Lean Silver Certification study materials
Lean Silver Certification study resources

Lean Silver Certification flashcards

Lean Silver Certification · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Muda, Mura, Muri
The three categories of process weakness: muda is waste, mura is unevenness in demand or workload, and muri is overburden. Attacking mura and muri reduces the muda a process generates.
Takt Time
Available production time divided by customer demand rate over the same period. It is the pace the process must meet; actual cycle time must be at or below takt to satisfy demand without overtime.
Value-Added Test
An activity qualifies as value-adding only if the customer would pay for it, it changes form, fit, or function, and it is done correctly the first time. Anything else is waste or necessary non-value-added work.
Seven Wastes
Overproduction, waiting, transport, over-processing, inventory, motion, and defects. Overproduction is treated as the worst because it generates and conceals the other six.
Jidoka
Autonomation: equipment or operators stop the process when an abnormality appears so defects are never passed downstream. It is one of the two pillars of the Toyota Production System alongside just-in-time.
Push Versus Pull
Push schedules work against a forecast and buffers with inventory; pull authorizes production only when downstream consumption occurs, usually through kanban signals, limiting work in process.
Lead Time Formula
Total lead time equals processing time plus waiting time across the stream. Value-added ratio is value-added time divided by lead time, and is typically a small percentage in office and production streams.
Product Family Selection
Product families for mapping are chosen by product-quantity analysis or a routing similarity matrix, grouping items that share downstream processes and equipment rather than mapping each part number separately.
Current-State Map Data Box
Each process box records cycle time, changeover time, uptime, batch size, operator count, available working time, and scrap or first-pass yield, so the map is built from measured facts rather than impressions.
Inventory Days Calculation
Inventory quantity between two processes divided by daily customer demand gives days of inventory. Summing inventory days across the stream and adding processing time yields total lead time.
Pacemaker Process
The most downstream process in the value stream that is scheduled by production control. Everything upstream is pulled from it, so scheduling elsewhere would create overproduction and excess inventory.
Future-State Map Questions
Standard questions: what is takt time, where can continuous flow be used, where is a supermarket pull needed, what single point schedules production, and how will the product mix be leveled.
Value Stream Versus Process Map
A process map details steps inside a single operation. A value stream map shows door-to-door material and information flow for a product family, including scheduling, inventory, and supplier and customer interfaces.
Timeline Ladder
The stepped line at the bottom of a value stream map: value-added processing times sit above the steps and waiting or inventory days sit below, giving a visual ratio of value-added to total lead time.
A3 Report Structure
A one-page PDCA story: background, current condition with data, target condition, root-cause analysis, countermeasures, implementation plan with owners and dates, and follow-up of results against target.
Five Whys
A causal-chain technique that asks why repeatedly until a process or system cause is found. Stopping at operator error usually indicates the analysis ended too early to prevent recurrence.
Pareto Analysis
Ranking problems by frequency or cost and addressing the vital few that account for most of the effect. A Pareto chart sorts bars descending and overlays a cumulative percentage line.
Kaizen Versus Kaikaku
Kaizen is small incremental improvement made by the people doing the work; kaikaku is radical transformation of a process or system. They need different sponsorship, timelines, and risk management.
Standard Work Elements
Standard work documents the current best method through takt time, work sequence, and standard in-process stock. It provides the baseline against which improvement is measured and is revised when a better method is proven.
Countermeasure
A change aimed at a verified root cause and tested for its effect on the metric. If the metric does not move, the root cause was misidentified and the analysis is reopened.
Fishbone Diagram
An Ishikawa cause-and-effect diagram grouping candidate causes by man, machine, material, method, measurement, and environment. It generates hypotheses that must then be confirmed with data.
PDCA Cycle
Plan, do, check, act. It is the underlying cycle for all Lean improvement, and every A3 report is a documented instance of one full turn of the cycle on a single problem.
Respect for People
A core Lean pillar meaning the organization develops each person's capability to solve problems and improve their own work, not merely treating employees courteously or providing comfortable conditions.
Genchi Genbutsu
Go and see: leaders observe the actual process, at the actual place, with actual data before deciding. It replaces reliance on reports and secondhand summaries with direct observation.
Nemawashi
Informal consensus building through pre-meeting discussion with affected parties so a proposal is socialized and adjusted before the formal decision, reducing resistance during implementation.
Hansei
Structured reflection after an effort, focused on what the process revealed and what the leader will personally change. It is not blame assignment and is usually documented and shared.
Leader Standard Work
Documented, repeatable leader routines such as tiered meetings, gemba walks, audits, and coaching cycles. It standardizes management behavior so improvement does not depend on individual style.
Tiered Daily Management
Short structured meetings at team, value-stream, and site levels where abnormalities escalate against defined triggers and response times, so problems get an owner quickly.
Kaizen Event
A time-boxed improvement workshop, usually three to five days, with defined scope, a cross-functional team, and implemented changes by the end. It is followed by standard work and follow-up.
Five S Sequence
Sort, set in order, shine, standardize, sustain (seiri, seiton, seiso, seiketsu, shitsuke). It organizes the workplace and is a foundation for flow, not the end goal of Lean.
OEE Formula
Overall equipment effectiveness equals availability multiplied by performance multiplied by quality, where each factor is actual divided by ideal. It is the headline metric for total productive maintenance.
SMED
Single-minute exchange of die: separate internal setup done with the machine stopped from external setup done while it runs, convert internal to external where possible, then streamline what remains.