Absolute volume mix design
Method that sums paste, fine aggregate, and coarse aggregate absolute volumes to 1 m³, then adjusts batch weights for aggregate moisture content before mixing.
Total float
Difference between late finish and early finish of an activity. It is the time an activity can slip without delaying the project completion date on the network.
Modified Proctor test
Compaction test using four or five layers and a heavier hammer, delivering about 4.5 times the energy of the standard Proctor test. Used for heavily loaded pavements and fills.
Earned value CPI
Cost Performance Index equals earned value divided by actual cost. A value below one indicates the work performed cost more than the budget allowed.
Curing duration
Minimum moist-curing period is typically seven days for Type I cement concrete and three days for Type III, counted from placement, to ensure strength and durability gain.
Finish rolling temperature
Asphalt compaction must be completed before the mix cools below about 85 degrees Celsius, when viscosity becomes too high for rollers to achieve specified density.
Effective stress
Total vertical stress minus pore water pressure at a point. It governs soil shear strength, settlement, and bearing capacity, unlike total stress in saturated soil.
Terzaghi bearing capacity
Ultimate bearing equation summing cohesion, surcharge, and unit weight terms with factors depending on friction angle. Shape factors modify the strip footing result for square and circular footings.
Rankine active coefficient
Ka equals tangent squared of forty-five degrees minus half the friction angle. It converts vertical effective stress to horizontal active earth pressure for a yielding wall.
Degree of consolidation
Ratio of settlement at a given time to ultimate settlement. Fifty percent consolidation occurs at a time factor of 0.197, ninety percent at about 0.848.
Plasticity index
Liquid limit minus plastic limit. A high index, often above thirty, indicates expansive clay with significant volume change potential under moisture variation.
Liquefaction susceptibility
Saturated loose uniform sands with corrected blow counts below fifteen and shallow groundwater are most susceptible to strength loss during earthquake shaking.
Slope factor of safety
Ratio of resisting to driving forces or moments on a potential failure surface. Permanent slopes usually require at least 1.5.
Tension-controlled section
Reinforced concrete section with tensile strain at least 0.005 at nominal strength, permitting a strength reduction factor of 0.90 for flexure.
Whitney stress block
Rectangular equivalent compressive stress of 0.85 f'c over depth a equal to beta-one times neutral axis depth, used to compute nominal flexural strength.
Beta-one factor
Factor reducing stress block depth for high-strength concrete. It is 0.85 up to 28 MPa and drops 0.05 per 7 MPa above, with a floor of 0.65.
Minimum shear reinforcement
Required when factored shear exceeds half the design concrete shear capacity. It prevents brittle failure and is provided as stirrups meeting minimum area and spacing rules.
Euler buckling load
Critical axial load equals pi squared times modulus times moment of inertia divided by effective length squared. Effective length factor depends on end restraint conditions.
Compact section
Steel section whose flange and web slenderness ratios are below the plastic limit, allowing the full plastic moment to develop before local buckling.
Live load deflection limit
Floor members are commonly limited to span divided by 360 under live load and span divided by 240 under total load to control cracking and vibration.
Stopping sight distance
Sum of distance traveled during perception-reaction time and braking distance. Braking distance depends on speed, friction, and grade.
Superelevation equation
Required rate relates speed squared divided by 127 times radius, minus side friction factor. Minimum radius follows from maximum superelevation and friction.
Vertical curve K value
Length of vertical curve divided by algebraic grade change in percent. Crest K values are governed by stopping sight distance, sag values by headlight distance.
Greenshields model
Linear speed-density relationship predicting zero flow at jam density and maximum flow at half free-flow speed and half jam density.
Structural number
Pavement design value summing layer thickness times layer coefficient and drainage modifier. It represents required structural capacity for traffic loads.
Passenger car equivalent
Factor converting heavy vehicles to equivalent passenger cars for capacity analysis. Trucks and buses reduce capacity on grades and in traffic streams.
Rational method
Peak runoff equals runoff coefficient times rainfall intensity times area. Intensity duration equals time of concentration. Suitable for small urban drainage areas.
Manning equation
Open channel velocity equals roughness reciprocal times hydraulic radius to the two-thirds power times slope to the one-half power. Flow is velocity times area.
Curve number method
Estimates direct runoff depth from rainfall using a curve number based on land use, soil group, and antecedent moisture. Higher numbers mean more runoff.
CT disinfection value
Product of disinfectant residual concentration and contact time. Required values rise with pH and fall with warmer water temperature for a given organism inactivation.
Froude number
Ratio of flow velocity to the square root of gravity times hydraulic depth. Below one is subcritical, above one supercritical, and one is critical flow.
Water hardness