- Calibration
- Related: As-Found Data, Traceability, Five-Point Check
The documented comparison of an instrument's output against a traceable reference standard, recording the deviation found, without necessarily making any adjustment to the device.
- Traceability
- Related: Calibration, Reference Standard
An unbroken chain of documented comparisons linking the reference standard used in a calibration back to a national or international metrology institute, proving the standard's stated accuracy.
- As-Found Data
- Related: As-Left Data, Calibration
The readings recorded before any adjustment is made, showing how the instrument performed in service and often used to judge whether it needs repair or replacement.
- As-Left Data
- Related: As-Found Data, Tolerance
The readings recorded after adjustment or repair, demonstrating the instrument now meets tolerance and serving as the record handed back to the owner.
- Tolerance
- Related: As-Left Data, Five-Point Check
The permissible band of error around a setpoint or span within which an instrument is considered acceptable for its intended service, usually stated in percent of span.
- Five-Point Check
- Related: Hysteresis, Calibration
A calibration sequence that checks output at 0, 25, 50, 75 and 100 percent of span, run both upscale and downscale to reveal hysteresis and linearity problems.
- Hysteresis
- Related: Five-Point Check, Deadband
The difference between an instrument's output when the input approaches a value from increasing versus decreasing direction, caused by mechanical friction, magnetisation or linkage slack.
- Deadband
- Related: Hysteresis, Setpoint
The range of input change that produces no measurable output change, common in switches and controllers that intentionally hold their last state until a threshold is crossed.
- Reference Standard
- Related: Traceability, Calibration
A measuring device of known, higher accuracy and documented traceability used as the comparison source during calibration of field instruments.
- Zero and Span Adjustment
- Related: Tolerance, Calibration
The two tuning actions on a transmitter: setting the output for the lower-range value and setting the gain so the output matches the upper-range value.
- Preventive Maintenance
- Related: Work Order, Predictive Maintenance
Scheduled, condition-driven servicing such as cleaning, lubricating, inspecting and testing performed to keep equipment reliable and to avoid unplanned failures.
- Predictive Maintenance
- Related: Preventive Maintenance, Vibration Analysis
Maintenance triggered by measured condition data such as vibration, temperature or oil analysis, so intervention happens just before a predicted failure rather than on a fixed calendar.
- Work Order
- Related: Preventive Maintenance, Permit to Work
A written authorisation and record for a maintenance task, listing scope, location, required parts, labour, safety permits and completion sign-off.
- Permit to Work
- Related: Lockout Tagout, Work Order
A formal document controlling high-risk activity, confirming hazards have been identified, isolation and gas testing are complete, and authorised persons have signed on.
- Lockout Tagout
- Related: Permit to Work, Loop Check
A procedure that physically locks energy-isolating devices and attaches warning tags so equipment cannot be re-energised while people are working on it.
- Root Cause Analysis
- Related: Troubleshooting Tree, Mean Time Between Failures
A structured investigation, often using the five-whys or fishbone method, that traces a failure past its symptom to the underlying process or design weakness.
- Troubleshooting Tree
- Related: Signal Tracing, Root Cause Analysis
A logical decision sequence that narrows a fault by testing signal presence at successive points, from field device through wiring to controller and final element.
- Signal Tracing
- Related: Troubleshooting Tree, Loop Check
The practice of measuring the process signal at each junction along a loop to locate where a valid reading stops and a fault begins.
- Ground Loop
- Related: Signal Tracing, Shielded Cable
An unwanted current path created when two or more grounded points sit at slightly different potentials, producing noise, offset or erratic readings in signal circuits.
- Shielded Cable
- Related: Ground Loop, Signal Tracing
Instrument wiring wrapped in a conductive foil or braid that is drained at one end to divert electrical noise away from low-level signal conductors.
- Fail-Safe Position
- Related: Final Control Element, Loop Check
The valve or actuator position chosen so that loss of air, power or signal produces the least hazardous outcome for the process.
- Loop Check
- Related: Punch List, Cold Commissioning
A verification that every component in a control loop is correctly wired, tagged, ranged and responding, from sensor input through controller logic to final element action.
- Cold Commissioning
- Related: Loop Check, Hot Commissioning
Testing of installed systems without process fluid present, covering wiring, instrument air, power distribution, calibration verification and functional response of final elements.
- Hot Commissioning
- Related: Cold Commissioning, Loop Check
Commissioning performed with process fluids or live utilities introduced, verifying real-flow performance, control tuning and safety system response under actual conditions.
- Punch List
- Related: Loop Check, Mechanical Completion
A running register of outstanding defects and incomplete items found during walkdowns, each assigned an owner and priority for closeout before handover.
- Mechanical Completion
- Related: Punch List, Pre-Commissioning
The milestone confirming that construction and installation are finished and systems are ready to begin commissioning, with only minor punch items outstanding.
- Pre-Commissioning
- Related: Mechanical Completion, Cold Commissioning
Activities carried out after installation and before commissioning, such as flushing, pressure testing, instrument calibration verification and motor rotation checks.
- P&ID
- Related: Loop Number, Instrument Index
A piping and instrumentation diagram showing equipment, process lines, instruments with tag numbers, and the control and interlock relationships between them.
- Instrument Index
- Related: P&ID, Loop Number
The master register of every instrument in a project, listing tag number, service, type, range, location, loop assignment and associated documentation status.
- Loop Number
- Related: P&ID, Loop Check
A unique identifier assigned to a control loop that groups its instruments, wiring, drawings and test records so they can be traced through design, construction and maintenance.
- Cause and Effect Matrix
- Related: Safety Instrumented System, Loop Check
A chart cross-referencing each trip input against the outputs it must drive, used to define, test and document safety and interlock system behaviour.
- Safety Instrumented System
- Related: Cause and Effect Matrix, Fail-Safe Position
An independent protective system of sensors, logic solver and final elements that brings the process to a safe state when demand occurs, rated by its safety integrity level.
- Final Control Element
- Related: Fail-Safe Position, Valve Positioner
The device that physically changes the process in response to controller output, typically a control valve, damper or variable-speed drive.
- Valve Positioner
- Related: Final Control Element, Hysteresis
A device mounted on an actuator that compares stem position with the control signal and adjusts air supply to reduce positioning error and overcome stem friction.
- Scope of Work
- Related: Work Breakdown Structure, Change Order
The written statement defining what a project or contract will deliver, including boundaries, deliverables, exclusions and acceptance criteria.
- Work Breakdown Structure
- Related: Scope of Work, Critical Path
A hierarchical decomposition of project deliverables into manageable work packages that can be estimated, scheduled, assigned and tracked.
- Critical Path
- Related: Work Breakdown Structure, Change Order
The longest sequence of dependent activities through a project schedule, which sets the shortest possible completion time and shows where delay directly slips the end date.
- Change Order
- Related: Scope of Work, Management of Change
A formally approved document authorising a modification to scope, schedule or cost after the baseline has been set, including its impact assessment.
- Management of Change
- Related: Change Order, Safety Instrumented System
A controlled process ensuring that proposed modifications to equipment, procedures or software are reviewed for risk, approved, documented and communicated before implementation.
- Mean Time Between Failures
- Related: Root Cause Analysis, Preventive Maintenance
The average operating time between successive failures of a repairable item, used to compare reliability and to plan spares and maintenance intervals.
- Setpoint
- Related: Deadband, Tolerance
The target value at which a controller is asked to hold the process variable, entered by the operator or written by a higher-level system.