements must equal 100% of parent scope, with no work omitted or added.