MD MHIC Contractor study materials
MD MHIC Contractor study resources

MD MHIC Contractor cheat sheet

MD MHIC Contractor · Keep the key ideas within reach.

Quick reference

Home Improvement Work Scope and Contract Requirements

  • Covered work: repair, replacement, remodeling, alteration, conversion, modernization, improvement, rehabilitation, or addition to a residence or lot, including driveways, swimming pools, porches, garages, roofs, siding, insulation, and landscaping tied to the improvement.

  • A home improvement contract must be written, signed by the owner and the contractor, and dated; it must identify the contractor's MHIC license number and the owner's name and address of the property.

  • Required contract content includes a description of the work, materials and equipment to be used, total contract price, deposit and payment schedule, start and completion dates, and notice of the owner's right to cancel.

  • Maryland's Door-to-Door Sales Act gives a 3-business-day right to cancel for contracts solicited at the buyer's home; the contract must state this right and include a cancellation form.

  • A contract must include a statement of the buyer's right to file a complaint with MHIC and the phone number, plus a statement about the Guaranty Fund's existence and purpose.

  • Changes to a signed contract must be in writing and signed by both parties before the changed work is performed; oral modifications are not enforceable against the owner.

  • A contractor may not demand or receive a deposit exceeding one-third of the contract price before any work is performed, unless the contractor posts a surety bond or the contract is for a specific purpose exempted.

  • Contractors must provide a written warranty statement if any warranty is offered; if no warranty is offered, the contract must state that the contractor makes no warranty.

  • Completion date and payment schedule must be tied to identifiable milestones or dates; open-ended "time and materials" terms without a cap or schedule are a common contract deficiency.

Quick reference

Maryland Home Improvement Law and Regulations

  • MHIC operates under the Maryland Home Improvement Law, Business Regulation Article, Title 8, and adopts regulations in COMAR Title 9, Subtitle 30.

  • "Home improvement contractor" includes persons who sell, install, or perform home improvement work, and subcontractors; a person who only sells must still be licensed.

  • Unlicensed contracting is a misdemeanor; MHIC may issue a citation and fine, and the contractor may not sue to collect compensation for unlicensed work.

  • MHIC may suspend, revoke, or refuse to renew a license for violations including abandonment, substantial misrepresentation, failure to perform, and failure to pay Guaranty Fund awards.

  • A contractor must respond to an MHIC complaint within the time set by MHIC; failure to respond is itself a ground for disciplinary action.

  • MHIC may order a contractor to pay restitution to an injured owner; the order is enforceable and unpaid orders can lead to license suspension and Guaranty Fund claims.

  • Advertising must include the contractor's MHIC license number; unlicensed persons may not advertise or hold themselves out as home improvement contractors.

  • Contractors must maintain records of contracts, invoices, and payments for at least 3 years after completion, and make them available to MHIC investigators on request.

  • MHIC inspections and investigations may be conducted without a warrant on the contractor's business premises; contractors must cooperate and produce records.

Quick reference

Guaranty Fund and Claims Process

  • The Home Improvement Guaranty Fund reimburses owners who obtain a final, unappealed MHIC order or a court judgment against a licensed contractor for actual loss caused by the contractor's violation.

  • The claimant must exhaust administrative remedies first: file an MHIC complaint, obtain a final order, and show the contractor has not paid; a court judgment must also be final and unsatisfied.

  • A claim must be filed on MHIC's form within the time set by regulation after the final order or judgment, and must include documentation of the loss and the unpaid amount.

  • Recoverable losses are actual damages, including unpaid deposits and the cost of correcting defective work, but not punitive damages, attorney's fees, or consequential damages.

  • The Fund pays a claim only after the contractor fails to pay within the time ordered; MHIC then pays the award and the contractor must reimburse the Fund plus interest.

  • A contractor whose license is suspended for failing to reimburse the Fund may not be relicensed until the Fund is repaid in full, with interest and costs.

  • The Fund has a per-claim and per-contractor cap set by statute; awards above the cap are not paid from the Fund, and the claimant may pursue the contractor for the balance.

  • A Guaranty Fund claim is not a substitute for a civil action; filing a claim does not stay the claimant's right to sue, but the claimant may not recover twice for the same loss.

  • MHIC may deny a claim if the claimant failed to cooperate, submitted false information, or the loss was not caused by the contractor's licensed home improvement activity.

Quick reference

Licensing, Insurance, and Business Practices

  • An applicant must pass the MHIC exam, provide proof of general liability insurance of at least $50,000 per occurrence, and pay the license fee; licenses are renewed every 2 years.

  • A contractor must be licensed before advertising, contracting, or performing home improvement work; a license is not transferable and applies only to the named person or entity.

  • A licensed contractor must display the MHIC license number on all contracts, bids, and advertisements, and must carry the license or a copy when performing work.

  • General liability insurance is required to be maintained in force during the license term; a lapse must be reported to MHIC and can result in suspension.

  • A contractor must maintain a business address and notify MHIC within 10 days of a change of name, address, or ownership structure.

  • A contractor may not use a contract that waives the owner's right to file a complaint with MHIC or to recover from the Guaranty Fund; such clauses are void.

  • A contractor may not perform work outside the scope stated in the contract, and may not use subcontractors who are not licensed; the contractor is responsible for subcontractor compliance.

  • Commingling or misappropriation of owner funds held for materials or subcontractors is a ground for discipline; funds must be used for the project for which they were received.

  • A contractor must provide a written estimate or proposal before work begins if the owner requests one, and may not charge for a written estimate unless the charge is disclosed in advance.