MN Journeyman Electrician · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

General Electrical Knowledge and Theory

  • Define voltage, current, resistance, and power and state the unit and symbol for each without notes

  • Apply Ohm's law and the power wheel to solve 20 mixed-series DC calculations with at least 90% accuracy

  • Compute series, parallel, and combination circuit equivalent resistance and branch currents for 10 circuits

  • Build a personal formula sheet limited to one page covering Ohm's law, power, impedance, and three-phase relationships

Your checkpoint

A scored 20-problem DC circuit worksheet (solutions shown) plus the one-page formula sheet, both dated

Week 2

General Electrical Knowledge and Theory

  • Explain alternating current behavior including frequency, phase, and the effect of inductance and capacitance on impedance

  • Calculate apparent, true, and reactive power and power factor for three single-phase loads

  • Convert between single-phase and three-phase values using line and phase relationships for wye and delta connections

  • Interpret Article 220 load calculation language for dwelling and non-dwelling occupancies and work three sample calculations

Your checkpoint

A written comparison table of wye versus delta line/phase relationships plus three completed Article 220 load calculations with cited sections

Week 3

Wiring Methods and Materials

  • Identify the Chapter 3 article that governs each of eight common wiring methods (NM, AC, MC, EMT, IMC, RMC, PVC, LFMC) and note the permitted and prohibited uses

  • Determine conductor ampacity adjustments for ambient temperature and more than three current-carrying conductors in a raceway using the applicable tables

  • Select box sizes and compute box fill for at least six scenarios including device and equipment-grounding fill

  • Specify support, securing, and bend-radius requirements for the eight wiring methods studied

Your checkpoint

A wiring-method selection matrix covering eight methods with permitted uses, prohibited uses, support spacing, and cited section numbers

Week 4

Wiring Methods and Materials & Branch Circuits, Feeders, and Services

  • Compute minimum conductor ampacity and overcurrent sizing for ten branch circuits across receptacle, lighting, appliance, and motor loads

  • Apply the small-appliance, laundry, and bathroom branch-circuit requirements to a sample dwelling layout

  • Size feeders and service conductors for a single-family dwelling using the standard and optional calculation methods

  • Verify each answer against the code section and record where the calculation came from

Your checkpoint

A full dwelling service and feeder calculation package including panel schedule, load summary, and section citations

Week 5

Branch Circuits, Feeders, and Services & Overcurrent Protection, Grounding, and Bonding

  • Differentiate grounded conductor, grounding electrode conductor, equipment grounding conductor, and bonding jumper and locate each requirement

  • Select the correct overcurrent device type and rating for ten scenarios involving motors, transformers, and standard branch circuits

  • Size equipment grounding conductors and grounding electrode conductors for six services using the applicable tables

  • Explain the difference between the grounded conductor and the equipment grounding conductor at the service and at subpanels

Your checkpoint

A grounding and bonding diagram set for a service and two subpanels, each labeled with the required conductor size and code section

Week 6

Overcurrent Protection, Grounding, and Bonding & Motors, Transformers, and Special Equipment

  • Perform motor branch-circuit, feeder, and overload calculations for three sample motors using the applicable tables and correction factors

  • Size disconnects, short-circuit protection, and overload protection for those three motors and justify each choice

  • Calculate transformer primary and secondary conductor and overcurrent protection sizing for two dry-type transformers

  • Identify the special equipment rules that apply to at least four common installations such as HVAC, pools, or signs

Your checkpoint

A motor and transformer calculation packet with three motor schedules and two transformer schedules, each fully cited

Week 7

Motors, Transformers, and Special Equipment & Minnesota Electrical Code Amendments and Licensing Rules

  • Summarize the Minnesota amendments that differ from the national model code and note how each changes an installation decision

  • Explain Minnesota licensing, continuing education, and code-adoption rules relevant to a journeyman

  • Work 40 timed practice questions weighted to the exam domain percentages and log each miss by domain

  • Re-study the two weakest domains using the error log rather than rereading whole chapters

Your checkpoint

A timed 40-question practice set score report with a domain-by-domain error log and a one-page Minnesota amendments summary

Week 8

General Electrical Knowledge and Theory & Wiring Methods and Materials & Branch Circuits, Feeders, and Services & Overcurrent Protection, Grounding, and Bonding & Motors, Transformers, and Special Equipment & Minnesota Electrical Code Amendments and Licensing Rules

  • Complete two full-length timed practice exams under test-day conditions and score each

  • Drill every missed question to the underlying code section until the concept is explainable in one sentence

  • Review the one-page formula sheet, wiring matrix, and Minnesota amendments summary for recall without references

  • Finalize a test-day plan covering allowed references, tab placement, and time allocation per question

Your checkpoint

Two scored full-length practice exams with a final error log showing every domain at or above 75% accuracy

Milestones

Week 2: Score at least 85% on a closed-book theory quiz covering Ohm's law, power, impedance, and three-phase relationships, and correctly complete three Article 220 load calculations

Week 4: Produce a dwelling service calculation that matches the answer key within one standard conductor size on every element, with each step cited

Week 6: Score at least 80% on a 30-question mixed set covering grounding, bonding, motors, and transformers, with no more than two misses in any single domain

Week 8: Score at least 75% overall on both full-length practice exams with every domain at or above 70% and the two heaviest domains at or above 80%