BORAQS Architect Exam · Keep the key ideas within reach.

Quick reference

Architecture: Professional Practice, Statutory Control and Design Standards

  • BORAQS (Board of Registration of Architects and Quantity Surveyors, Kenya) registers architects and quantity surveyors under the Architects and Quantity Surveyors Act (Cap 525); registration categories include full registration and temporary/practical-training status, and only registered persons may use the protected titles and submit statutory drawings.

  • Under the Physical and Land Use Planning Act 2019, development permission is sought from the county government; approval of building plans is a separate county function, and construction may not start before both planning permission and building-plan approval are granted.

  • Occupancy certificate: a building may not be occupied until the local authority issues a certificate of occupation/completion confirming compliance with the approved plans, structural adequacy and sanitary requirements; partial occupancy can be certified for completed sections.

  • Means of escape rule of thumb: two independent exits are required where occupant load exceeds 50 or travel distance exceeds about 18–22 m in a single direction; exit widths are sized from occupant load at roughly 5 mm per person for level egress and more for stairs.

  • Fire resistance periods (Kenya Building Code practice) commonly used: 30 min for small/low-rise elements, 60 min for institutional and medium-rise floors, 90–120 min for structural frames and shafts in high-rise or basement situations; compartment floor area limits reduce with height and use.

  • Stair geometry: maximum riser 180 mm and minimum going 250 mm for private stairs (public/assembly stairs stricter, e.g. riser ≤150–175 mm, going ≥280–300 mm); 2R + G should fall between about 550 mm and 700 mm; headroom minimum 2.0–2.1 m.

  • Sanitary provision is calculated from occupant load by use: e.g. offices roughly 1 WC per 15–25 persons with separate provision for each sex, schools 1 WC per 15–30 pupils plus urinals, and additional accessible unisex WC per floor where sanitary facilities are provided.

  • Accessibility: at least one accessible route from parking/plot boundary to the entrance, ramps at maximum 1:12 gradient (1:15 preferred) with landings every 6–9 m, door clear opening ≥800–850 mm, and accessible WC of about 1.5 m × 2.0 m minimum with grab rails.

  • Architect's statutory duties under the standard professional services contract: prepare and administer the building contract, issue instructions and certificates fairly, certify payment within the stated period, and avoid conflicts of interest; the architect does not guarantee the contractor's workmanship.

Quick reference

Quantity Surveying: Measurement, Costing and Contract Administration

  • Building cost estimate at design stage: cost = gross floor area × benchmark rate per m², adjusted by a location factor and a price-index factor (current index ÷ base index); elemental estimating refines this by summing element quantities × element unit rates plus preliminaries, contingency and design fees.

  • Measurement conventions (CESMM/SMM-style): masonry walls measured in m² net of openings exceeding a stated area (commonly 1–3 m²), deducting reveals; concrete measured in m³ by net volume excluding reinforcement; formwork in m² of contact area; reinforcement in kg or tonnes with 5–10% laps/wastage.

  • Standard rebar mass check: mass (kg/m) ≈ d²/162 for bar diameter d in mm (e.g. 12 mm ≈ 0.888 kg/m, 16 mm ≈ 1.58 kg/m, 20 mm ≈ 2.47 kg/m); multiply by total length and add laps and wastage.

  • Interim valuations: value of work done = measured quantities executed × BoQ rates, plus pro-rata preliminaries and variations, less retention (typically 5–10% of each certificate up to a cap of about 5% of contract sum) and less previous payments; add VAT/levies as applicable.

  • Retention and securities: retention is deducted from each interim certificate until the limit is reached, half released at practical completion and the balance at end of defects liability/maintenance period; performance security commonly 10% of contract sum, and advance payment bond secures advance recovery.

  • Variation valuation hierarchy: (1) BoQ rate if work is of similar character and quantity, (2) derived rate by pro-rata analysis of the BoQ rate, (3) fair valuation based on actual cost plus reasonable overhead and profit; dayworks apply where work cannot be measured.

  • Fluctuations: price adjustment formula P = A + b(Ln/Lo) + c(Mn/Mo) + … where A is the non-adjustable portion and L, M are labour and material indices at base (o) and current (n) dates; the sum of coefficients equals 1.0.

  • Cash flow and cost control: S-curve of cumulative value plotted against time; earned value indicators CPI = EV/AC and SPI = EV/PV; forecast final cost = contract sum ± approved variations ± measured remeasurement ± fluctuations + claims provision.

  • Final account components: original contract sum, remeasured adjustments, instructed variations, provisional/prime cost sums adjusted to actual, fluctuations, loss and expense claims, less retention released and contra charges for architect-instructed remedial work.