The Michigan Fire Sprinkler Contractor License Examination is the assessment step for individuals and business entities seeking state authorization to design, install, maintain, or alter fire sprinkler systems in Michigan. It is aimed at contractors, journeypersons, and business owners who already have field experience with automatic sprinkler systems and now need to demonstrate code and administrative competence. The exam spans six content areas: fire sprinkler system design and installation standards, Michigan fire safety rules and administrative code, contractor licensing law and business practices, water supply analysis and hydraulic calculations, inspection/testing/maintenance, and plans, permits, and plan review procedures. Expect a mix of code-based questions, hydraulic problem-solving, and scenario items about plan submittal and inspection workflows. The MI Fire Sprinkler case studies are 5 cases and about 2,041 words.
1Five-Story Hotel Proposed With NFPA 13R
A design-build team submits a preliminary plan for a new five-story, 90,000 ft² hotel of Type III-A construction. The highest occupied floor is 64 ft above grade; the roof is 72 ft.
486 words, about 2 min2Office Building Water Supply Shortfall
A two-story, 20,000 ft² office building is proposed with an NFPA 13 wet-pipe system. The sprinkler contractor classifies the occupancy as Ordinary Hazard Group 2 and calculates a 1,500 ft² remote area at 0.20 gpm/ft².
387 words, about 2 min3Wet-Pipe Internal Inspection and Main Drain Deterioration
A 10-year-old wet-pipe system protects a six-story office building. Annual inspection reports are complete, but the owner cannot produce records of any internal pipe inspection.
317 words, about 2 min4Unlicensed Sprinkler Alteration in a Restaurant Tenant Space
A property management company renovates a 4,000 ft² restaurant tenant space in a Michigan strip mall. The work adds a suspended ceiling and moves 18 existing sprinkler heads; two new heads are added in a walk-in cooler.
411 words, about 2 min5ESFR Warehouse Plan Review: Clearance and Supply
A 100,000 ft² single-story warehouse has a 36 ft ceiling and is proposed for 34 ft high-piled storage of Group A plastics in cartons. The design uses ESFR K-25.2 sprinklers at 52 psi and 12 sprinklers in the remote area.
440 words, about 2 min