- Certification point thresholds
- LEED certification requires at least 40 points for Certified, 50 for Silver, 60 for Gold, and 80 for Platinum; ID+C v4 projects have 110 points available in total.
- LEED ID+C minimum project size
- An ID+C project must contain a minimum gross floor area of 250 square feet (23 square meters) within a single building to register and pursue certification.
- LEED prerequisite rule
- Prerequisites are mandatory requirements worth zero points; a project that fails any prerequisite cannot be certified no matter how many credit points it earned.
- Credit Interpretation Request
- A formal ruling requested through LEED Online when credit requirements are unclear for a specific project; the decision is published and treated as precedent for other projects.
- Integrative process
- A collaborative approach in which the owner, design team, contractor, and building operators analyze systems together early, before design decisions become locked in and expensive to change.
- Goal-setting charrette
- A pre-design workshop that brings all disciplines together to set measurable energy, water, and indoor environmental quality targets and to assign responsibility for meeting them.
- Simple box energy model
- A massing-level energy model used before design decisions are fixed, comparing orientation, envelope, and glazing options and helping right-size HVAC systems.
- Quality transit walking distances
- In LEED v4, quality transit is measured as one-quarter mile (400 meters) walking distance to a bus or BRT stop, or one-half mile (800 meters) to a rail station.
- Diverse uses threshold
- The surrounding density and diverse uses credit can be satisfied by locating within one-half mile (800 meters) walking distance of at least 10 diverse uses across multiple use categories.
- Bicycle storage quantities
- The bicycle facilities credit requires long-term storage for at least 5% of regular building occupants and short-term storage for 2.5% of peak visitors, with a minimum of four spaces each.
- Heat island SRI values
- Heat island reduction requires a solar reflectance index of at least 78 for low-slope roofs, 29 for steep-slope roofs, and solar reflectance of at least 29 for hardscape.
- Construction activity pollution prevention
- A Sustainable Sites prerequisite requiring an erosion and sedimentation control plan that conforms to the EPA Construction General Permit or stricter applicable local standards.
- Rainwater management event size
- The LEED v4 rainwater management credit requires managing runoff from the 95th percentile rainfall event using green infrastructure and low-impact development strategies.
- Indoor water use prerequisite
- The water efficiency prerequisite requires reducing aggregate indoor water use by at least 20% compared with the calculated baseline for fixtures, fittings, and appliances.
- EPAct 1992 fixture baselines
- Baseline rates used in LEED calculations: water closets 1.6 gallons per flush, urinals 1.0 gallons per flush, lavatory faucets 2.2 gallons per minute at 60 psi, showerheads 2.5 gallons per minute at 80 psi.
- Cooling tower cycles of concentration
- The cooling tower water use credit rewards increasing cycles of concentration, which reduces blowdown and makeup water demand; projects without cooling towers follow an alternative compliance path.
- Minimum energy performance
- An Energy and Atmosphere prerequisite requiring demonstrated energy cost improvement over an ASHRAE 90.1-2010 Appendix G baseline, documented by simulation or an approved prescriptive path.
- Advanced energy metering
- The credit requires permanent meters recording every end use representing 10% or more of annual consumption, with data collected at hourly or shorter intervals.
- Fundamental refrigerant management
- A prerequisite prohibiting CFC-based refrigerants in new HVAC and refrigeration equipment and requiring a phase-out plan where existing CFC systems continue in service.
- Enhanced commissioning scope
- Requires an independent commissioning authority who reviews the owner's project requirements and basis of design, verifies installation and performance, conducts seasonal testing, and delivers a systems manual with training.
- Construction waste diversion tiers
- The construction and demolition waste management credit awards one point for diverting 50% of waste and two points for diverting 75% away from landfill or incineration.
- EPD product thresholds
- The building product disclosure credit option one requires at least 20 different permanently installed products, from at least five different manufacturers, that have published environmental product declarations.
- Recycled content valuation
- Recycled content equals post-consumer content plus half of pre-consumer content, valued as a percentage of total permanently installed materials cost, with thresholds at 10% and 20%.
- Interior reuse thresholds
- The interiors life-cycle impact reduction credit awards points for reusing existing interior nonstructural elements such as walls, floors, and ceilings at the 25%, 50%, and 75% thresholds.
- Environmental tobacco smoke control
- An indoor environmental quality prerequisite prohibiting smoking inside the project and within a specified distance of entries, outdoor air intakes, and operable windows.
- Flush-out air volume
- The flush-out alternative to air testing requires supplying 14,000 cubic feet of outdoor air per square foot of floor area before occupancy, or 3,500 cubic feet per square foot after occupancy.
- VOC paint limits
- The low-emitting materials credit caps volatile organic compounds at 50 grams per liter for flat paints and 150 grams per liter for non-flat paints, with separate limits for coatings and adhesives.
- Quality views requirement
- The quality views credit requires a direct line of sight to perimeter vision glazing from at least 75% of the regularly occupied floor area of the project.
- Innovation category points
- The Innovation category offers 6 points: up to 5 for innovative strategies or exemplary performance and 1 for having an appropriately credentialed LEED Accredited Professional on the project team.
- Exemplary performance
- An Innovation path earned by exceeding the highest tier of an existing credit, typically doubling its threshold or reaching the next increment beyond the maximum listed.
- Tenant design and construction guidelines
- A Sustainable Sites credit requiring the project to provide tenants with design guidance and lease language so that future fit-outs preserve the building's sustainability features.
- Green building education
- An Innovation credit earned by providing publicly visible signage, tours, or outreach that explains the project's green building strategies and its measured performance.