MA Electrician study materials
MA Electrician study resources

MA Electrician cheat sheet

MA Electrician · Keep the key ideas within reach.

Quick reference

General Code Requirements, Definitions, and Administration

  • NEC Chapter 1 applies generally; Chapters 2-4 cover wiring and equipment, Chapter 5 special occupancies, Chapter 6 special equipment, Chapter 7 special conditions, Chapter 8 communications, and Chapter 9 tables.

  • In the NEC, 'shall' is mandatory, 'shall not' is prohibited, and 'should' is advisory rather than enforceable.

  • Equipment must be approved and installed in accordance with its listing and labeling instructions under 110.3(B).

  • Working space for 600 V or less is at least 30 in wide, 6.5 ft high, and 3 ft deep for 0-150 V; 151-600 V uses 3, 3.5, or 4 ft based on condition.

  • Dedicated electrical equipment space above and around switchboards, panelboards, and similar equipment must be kept clear.

  • Overcurrent devices must have an interrupting rating not less than available fault current, and equipment must have adequate short-circuit current rating.

  • Boxes and conduit bodies containing splices or terminations must be accessible without removing building finish.

  • Electrical work generally requires a permit and inspection by the local authority having jurisdiction unless specifically exempted.

Quick reference

Wiring Methods, Materials, and Installation Practices

  • NM cable is permitted in dry locations, must be protected from physical damage, and is secured every 4.5 ft and within 12 in of boxes.

  • EMT must be supported at intervals not exceeding 10 ft and within 3 ft of boxes or termination fittings.

  • Conduit fill limits are 53% for one conductor, 31% for two conductors, and 40% for three or more conductors.

  • Box fill counts conductors, clamps, devices, and equipment grounding conductors using Article 314.16 volume allowances.

  • Minimum cover for direct-buried cable is 24 in; PVC raceway is 18 in; rigid metal conduit is 6 in.

  • Parallel conductors must be 1/0 AWG or larger and identical in material, size, insulation type, and length.

  • Splices and terminations must be made in accessible boxes or conduit bodies with adequate volume.

  • Receptacles in wet locations require weatherproof enclosures with while-in-use covers.

Quick reference

Branch Circuits, Feeders, and Service Load Calculations

  • Continuous loads are calculated at 125% for branch circuits, feeders, and services, then added to noncontinuous loads.

  • Standard overcurrent device ratings include 15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, and 100 A.

  • Dwelling kitchens require at least two 20 A small-appliance branch circuits; laundry and bathroom receptacle circuits are also 20 A.

  • Wall receptacle spacing in dwellings uses the 12 ft rule and the 6 ft rule so no wall point is more than 6 ft from a receptacle.

  • Countertop receptacles must be installed so no point along the countertop is more than 24 in from a receptacle.

  • The optional dwelling calculation method uses the first 10 kVA at 100% and the remainder at 40%, plus other loads per Article 220.

  • Dwelling lighting demand is first 3 kVA at 100%, next 117 kVA at 35%, and remainder at 25%.

  • Informational voltage-drop recommendations are 3% maximum on a branch circuit and 5% maximum total from service to load.

Quick reference

Grounding, Bonding, and Overcurrent Protection

  • The grounding electrode system must include all available electrodes, and those electrodes must be bonded together.

  • A ground rod must be at least 8 ft long and have 25 ohms or less resistance; otherwise a supplemental electrode is required.

  • The grounding electrode conductor is sized from Table 250.66 using the largest service conductor.

  • The equipment grounding conductor is sized from Table 250.122; common copper sizes include 12 AWG for 20 A, 10 AWG for 30-60 A, 8 AWG for 100 A, and 6 AWG for 200 A.

  • Small conductors are protected at 15 A for 14 AWG, 20 A for 12 AWG, and 30 A for 10 AWG unless specifically permitted otherwise.

  • GFCI protection is required for receptacles in bathrooms, kitchens, outdoors, garages, unfinished basements, and other specified wet or hazardous areas.

  • AFCI protection is required for specified 120 V, 15 A and 20 A branch circuits in dwelling units.

  • Bonding creates a low-impedance fault path so overcurrent protection operates quickly during a ground fault.

Quick reference

Electrical Theory and Fundamentals

  • Ohm's law: V = I × R; power: P = V × I = I²R = V²/R.

