240 Kaizen Events and No Result: What to Scale and What to Refuse

Lean Silver Certification · Put your knowledge to work in context.

All case studies

240 Kaizen Events and No Result: What to Scale and What to Refuse

A 12-site building-products group launched Lean 18 months ago. A central CI team of four ran 240 kaizen events; 5S audits average 4.2 out of 5; 96% of employees have been trained in the eight wastes; there is a monthly newsletter. Results: OTIF has fallen from 91% to 78%, total inventory is up 9%, and no site has a value-stream map of a whole order-to-cash flow - maps were done cell by cell. Events were chosen because a site volunteered or a consultant recommended one. Each site has a Lean coordinator who reports to the plant manager; two of them are also the maintenance manager. No site has tiered daily accountability beyond a supervisor walk. A new COO wants to scale by mandating the same 20-event calendar at all 12 sites within nine months, funded by two additional CI engineers and nothing else. The one exception: Plant C connected its events along a single value stream and improved OTIF on that stream from 84% to 96% while cutting WIP 38%.

1. Diagnose why 240 completed events produced no enterprise result. Distinguish activity measures from system effects.

Read the worked answer

The programme's unit of improvement was the event, not the value stream. Events end at the event boundary; there is no owner of the end-to-end flow, so local gains are absorbed back into the system - capacity is freed, then immediately filled with WIP because the scheduling rules, batch sizes and MRP logic were never touched. That is exactly why inventory rose 9% while everyone was 'doing Lean': freed capacity without a pull signal becomes overproduction.

Specific failure modes:

  • Activity metrics masquerading as results. 240 events, 4.2/5 on 5S and 96% trained measure effort and tidiness. None measures flow, lead time or delivery. The 5S score is the most dangerous: it is auditable, it always rises, and it is uncorrelated with OTIF.
  • No order-to-cash VSM means the group never agreed on what the problem was, never located the constraint, and never sized the gap between current and future state.
  • Event selection by volunteering or consultant preference optimized for enthusiasm, not for constraint or cash impact.
  • Structural weakness: coordinators report to plant managers and two double as maintenance managers, so there is neither dedicated capacity nor authority to change cross-functional rules.
  • No daily management. Without tiered accountability, nothing holds a gain after the consultant leaves.

OTIF falling means due-date performance and the constraint were never addressed; Plant C is the counter-example that proves the point - same toolset, but connected along a value stream.

2. Recommend a 12-month deployment architecture and selection criteria. What would you refuse from the COO's mandate, and what would you negotiate?

Read the worked answer

Refuse the 20-event × 12-site calendar. With two additional engineers that is 240 events in nine months - the same volume that just failed, at higher cost, and it repeats the activity-not-results design. Also refuse to scale before the holding mechanism (daily management) exists; replication of an unheld gain just multiplies rework.

Negotiate to a value-stream-led deployment:

Selection criteria for the first waves: streams with the largest OTIF or cash gap, a single accountable value stream manager with authority over scheduling, stable enough demand to see the effect, and a site leader who will personally run leader standard work. Pick two or three sites and roughly four streams - not twelve sites.

Per stream, 90 days: an order-to-cash current and future-state map; a value stream manager named and empowered; two or three KPIs only (OTIF, lead time, WIP); a plan that changes rules (scheduling, batch size, pull, changeover) not just workplaces; and tiered daily accountability installed in the first 30 days so gains are held.

Capability: coaching on the line, not more classroom. Two coaches can realistically support one new stream each per quarter - so four to six streams in year one, with internal coaches being certified as they go.

Structure: make the CI coordinator role dedicated, trained and dual-reporting to the group CI lead, not to the plant manager alone.

The trade-off to present to the COO: publish it in units he cares about - 'three sites and four streams this year, targeting 8–10 OTIF points and 20% WIP reduction on those streams; the remaining nine sites begin in year two once the gate is met.' A committed, gated plan beats a symbolic 12-site mandate.

3. Define the gate that must be met before a site or stream is scaled further, and the measure set that shows whether deployment is real rather than theatrical.

Read the worked answer

Gate (all conditions, not a score):

  1. The stream's OTIF has held at or above target for eight consecutive weeks after the CI team stepped back.
  2. Tiered daily meetings run at every level without a CI person in the room, and escalated items close with a named owner and a date.
  3. A local person has led a full order-to-cash VSM and taken at least one A3 to a verified countermeasure.
  4. Leader standard work exists and is audited by a peer, not self-reported.
  5. Inventory and lead-time gains are confirmed by physical or ERP audit, not by the event report.
  6. The value stream manager has scheduling authority in writing.

Measure set:

  • Lagging (outcomes, one set for the group): OTIF, order-to-cash lead time, inventory turns, cost per unit, safety.
  • Leading (system health): percentage of streams with daily management operating; escalation closure time; A3s closed with verified countermeasures; certified internal coaches; percentage of improvement plans that changed a rule rather than a workplace.
  • Explicitly not used as a success measure: event count, training completion, 5S audit score, newsletter frequency.

Anti-theatricality: audit the data source against the ERP and the shop floor on a sample basis each quarter; require every stream to report a baseline before its first intervention; and publish failures alongside successes - a deployment where no stream failed a gate is not being measured. If the leading measures improve for two quarters without lagging movement, the diagnosis is wrong and the deployment should stop and be re-scoped, not accelerated.