The 150 psi Hydro Test on a 200 psi Main

KY Fire Sprinkler · Put your knowledge to work in context.

All case studies

The 150 psi Hydro Test on a 200 psi Main

A private 8-inch cement-lined ductile iron main, about 1,600 ft long, is tapped off a 12-inch city main at 90 psi static to serve a four-building office park with six private hydrants. The contractor has laid the main, backfilled all but the tap, and hydro-tested at 150 psi for two hours with no measurable drop, which he considers a pass. Two 90-degree bends, one 45-degree jog, and a tee to Building C are in the run. Restrained joints were used at the 90-degree bends and at the tee; the 45-degree fitting got a poured concrete block built by the crew from a form. Soil borings show sandy soil with an allowable bearing pressure of 2,000 psf. For flushing, the crew opened a 2 1/2-inch hydrant nozzle and ran it until the water looked clear, roughly 350 gpm. The water utility requires disinfection before the main is placed in service and will not accept the main until the testing is documented.

1. Is the 150 psi, two-hour test acceptable? State the correct test pressure and what it means for the fittings already installed.

Read the worked answer

No. The test is 50 psi short and must be redone.

  • The rule: NFPA 24 requires private fire service mains to be hydrostatically tested at 200 psi for 2 hours. Where the system working pressure exceeds 150 psi, the test pressure is the working pressure plus 50 psi. Here the working pressure is 90 psi, so the governing test pressure is 200 psi for 2 hours.
  • Why 150 psi is not a 'close enough' pass: the test is a proof test of the pipe, joints, gaskets, valves, and thrust restraint. Passing at 150 psi demonstrates nothing about performance at the code-mandated proof pressure, and a main that leaks or blows a joint at 200 psi would do so after the paving and landscaping are in place.
  • Consequence for the fittings: thrust restraint must be designed for the test pressure, not the 90 psi working pressure. Thrust scales linearly with pressure, so a block sized for 90 psi will be carrying barely half the load it must resist during the test. Every restrained joint, block, and tapping sleeve must be evaluated at 200 psi before the retest.
  • Test procedure: the test should be conducted with joints exposed where practicable so that leaks can be located, witnessed by the AHJ or utility, with calibrated gauges at the low end of the main, and documented with date, pressure, duration, and the witness. Verify that valves, hydrants, and fittings are rated for the test pressure and that the test does not over-stress the city main or its valve at the tap.

2. Compute the thrust at the 8-inch 90-degree bend at the test pressure. Then compute the thrust at the 45-degree jog and the bearing area its block needs. What do you tell the contractor about his poured block?

Read the worked answer

Thrust computations at 200 psi (use full-face area, A = pi x d^2 / 4 = 50.27 sq in for 8-inch pipe):

  • 90-degree bend: T = 1.57 x P x d^2 = 1.57 x 200 x 64 = 20,100 lb (about 10 tons).
  • 45-degree bend: T = 2 x P x A x sin(theta/2) = 2 x 200 x 50.27 x sin(22.5 degrees) = 20,108 x 0.3827 = 7,700 lb.
  • Tee with a dead-end or capped branch: T = P x A = 200 x 50.27 = 10,054 lb.
  • Required bearing area for the 45-degree block: 7,700 lb / 2,000 psf = 3.9 sq ft of bearing surface against undisturbed soil. For the 90-degree bend, if a block were used instead of restraint: 20,100 / 2,000 = 10.0 sq ft.

What to tell the contractor:

  1. The poured block cannot be accepted on the basis of 'we always pour about this big.' It must have a designed bearing area at the 200 psi test pressure, bear on undisturbed or properly compacted soil (not backfill), be oriented so the thrust is directed into the block face, and be separated from the fitting by a joint that will not damage the pipe coating.
  2. A block poured against loose backfill has effectively zero design bearing capacity, regardless of its size. The soil at the block must be verified.
  3. Restrained joints are a legitimate alternative - and often preferable in poor or wet soil - but the length/number of restrained joints must be taken from the manufacturer's design tables for the actual pressure, and the transition to the unrestrained pipe must be restrained too. Mixing a restrained 90 and an unengineered 45 in the same run is a red flag that no one designed the restraint system.
  4. The tapping sleeve and valve at the city main need restraint as well, and the utility will have its own detail.

3. Evaluate the flushing operation and state what else must happen before the main can be placed in service.

Read the worked answer

The flushing was far too slow to be effective.

  • Required velocity: flushing must achieve a minimum of 10 ft/s in the main to scour debris that settled during construction. For an 8-inch main: A = pi x (0.333 ft)^2 = 0.349 sq ft; Q = A x V = 0.349 x 10 = 3.49 cfs x 448.8 = about 1,570 gpm.
  • What actually happened: 350 gpm through an 8-inch main gives V = (350 / 448.8) / 0.349 = about 2.2 ft/s. 'Clear water' at 2 ft/s proves nothing - it means the water was clear at the outlet while the heavier debris, mill scale, and construction grit remained in the main, where it will later foul sprinkler heads, valves, and the fire pump.
  • Practical remedy: flush at or near 1,570 gpm, which may require a large-capacity blow-off, a temporary connection to a hydrant with a known flow, or flushing in segments. If 10 ft/s truly cannot be achieved through the available outlets, document it and get the AHJ's written direction; do not silently substitute 'it looked clear.'
  • Before service, also require:
    1. A successful 200 psi / 2-hour hydrostatic test, witnessed and documented, with restraint designed for that pressure.
    2. Disinfection of the main in accordance with the utility/AWWA requirements - chlorination, retention time, flushing to remove the chlorine residual, and any required bacteriological sampling.
    3. Verification that all valves are open, hydrants are properly drained and set, and thrust restraint is inspected before the trench is backfilled over the fittings.
    4. A documented flow test at a hydrant on the completed main to confirm the installed system's supply, which becomes the baseline for the building's sprinkler design and for future NFPA 25 water supply comparisons.