LEED AP ID+C study materials
LEED AP ID+C study resources

LEED AP ID+C: Integrative Strategies

LEED AP ID+C · Work through your exam, one topic at a time.

All guide sections

Integrative Strategies

Integrative process

The Integrative Process credit rewards early, cross-discipline analysis rather than late add-ons. The team holds a goal-setting workshop (charrette) before schematic design, records the Owner's Project Requirements (OPR), and the design team then translates those goals into the Basis of Design (BOD). Systems thinking means hunting synergies - a daylighting strategy that also cuts lighting power density, a ventilation strategy that also improves occupant health - and surfacing trade-offs while they are still cheap to change.

What the credit actually requires

In ID+C the credit is earned through discovery and analysis of energy and water systems early in design: simple energy modeling to compare options, and analysis of water use (fixtures, process loads, and where relevant cooling or irrigation). Documentation must show the analysis and, critically, how the findings changed the design. A narrative that the team collaborated well earns nothing.

Traps

  • Assuming a charrette alone earns the credit; the analysis and its influence on design must be documented.
  • Confusing OPR (owner goals and measurable performance targets) with BOD (the design team response to those targets).
  • Treating integrative design as a schedule milestone rather than a decision method; if the decision was already made and the team is back-filling justification, it is not integrative.

Rule of thumb

Sequence it: OPR, then charrette, then analysis, then design decisions, then commissioning verifies the OPR is actually met. Analysis before design, always.