  • Single-phase power: kW = V × I × PF ÷ 1000; three-phase power: kW = √3 × V × I × PF ÷ 1000.

  • Apparent power: kVA = V × I ÷ 1000 single-phase; kVA = √3 × V × I ÷ 1000 three-phase.

  • Impedance: Z = √(R² + (XL - XC)²); inductive reactance XL = 2πfL; capacitive reactance XC = 1/(2πfC).

  • Power factor equals true power divided by apparent power, PF = P/S, and equals cosine of the voltage-current angle.

  • Series circuits have the same current and add voltages; parallel circuits have the same voltage and add currents.

  • Balanced wye: line voltage = √3 × phase voltage; balanced delta: line current = √3 × phase current.

  • Transformer turns ratio: Vp/Vs = Np/Ns; current ratio is inverse; 1 horsepower equals 746 watts.

Quick reference

Motors, Controls, and Utilization Equipment

  • Motor branch-circuit conductors are sized at 125% of motor full-load current from the Code tables, not the nameplate current.

  • Motor overload protection is sized from the motor nameplate current and is separate from short-circuit and ground-fault protection.

  • Motor short-circuit and ground-fault protection is selected from Article 430.52 percentages and the motor full-load current.

  • A motor disconnecting means must be within sight of the motor and controller or capable of being locked open.

  • Single-phase and three-phase motor full-load currents are found in Tables 430.248 and 430.250.

  • Air-conditioning and refrigeration equipment requires a disconnecting means within sight and readily accessible from the equipment.

  • Motor control circuits are classified as Class 1, 2, or 3 under Article 725 and must be protected accordingly.

  • Motor starting current can be several times running current, so voltage drop and conductor sizing deserve careful checking.

Quick reference

Special Occupancies, Special Equipment, and Special Conditions

  • Class I locations contain flammable gases or vapors; Class II contains combustible dust; Class III contains ignitable fibers or flyings.

  • Division 1 is a normal hazardous condition; Division 2 is an abnormal condition, and Class I locations may use zones instead.

  • Swimming pool installations require equipotential bonding of metal parts and equipment and GFCI protection for specified receptacles.

  • Health care facilities use essential electrical systems with critical and equipment branches to maintain power for patient care.

  • Photovoltaic systems on buildings require rapid shutdown to reduce conductor voltage for emergency responders.

  • Temporary wiring on construction sites requires GFCI protection for receptacles and proper support and protection.

  • Assembly occupancies are covered by Article 518; theaters and similar locations by Article 520.

  • Agricultural buildings are covered by Article 547 and require attention to dust, water, and equipotential planes.

Quick reference

Massachusetts Electrical Code Amendments, Statutes, and Board Regulations

  • The Massachusetts Electrical Code is 527 CMR 12.00, which adopts the NEC with Massachusetts amendments.

  • The Board of State Examiners of Electricians administers licensing under 237 CMR 12.00.

  • A Massachusetts master electrician is licensed to perform electrical work and obtain electrical permits; journeymen work under a master's supervision.

  • The local wiring inspector enforces the code in the municipality, issues permits, and inspects installations.

  • Board regulations govern license types, qualifications, renewal, and disciplinary action.

  • Massachusetts amendments can add to or modify NEC requirements; the stricter applicable requirement controls.

  • Concealed electrical work must be inspected before it is covered, and services must be inspected before energization.

  • Electrical work must be performed by properly licensed individuals as required by Massachusetts law and board rules.

Quick reference

Jobsite Safety and Electrical Safe Work Practices

  • NFPA 70E establishes safe work practices for shock and arc-flash hazards, including approach boundaries and PPE.

  • The limited approach boundary restricts unqualified persons; the restricted approach boundary is for qualified persons with proper protection.

  • Lockout/tagout isolates energy sources, and the qualified worker verifies absence of voltage before work begins.

  • Test before touch: use a meter with the correct CAT rating and confirm the tester on a known live source.

  • Arc-rated clothing, voltage-rated gloves with leather protectors, and face protection are selected for the hazard.

  • GFCI protection is required for temporary receptacles on construction sites and for assured grounding programs.

  • De-energize equipment before work when feasible; treat conductors as energized until verified otherwise.

  • For electrical injury, call 911, use CPR or an AED as needed, and do not touch a victim who may still be energized.