Load chart

A manufacturer's table or graph showing the maximum allowable load for a specific crane at each combination of boom length, radius, and boom angle, under the conditions and notes printed with it.

Related: Rated capacity, Load radius, Capacity deduction
Rated capacity

The maximum load a crane may handle in a given configuration and working area as published by the manufacturer, after any required deductions, under the conditions stated in the chart notes.

Related: Load chart, Gross load, Capacity deduction
Gross load

The total weight the crane actually supports: the load, all rigging below the hook, and any attachments the load chart says must be counted, such as a jib or stowed boom section.

Related: Rated capacity, Capacity deduction, Center of gravity
Capacity deduction

A weight the chart requires you to subtract from the published rating before lifting, such as an auxiliary jib, an attached spreader, or a stowed boom section.

Related: Rated capacity, Gross load
Load radius

The horizontal distance from the crane's center of rotation to the hoist line or to the load's center of gravity, measured with the boom in its working position.

Related: Load chart, Rated capacity
Working area

One of the defined sectors around a crane, such as over the front, side, rear, or corner, for which the load chart gives separate ratings because capacity changes with direction.

Related: Load chart, Rated capacity
Stability limit

The capacity limit set by the crane's resistance to tipping rather than by component strength; it usually governs long-radius and side lifts, and exceeding it can overturn the crane.

Related: Rated capacity, Load chart, Ground bearing pressure
Horizontal sling angle

The angle between a sling leg and the horizontal; as the angle gets flatter, tension in each leg rises sharply and the legs push outward against the load.

Related: Sling leg tension, Center of gravity
Sling leg tension

The force carried by each individual sling leg, which depends on the share of the load it takes and the sling angle; flatter angles produce much higher tension for the same load.

Related: Horizontal sling angle, Center of gravity, Shock loading
Choker hitch

A hitch where the sling wraps the load and passes through its own eye, tightening as it lifts; for wire rope this typically reduces capacity to about three-quarters of the vertical rating.

Related: Sling inspection, Horizontal sling angle
Center of gravity

The point where the load's weight acts; the hook must be directly above it, or the load will tilt, swing, and shift weight onto some slings more than others.

Related: Sling leg tension, Gross load
Shock loading

A sudden increase in force caused by jerking a load, letting it fall into a sling, or stopping a swing abruptly; the momentary load can far exceed the static weight.

Related: Sling leg tension, Rated capacity
Sling inspection

The required examination of slings and hardware before use for broken wires, cuts, burns, kinks, severe wear, or illegible tags; defective gear is removed from service, not returned to the rack.

Related: Pre-operation inspection, Choker hitch
Tag line

A rope tied to the load and handled from a safe distance to control rotation and swinging, keeping workers from having to touch or stand under the load.

Related: Swing radius, Critical lift
Ground bearing pressure

The load per unit area a crane's outrigger, tire, or track puts on the ground; when it exceeds what the soil or slab can carry, the crane settles, tilts, or tips.

Related: Blocking and cribbing, Leveling, Stability limit
Blocking and cribbing

Timber, mats, or steel plates placed under outrigger floats or tracks to spread load over a wider area and bridge soft spots, voids, or buried utilities.

Related: Ground bearing pressure, Leveling
Leveling

Setting the crane so the carrier is level within the manufacturer's tolerance, confirmed on the crane's level indicator, before extending the boom or lifting a load.

Related: Ground bearing pressure, Blocking and cribbing
Pre-operation inspection

The walk-around and functional checks required at the start of each shift and after setup, covering fluids, tires, wire rope, hook, brakes, limit devices, alarms, and safety decals.

Related: Sling inspection, Anti-two-block device
Anti-two-block device

A device that stops the hoist before the hook block or ball contacts the boom tip, preventing rope damage, broken parts, and a dropped load.

Related: Pre-operation inspection, Critical lift
Swing radius

The area swept by the counterweight and rear of the rotating upper structure; it must be barricaded or kept clear because the operator often cannot see it.

Related: Tag line, Prohibited zone
Power line clearance distance

The minimum separation required between any part of the crane, load, or rigging and an energized line, set by line voltage; if it cannot be kept, the line is de-energized.

Related: Prohibited zone, Power line contact response
Prohibited zone

The space within the required power-line clearance distance, into which no part of the crane, load, or rigging may enter while the line remains energized.

Related: Power line clearance distance, Critical lift
Critical lift

A lift with unusually high risk, such as one near capacity, over people or power lines, or using multiple cranes, requiring an engineered plan, added supervision, and often a lift director.

Related: Load chart, Power line clearance distance, Competent person
Wind limit

The maximum wind speed the manufacturer allows for a given boom length and configuration; when it is reached, lifting stops and the boom is lowered or stowed.

Related: Load chart, Critical lift
Qualified signalperson

A person trained and evaluated on the standard signals, the crane's operating characteristics, and the hazards of the lift, and designated by the employer to direct the operator.

Related: Hand signal, Voice signal, Stop signal
Hand signal

A standard arm and hand movement used to direct the operator to hoist, lower, swing, travel, or stop; it must be given clearly and within the operator's line of sight.

Related: Qualified signalperson, Stop signal
Voice signal

Spoken or radio commands used when hand signals are not practical; they must use the standard wording and be repeated back by the operator before acting.

Related: Qualified signalperson, Hand signal
Stop signal

The command to halt all crane motion immediately; anyone on site may give it, and the operator must obey it no matter who else is signaling.

Related: Hand signal, Qualified signalperson
Hoisting engineer license

The Massachusetts credential required to operate hoisting machinery; it is issued for particular equipment classes, must be kept in the operator's possession while working, and is subject to renewal.

Related: M.G.L. c. 146, License class
M.G.L. c. 146

The Massachusetts general law covering boilers, pressure vessels, and hoisting machinery, including the licensing of hoisting engineers and the inspection of regulated equipment.

Related: Hoisting engineer license, License class
License class

The equipment category printed on a Massachusetts hoisting engineer license that determines which types of hoisting machinery the holder is authorized to operate.

Related: Hoisting engineer license, M.G.L. c. 146
29 CFR 1926 Subpart CC

The federal OSHA standard for cranes and derricks in construction, addressing operator qualification, inspections, rigging, power-line clearance, signals, and recordkeeping.

Related: ASME B30.5, Competent person
ASME B30.5

The consensus safety standard for mobile and locomotive cranes that covers load ratings, stability, inspection, and operating practices, and that OSHA references for several crane requirements.

Related: Load chart, 29 CFR 1926 Subpart CC
ASME B30.9

The consensus safety standard for slings that sets rated capacities, hitch factors, inspection intervals, and removal-from-service criteria for wire rope, chain, and synthetic slings.

Related: Sling inspection, Choker hitch
Competent person

Someone able to recognize existing and predictable hazards in the work area and authorized to take prompt corrective action, such as stopping work or removing unsafe gear.

Related: Pre-operation inspection, Sling inspection
Near miss

An unplanned event that did not injure anyone or damage anything but could have; it is reported and investigated so the cause is fixed before a serious accident happens.

Related: Incident report, Critical lift
Incident report

A written account of an accident, injury, load drop, contact, or near miss, prepared promptly with facts, conditions, and witnesses as required by the employer and regulators.

Related: Near miss, Power line contact response
Power line contact response

If the crane touches an energized line, the operator stays in the cab and warns others away until the utility confirms the line is dead; jumping clear is a last resort.

Related: Power line clearance distance, Incident report
Emergency lowering

A planned procedure to bring the boom and load down after a power or hydraulic failure, using the manufacturer's emergency controls after clearing and securing the area below.